How far have violations at the Ha Dinh new urban area project been remedied?

Nhóm Phóng viên |

As Lao Dong reported, the investor of the Ha Dinh new urban area project lost the basic drawings and delayed the construction of social housing, kindergartens, and medical examination areas.

Accordingly, in January 2024, the Department of Construction inspected and clarified responsibilities at this project, as well as issued conclusions with many requirements that needed to be overcome.

According to the Inspectorate of Hanoi Department of Construction, at the time of inspection, the investor did not provide basic design drawings attached to document No. 1294/SXD-TD dated March 1, 2013.

At the time of inspection, some kindergarten and medical examination areas had not been built.

The fact that the investor has not fully fulfilled the obligations of the inspected subject by not providing complete records and documents as requested is a violation of the provisions of Clause 2, Article 93 of the Law on Inspection 2022.

Regarding the project's progress, the Construction Department Inspectorate said that, up to now, the investor has not invested in building social infrastructure works.

The Inspectorate concluded that the responsibility for the delay in implementing the social housing project at land plot N01 belongs to the joint venture investor: UDIC Construction Investment Corporation - Hanoi Electricity and Water Construction Joint Stock Company, and DAC Hanoi Housing Development and Construction Joint Stock Company.

Based on clarifying the responsibilities of the parties, the Inspectorate of the Hanoi Department of Construction requested administrative sanctions against the investor, Haweico Construction and Installation Joint Stock Company, for the act of incompletely storing the list of documents with a fine of 30 million VND. The remedial measure is to force the complete list of archived documents to be supplemented.

The Inspectorate also recommended a fine of VND140 million for the UDIC Construction Investment Corporation - Hanoi Electricity and Water Construction Joint Stock Company, and DAC Hanoi Housing Development and Construction Joint Stock Company for their slow progress in implementing social housing investment in Ha Dinh urban area.

The remedy is that within 30 days at the latest, the investor must start construction.

In addition, the Inspectorate also recommended that the Hanoi People's Committee direct departments, branches and sectors to consider the participation conditions of investors of this project when they propose to participate in other projects in Hanoi.

To learn about the process of overcoming the consequences, including supplementing drawings, starting construction and reviewing the investor's participation conditions for other projects in Hanoi, Lao Dong Newspaper reporters contacted the investor, UDIC Construction Investment Corporation and the Hanoi Department of Construction.

However, to date, the reporter has not received a response.

Nhóm Phóng viên
RELATED NEWS

Forecast in the North with very heavy rain due to cold air from tonight

|

Forecast for the North (except Lai Chau, Dien Bien) and North Central region to have rain, moderate rain and scattered thunderstorms, with very heavy rain in some places from tonight April 16 due to cold air.

Case of teacher punishing 5 students for self-injecting needles in their hands: Taking students for testing

|

Ho Chi Minh City - Regarding the case of a teacher punishing 5 students for self-injecting needles into their hands, on the 16th, the school is taking the children for testing.

Land acquisition of nearly 1,500 households in Ho Chi Minh City to build the largest road in the Southeast region

|

Ho Chi Minh City recovers land from about 1,500 households in Tan An Hoi and Nhuan Duc communes to build the Ho Chi Minh City Ring Road 4 project (section from Saigon River to Thay Cai canal).

Ha Anh Tuan participates in Sao Nhap Ngu concert with Hoa Minzy, Chi Pu

|

Sao Nhap Ngu concert 2026 - Tuoi Doi Muoi" quickly became the focus of attention when announcing the cast of participating artists, including the appearance of Ha Anh Tuan.

Stock market faces many challenges with the goal of reaching the 2,000 point threshold

|

The upward momentum of the stock market is being driven by large-cap stocks that have not yet spread to many sectors.

Early ripe Son La plums priced at up to 120 thousand VND still attract customers

|

Son La - Early ripe plums are a bumper crop, beautiful fruit, high prices, farmers are excited, traders come to the garden to buy, and the consumption market is vibrant.

Collecting people's opinions on the draft Political Report at the XI National Congress of the Vietnam Fatherland Front

|

The 11th National Congress of the Vietnam Fatherland Front, term 2026 - 2031 will take place from May 11-13 in Hanoi Capital. This is an important socio-political event taking place immediately after the success of the 14th National Congress of the Party and the election of National Assembly deputies of the 16th term, People's Councils at all levels for the term 2026 - 2031.

Ha Dinh social housing project is behind schedule, but land brokers are still selling it aggressively

Nhóm phóng viên |

Hanoi - The social housing project in Ha Dinh urban area has been behind schedule for many years, but land brokers are still advertising it on social networks.

Ha Dinh new urban area only has villas, no social infrastructure

Nhóm phóng viên |

Hanoi - After 20 years of launching, Ha Dinh new urban area has only "sprouted up" villas, without social infrastructure as announced.

Hiện trạng dự án nhà ở xã hội NO1 Hạ Đình xin gia hạn tiến độ sau xử phạt

NGỌC THÙY |

Sau khi Thanh tra Sở Xây dựng TP Hà Nội kiến nghị UBND TP Hà Nội ban hành Quyết định xử phạt chủ đầu tư dự án nhà ở xã hội tại khu đất NO1 Hạ Đình (thuộc khu đô thị mới Hạ Đình, xã Tân Triều, huyện Thanh Trì) về việc chậm khởi công công trình, đến nay, chủ đầu tư đã nộp phạt, đồng thời triển khai các thủ tục về đầu tư xây dựng cho dự án.