Resettlement area not completed after 4 years, landslides threaten people

Đinh Đại |

Lao Cai - After 4 years of planning the resettlement area of ​​Lao Vang village, people living in the area at high risk of landslides have not yet been relocated.

Unfinished resettlement area 21 billion VND

In late September 2024, in Phin Ngan commune, Bat Xat district, Lao Cai province - according to the reporter of Lao Dong Newspaper, the road leading to the villages appeared many landslides.

This greatly affects people's movement and is potentially dangerous, especially at night because one side of the road is a landslide and the other side is a deep abyss.

Nhieu diem sat lo tren tuyen duong dan vao thon Lao Vang (xa Phin Ngan, huyen Bat Xat, tinh Lao Cai) khien viec di chuyen cua nguoi dan them phan kho khan va nguy hiem. Anh: Dinh Dai
Many landslides on the road leading to Lao Vang village, Phin Ngan commune, make people's movement more difficult and dangerous. Photo: Dinh Dai

The most serious situation is in Lao Vang village of Phin Ngan commune, where dozens of households are living and are at risk of landslides due to storms and floods, with danger lurking.

Through research, households of Lao Vang village are currently included in the project to relocate residents from the disaster area of ​​Bat Xat district.

The project covers an area of ​​11.6 hectares, arranging for 70 resettled households with a total cost of more than 21.2 billion VND, implemented in the period of 2023-2025. The investor is the Bat Xat District Construction Investment Project Management Board.

The purpose of the project is to build concentrated rural residential areas to relocate households affected by natural disasters such as storms, floods, and landslides, stabilize people's lives, and develop the socio-economy in the area.

Vi tri quy hoach xay tai dinh cu cho ba con thon Lao Vang tu nam 2020, nhung den nam 2024 moi duoc bo tri von de trien khai. Anh: Dinh Dai
The planned location for resettlement construction for Lao Vang villagers was from 2020, but capital was only allocated for implementation in 2024. Photo: Dinh Dai

Mr. Vang Van San (local resident) said: “We have lived here for decades. Landslides have occurred many times, affecting households in the village. However, up to now, people are still waiting to rebuild while continuing to live in anxiety."

According to Mr. San, the resettlement area of ​​Lao Vang village was planned 3-4 years ago. Construction only started this year but it is not yet completed and has only stopped at building a clean water tank.

Be nuoc cua khu tai dinh cu duoc dat canh diem truong mam non cua thon Lao Vang. Anh: Dinh Dai
Up to now, the resettlement area has only built a water tank near the Lao Vang village kindergarten. Photo: Dinh Dai

“We want to move to a new place, but the project has not been implemented yet so we cannot go. We hope that the construction unit will quickly level the ground and install an electrical system so that the households can soon move out of the area at risk of landslides,” said Mr. San.

Many years of immobility due to lack of capital

Ms. Chao Thi May (residing in Lao Vang village, Phin Ngan commune) also said: "During the recent flood, there were many landslides in the commune, fortunately there were no human casualties. However, the traffic infrastructure system was eroded and broken, making it extremely difficult for people to travel."

According to Ms. May, many households in the commune always have to live in fear because of the risk of landslides that threaten their lives at any time. The resettlement project was planned for people to move to, but now it is nowhere to be seen.

Hang chuc ho dan o thon Lao Vang, xa Phin Ngan (Bat Xat, Lao Cai) dang phai doi mat voi sat lo moi khi mua lu ve. Anh: Dinh Dai
Dozens of households in Lao Vang village, Phin Ngan commune (Bat Xat, Lao Cai) are facing landslides every time there is heavy rain and floods. Photo: Dinh Dai

Regarding this issue, the Chairman of the People's Committee of Phin Ngan - Vang Lao Lo commune informed: The resettlement area in Lao Vang village is invested by the Bat Xat district Construction Investment Project Management Board. The project was planned since June 2020, but has been stagnant for many years due to lack of capital.

In 2023, the project will receive funding from the National Target Program. According to the plan, construction will start on September 12, but it happened right at the time of the flood, the traffic infrastructure in the commune was heavily eroded, so up to now, the machinery has not been able to be deployed.

Mat bang lam tai dinh cu cach vi tri cu noi cac ho dan dang o khoang hon 1km. Anh: Dinh Dai
The resettlement site is about 1km away from the old location where the households are living. Photo: Dinh Dai

According to the Chairman of the People's Committee of Phin Ngan Commune, during the recent flood, the government mobilized human resources to move households to safe shelters. However, the infrastructure and traffic system were seriously eroded, and a suspension bridge was completely damaged.

“We are also very impatient. Currently, the water system of the resettlement area is almost completed. If the weather is favorable, the construction unit will transport machinery to level the ground and install the electrical system. It is expected to be completed by the end of this year to welcome residents,” Mr. Vang Lao Lo added.

Dat da sat lo, duong xa dut gay trong nhung ngay mua bao dau thang 9. Anh: Dinh Dai
Landslides and broken roads during the stormy days of early September. Photo: Dinh Dai

On the morning of September 28, speaking with Lao Dong Newspaper reporters, Mr. Vu Van Sinh - Director of Bat Xat District Construction Investment Project Management Board - said: The project was planned and proposed since 2020 but there was no budget for implementation. It was not until the end of 2023 that it was included in the National Target Program for capital allocation.

“During the flood in early September, Bat Xat district suffered a lot of damage, the transport infrastructure to the communes was eroded and broken, so we could not transport machinery to work. The cracked road leading to Phin Ngan commune was also related to the hydropower plant, because that side is waiting for insurance.

If the weather is dry, we will repair the access road and strive to complete the site and electricity and water systems to hand over to the people by the end of this year," affirmed the Director of the Bat Xat District Construction Investment Project Management Board.

Đinh Đại
RELATED NEWS

All vehicles trapped on Gia Bac Pass in Lam Dong have been rescued

|

Lam Dong - After many efforts, the rescue forces have cleared the landslides on Gia Bac Pass, and many vehicles are being rescued.

Vietnam table tennis team practices with Russia

|

The players of the Vietnam Table Tennis Team were rubbed off before the 33rd SEA Games with the Russian Federation team.

Mr. Putin affirmed that Russia has no intention of returning to G8

|

President Putin affirmed that Russia has no intention of returning to the G8, and highly appreciated the strong rise of the Indian economy.

Preparing for the peak of the dry season, the Lo River begins to dry up

|

Tuyen Quang - Although not yet the peak of the dry season, many upstream areas of the Lo River have begun to dry up, exposing underground rock covers.

Another deep flooding point on National Highway 1 through Lam Dong

|

Lam Dong - Floodwaters caused deep flooding at km1700 of National Highway 1, causing traffic congestion.

The BT project of La Vong Group was once clarified for violations

|

Regarding the BT project invested by a company under La Vong Group, the Government Inspectorate has pointed out many violations.

Live football Nam Dinh vs Shan United in the Southeast Asian Cup C1

|

Live match between Nam Dinh and Shan United in the Southeast Asian Cup C1, taking place at 6:30 p.m. today (December 4).

33rd SEA Games and the expectation of a generation transfer of Vietnamese sports

|

Vietnamese sports are entering an important SEA Games period, where young people are expected to continue the success of the previous golden generation.

70 billion VND spiritual symbol under construction in Lao Cai

Đinh Đại |

Lao Cai - After about 10 months of construction, the Kim Thanh Tower project in the border province of Lao Cai has taken shape.

Lao Cai's 100 billion dong road misses finish line due to iron ore discovery

Đinh Đại |

Lao Cai - After 1 year of implementation, the road connecting Provincial Road 151 with Noi Bai - Lao Cai Expressway with a total investment of 115 billion VND could not be completed on time due to the discovery of iron ore.

The People's Petition Committee speaks out about the sky-high resettlement land prices

TẠ QUANG |

The People's Petition Committee (National Assembly Standing Committee) has forwarded the citizen's petition to the Chairman of the Can Tho City People's Committee for consideration and direction on the settlement of resettlement land prices.