Hue terminates contract for bidding package worth over 114 billion VND due to slow progress

PHÚC ĐẠT |

HUE - The contractor of the Vy Da bridge project was terminated after many warnings of slow progress.

On April 18, the Investment Project Management Board of the Program for Development of Grade II Cities (Green Cities) - Thua Thien Hue sub-project announced that it had issued a decision to terminate the construction contract for package No. 28 (HU-CW07) with Hoa Binh 479 Joint Stock Company (Nghe An).

The bidding package includes items to upgrade and expand Vy Da bridge and the 100m road connecting urban areas A and B of An Van Duong area (bridge over Nhu Y river). The construction contract signed on June 4, 2021 and 9 related appendices were all terminated.

According to the investor, the construction value of the bidding package is more than 114 billion VND, but by March 31, nearly 79.8 billion VND had been disbursed, reaching about 69.93%. The construction progress does not meet the requirements according to the contract and signed commitments.

During the implementation process, the Project Management Board issued 12 documents warning of slow progress and 4 documents warning of serious contract violations, requesting contractors to rectify, but no results were achieved.

Notably, from mid-January to March 20, the contractor did not mobilize manpower and materials to construct the main items such as the bridge part, casting girder T33 of Vy Da bridge, sidewalks, railings and signage system at Nhu Y bridge.

The Project Management Board determined that the contractor seriously violated construction obligations, arbitrarily stopped construction for a long time, and did not ensure the capacity to continue project implementation.

Previously, on March 26, Hue City People's Committee agreed on the policy of terminating the contract for this bidding package.

According to the investor, the remaining workload will be processed according to the contract terms to implement the next steps, ensuring the overall progress of the project.

PHÚC ĐẠT
RELATED NEWS

Contractor requests postponement of nearly 200 billion VND project in Hue but is not approved

|

HUE - The contractor for the Culture and Sports Square Project worth nearly 200 billion VND proposed to extend the progress due to difficulties arising, but the investor did not approve.

Nhu Y riverside pedestrian street project littered with garbage and weeds

|

HUE - The Nhu Y riverside pedestrian road project has piles of garbage, weeds grow lushly, and many unfinished items due to site clearance problems have prolonged progress.

Nearly 5 years of construction, Vy Da bridge in Hue is still unfinished

|

Vy Da bridge, belonging to a type II urban development project in Hue City, has not been completed after nearly 5 years of construction, the volume has only reached about 67%, causing the contractor to be fined more than 1.5 billion VND for violating the progress.

Ho Chi Minh City People's Committee headquarters nearly 120 years old will become a tourist attraction

|

Ho Chi Minh City - The headquarters of the People's Council - People's Committee of Ho Chi Minh City on Le Thanh Ton Street (nearly 120 years old) will be preserved and exploited as a tourist and educational destination.

Hanoi Party Secretary sets deadline for completion of "most expensive road on the planet

|

Hanoi - Regarding the progress of the Ring Road 1 project (Hoang Cau - Voi Phuc section), the Hanoi Party Secretary requested to complete the entire roadbed before September 2, 2026; complete the construction of 2 overpasses on the route before December 31, 2026.

Hanoi Traffic Police show trainees videos of accidents before driving test

|

Hanoi - Before the test, traffic police show trainees videos recording serious traffic accidents, thereby making them more aware of their responsibilities when holding the steering wheel.

Complete the installation of medical equipment at facility 2 of Bach Mai and Viet Duc Hospitals before June 30

|

Ninh Binh - The investor of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 project committed to complete the installation of equipment before June 30.

Salary reform from the Central to local levels, implemented in all 3 blocs

|

The Ministry of Home Affairs is assigned to carefully prepare the reform of salaries, allowances and other regimes from the Central to local levels, implemented in all 3 blocs.

Contractor requests postponement of nearly 200 billion VND project in Hue but is not approved

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - The contractor for the Culture and Sports Square Project worth nearly 200 billion VND proposed to extend the progress due to difficulties arising, but the investor did not approve.

Nhu Y riverside pedestrian street project littered with garbage and weeds

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - The Nhu Y riverside pedestrian road project has piles of garbage, weeds grow lushly, and many unfinished items due to site clearance problems have prolonged progress.

Nearly 5 years of construction, Vy Da bridge in Hue is still unfinished

PHÚC ĐẠT- NGUYỄN LUÂN |

Vy Da bridge, belonging to a type II urban development project in Hue City, has not been completed after nearly 5 years of construction, the volume has only reached about 67%, causing the contractor to be fined more than 1.5 billion VND for violating the progress.