Lao Cai sprints to hand over the site for the billion-dollar railway project

Đinh Đại |

Lao Cai - Units are urgently preparing to ensure conditions to organize the groundbreaking ceremony for the railway line on December 19 as planned.

The Lao Cai - Hanoi - Hai Phong railway line was approved by the National Assembly in Resolution 187, with a total length of about 391km of main route and 28km of branch route, passing through six provinces and cities.

The route is designed with a scale of 1,435mm, a maximum speed of 160km/h on the main axis, 120km/h in the Hanoi area and 80km/h in the remaining sections.

The total preliminary investment is more than 203,000 billion VND (equivalent to 8.37 billion USD), implemented in 2 phases, of which phase 1 is to invest in a single road and site clearance according to the scale of a double road.

Tuyen duong sat Lao Cai-Ha Noi-Hai Phong du kien khoi cong vao ngay 19.12. Anh: Dinh Dai
The Lao Cai - Hanoi - Hai Phong railway line is expected to start construction on December 19. Photo: Dinh Dai

For the route through Lao Cai, which is more than 143km long, the total area of pre-feasibility land acquisition is about 1,397 hectares, involving 6,694 households.

The Lao Cai - Coc San Construction Investment Project Management Board said that by the end of November, the entire construction site had been handed over to the Railway Project Management Board to level and build infrastructure systems for the event.

This area is 6.8ha wide, belonging to Dong Pho Moi Industrial Park; of which 6.27ha was handed over before November 27.

Recorded on December 6, in Dong Pho Moi Industrial Park, a large area has been fenced off to prepare for the groundbreaking ceremony of the railway project on December 19.

Khu vuc chuan bi cho le khoi cong da duoc giai phong mat bang. Anh: Dinh Dai
The area preparing for the groundbreaking ceremony has been cleared. Photo: Dinh Dai

Component project 1 on infrastructure investment connecting stations and station squares of the railway line was approved by the Ministry of Construction on November 7 with a total amount of more than VND 3,347 billion.

According to the plan, the groundbreaking ceremony will be held simultaneously at five locations including Lao Cai, Phu Tho, Bac Hong, Luong Tai and Hai Duong Nam; in which the central bridge point will be at Lao Cai station.

In Lao Cai ward, immediately after receiving the deposit documents, the Lao Cai - Coc San Construction Investment Project Management Board coordinated to organize statistics and count households and production facilities within the affected area.

Tuyen duong sat se di qua 6 tinh thanh. Anh: Dinh Dai
The railway line will pass through 6 provinces and cities. Photo: Dinh Dai

Chairman of Lao Cai Ward People's Committee Nguyen Van Nhat said that the items are being implemented simultaneously, from determining resettlement locations, making compensation plans to approving and paying funds.

Some units in Dong Pho Moi Industrial Park are still stuck with property unit prices, the ward has hired consulting units to count, evaluate and complete the documents.

During the process of completing the site, production facilities in the area that must be relocated are being inventoried and support plans are being prepared according to regulations.

Mot so co so san xuat cong nghiep se phai di doi de phuc vu viec thi cong du an duong sat. Anh: Dinh Dai
Some industrial production facilities will have to be relocated to serve the construction of the railway project. Photo: Dinh Dai

Through research, the resettlement infrastructure in Bac Lao Cai includes 22 areas, of which 6 areas have cleared land, 4 areas are under construction and 12 areas are preparing for investment, expected to start construction from December to the first quarter of 2026.

The southern area has 16 resettlement areas, many of which have selected contractors and are ready to be deployed in December.

According to the updated documents in the feasibility report step, the number of resettlement areas is expected to decrease to 38. To date, the entire route has completed the measurement of 143.29km, counting 1,414 households, and issuing land reclamation notices to 577 households.

Phuong an thiet ke ga Lao Cai va ga Yen Bai. Anh: Tien Lap
Design plan of Lao Cai station and Yen Bai station. Photo: Tien Lap

At a recent meeting, Lao Cai Provincial Party Secretary Trinh Viet Hung requested the Steering Committee and related units to ensure full conditions on site, security, order, and traffic safety; at the same time, update daily progress and immediately handle arising issues.

The People's Committee of Lao Cai province requested the Railway Project Management Board to promptly hand over complete technical documents and site clearance milestones so that the locality can be proactive in compensation, support and resettlement.

Đinh Đại
RELATED NEWS

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

|

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.

Location of remaining stations of the Lao Cai - Hanoi - Hai Phong railway in October

|

The Prime Minister assigned the Ministry of Construction to work with 3 localities to agree on the route plan and location of the remaining stations of the Lao Cai - Hanoi - Hai Phong railway.

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

|

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.

An Giang effectively mobilizes all resources for rapid development, joining the whole country in entering a new era

|

With GRDP growth rate in 2025 reaching 8.39%, leading the Mekong Delta region, An Giang province is showing strong momentum after merging to implement the 2-level local government model. To realize the aspiration to make the province one of the bright spots of the whole country in the new era, An Giang has been and is focusing all resources on strategic economic pillars such as the marine economy, tourism and logistics infrastructure.

Minister Nguyen Manh Hung: Science and technology, innovation elevate Vietnam's position in the new era

|

On the occasion of the 14th National Party Congress - an important milestone opening a new stage of development for the country, Minister of Science and Technology Nguyen Manh Hung shared about the role of science and technology, innovation and digital transformation in becoming the central driving force for rapid and sustainable development of Vietnam.

Minister of Justice Nguyen Hai Ninh: Resolution No. 66-NQ/TW is truly a "call to action" for a profound institutional reform

|

On April 30, 2025, the Politburo issued Resolution No. 66-NQ/TW on innovating the work of building and enforcing laws to meet the requirements of national development in the new era. The results of implementing Resolution No. 66-NQ/TW to date have created clear changes with many breakthroughs in building and perfecting institutions and laws, meeting the requirements of national development. On the occasion of the 14th Party Congress, Member of the Party Central Committee, Minister of Justice Nguyen Hai Ninh had an exchange with the press about the achievements in nearly 1 year of implementing Resolution No. 66-NQ/TW.

Looking towards the 14th Party Congress, Can Tho is brilliant with flags, flowers, and banners

|

Can Tho - Heading towards the 14th Party Congress, many central streets of Can Tho are brilliant with flags, flowers, and banners, creating a solemn and exciting atmosphere.

Mobile Police Commander inspects combat readiness to protect the 14th Party Congress

|

Hanoi - Mobile Police Commander inspects on-duty work, combat readiness at key targets, ensuring absolute security for the 14th Party Congress.

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

Mai Hương |

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.

Location of remaining stations of the Lao Cai - Hanoi - Hai Phong railway in October

PHẠM ĐÔNG |

The Prime Minister assigned the Ministry of Construction to work with 3 localities to agree on the route plan and location of the remaining stations of the Lao Cai - Hanoi - Hai Phong railway.

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

PHẠM ĐÔNG |

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.