Lao Cai sprints to hand over the site for the billion-dollar railway project

Đinh Đại |

Lao Cai - Units are urgently preparing to ensure conditions to organize the groundbreaking ceremony for the railway line on December 19 as planned.

The Lao Cai - Hanoi - Hai Phong railway line was approved by the National Assembly in Resolution 187, with a total length of about 391km of main route and 28km of branch route, passing through six provinces and cities.

The route is designed with a scale of 1,435mm, a maximum speed of 160km/h on the main axis, 120km/h in the Hanoi area and 80km/h in the remaining sections.

The total preliminary investment is more than 203,000 billion VND (equivalent to 8.37 billion USD), implemented in 2 phases, of which phase 1 is to invest in a single road and site clearance according to the scale of a double road.

Tuyen duong sat Lao Cai-Ha Noi-Hai Phong du kien khoi cong vao ngay 19.12. Anh: Dinh Dai
The Lao Cai - Hanoi - Hai Phong railway line is expected to start construction on December 19. Photo: Dinh Dai

For the route through Lao Cai, which is more than 143km long, the total area of pre-feasibility land acquisition is about 1,397 hectares, involving 6,694 households.

The Lao Cai - Coc San Construction Investment Project Management Board said that by the end of November, the entire construction site had been handed over to the Railway Project Management Board to level and build infrastructure systems for the event.

This area is 6.8ha wide, belonging to Dong Pho Moi Industrial Park; of which 6.27ha was handed over before November 27.

Recorded on December 6, in Dong Pho Moi Industrial Park, a large area has been fenced off to prepare for the groundbreaking ceremony of the railway project on December 19.

Khu vuc chuan bi cho le khoi cong da duoc giai phong mat bang. Anh: Dinh Dai
The area preparing for the groundbreaking ceremony has been cleared. Photo: Dinh Dai

Component project 1 on infrastructure investment connecting stations and station squares of the railway line was approved by the Ministry of Construction on November 7 with a total amount of more than VND 3,347 billion.

According to the plan, the groundbreaking ceremony will be held simultaneously at five locations including Lao Cai, Phu Tho, Bac Hong, Luong Tai and Hai Duong Nam; in which the central bridge point will be at Lao Cai station.

In Lao Cai ward, immediately after receiving the deposit documents, the Lao Cai - Coc San Construction Investment Project Management Board coordinated to organize statistics and count households and production facilities within the affected area.

Tuyen duong sat se di qua 6 tinh thanh. Anh: Dinh Dai
The railway line will pass through 6 provinces and cities. Photo: Dinh Dai

Chairman of Lao Cai Ward People's Committee Nguyen Van Nhat said that the items are being implemented simultaneously, from determining resettlement locations, making compensation plans to approving and paying funds.

Some units in Dong Pho Moi Industrial Park are still stuck with property unit prices, the ward has hired consulting units to count, evaluate and complete the documents.

During the process of completing the site, production facilities in the area that must be relocated are being inventoried and support plans are being prepared according to regulations.

Mot so co so san xuat cong nghiep se phai di doi de phuc vu viec thi cong du an duong sat. Anh: Dinh Dai
Some industrial production facilities will have to be relocated to serve the construction of the railway project. Photo: Dinh Dai

Through research, the resettlement infrastructure in Bac Lao Cai includes 22 areas, of which 6 areas have cleared land, 4 areas are under construction and 12 areas are preparing for investment, expected to start construction from December to the first quarter of 2026.

The southern area has 16 resettlement areas, many of which have selected contractors and are ready to be deployed in December.

According to the updated documents in the feasibility report step, the number of resettlement areas is expected to decrease to 38. To date, the entire route has completed the measurement of 143.29km, counting 1,414 households, and issuing land reclamation notices to 577 households.

Phuong an thiet ke ga Lao Cai va ga Yen Bai. Anh: Tien Lap
Design plan of Lao Cai station and Yen Bai station. Photo: Tien Lap

At a recent meeting, Lao Cai Provincial Party Secretary Trinh Viet Hung requested the Steering Committee and related units to ensure full conditions on site, security, order, and traffic safety; at the same time, update daily progress and immediately handle arising issues.

The People's Committee of Lao Cai province requested the Railway Project Management Board to promptly hand over complete technical documents and site clearance milestones so that the locality can be proactive in compensation, support and resettlement.

Đinh Đại
RELATED NEWS

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

|

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.

Location of remaining stations of the Lao Cai - Hanoi - Hai Phong railway in October

|

The Prime Minister assigned the Ministry of Construction to work with 3 localities to agree on the route plan and location of the remaining stations of the Lao Cai - Hanoi - Hai Phong railway.

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

|

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.

Coast Guard Region 4 is a fulcrum for fishermen to go offshore and fight IUU fishing

|

An Giang - Coast Guard Region 4 not only propagates against IUU fishing but also supports and accompanies fishermen in many aspects when they exploit at sea.

From this morning, there will only be one lane on the La Son - Tuy Loan Expressway

|

From the morning of December 6, the Ho Chi Minh Road Project Management Board has implemented a temporary traffic organization plan on the La Son - Tuy Loan Expressway.

Police block off the area of a house fire in an alley that killed one person in Ho Chi Minh City

|

HCMC - A fire broke out at a house in alley 72, street No. 4, Hiep Binh ward, killing a 47-year-old man.

Water recedes, Lam Dong flood area urgently cleans houses

|

Lam Dong - Floodwaters have receded, people in flooded areas have returned home, urgently cleaned up and restored their lives.

Overnight rescue of fishermen after their boats sank

|

Quang Tri - During the night, two fishermen living in Bac Gianh ward had their boat sinking while fishing and drifting at sea.

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

Mai Hương |

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.

Location of remaining stations of the Lao Cai - Hanoi - Hai Phong railway in October

PHẠM ĐÔNG |

The Prime Minister assigned the Ministry of Construction to work with 3 localities to agree on the route plan and location of the remaining stations of the Lao Cai - Hanoi - Hai Phong railway.

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

PHẠM ĐÔNG |

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.