Series of transportation projects in Lao Cai due for completion in 2025

Đinh Đại |

The trillion-dong road connecting Lao Cai - Lai Chau, along with a series of transport infrastructure projects with hundreds of billions of dong invested, will have to be completed in 2025.

Project to upgrade National Highway 279 connecting Lai Chau with Noi Bai - Lao Cai Expressway

The project to connect the northern mountainous provinces with the Noi Bai - Lao Cai expressway is funded by the Asian Development Bank and the Australian Government.

The project consists of two connecting routes, of which route 1 is 147 km long, connecting Lai Chau with the Hanoi - Lao Cai highway. Route 2 is about 53 km long, connecting Nghia Lo town (Yen Bai) with the Hanoi - Lao Cai highway.

The project is invested by the Ministry of Transport, with a total investment of VND 6,018.1 billion. The implementation period is from 2021-2024.

Don vi thi cong duong noi cac tinh mien nui phia Bac, doan qua huyen Van Ban (Lao Cai). Anh: Dinh Dai
Construction unit of the road connecting the northern mountainous provinces, section passing through Van Ban district (Lao Cai). Photo: Dinh Dai

In mid-January 2025, according to the records of Lao Dong Newspaper reporters in Van Ban district, a series of workers, machines and equipment were working tirelessly.

A representative of Project Management Board 2 (Ministry of Transport) - said: "Both the investor and the contractor are coordinating to resolve difficulties and obstacles in the process of implementing the project. The construction progress is currently about 40% of the volume. It is expected that the entire route will be completed by June 30, 2025."

Project to renovate and upgrade Provincial Road 160

The project to renovate and upgrade Provincial Road 160, from National Highway 279 (in Xuan Hoa commune) to Xuan Thuong, Bao Yen district (Km41-Km63) has a total investment of 138 billion VND, invested by the Lao Cai Provincial Traffic Construction Investment Project Management Board.

According to research, the project will start construction at the end of 2023 and is expected to be completed and put into use in April 2025.

Tinh lo 160, doan tu Quoc lo 279 (thuoc dia phan xa Xuan Hoa) di Xuan Thuong, huyen Bao Yen, Lao Cai (Km41- Km63). Anh: Dinh Dai
Provincial Road 160, from National Highway 279 (in Xuan Hoa commune) to Xuan Thuong, Bao Yen district, Lao Cai (Km41-Km63). Photo: Dinh Dai

Actual records show that the upgrading and renovation work is still being carried out by workers. Contractors are currently constructing the roadbed, installing sewer systems at some points; completing the retaining walls; constructing bridges...

In mid-July 2024, during an inspection of key projects in the province, Vice Chairman of Lao Cai Provincial People's Committee Nguyen Trong Hai requested the locality to focus on removing difficulties and obstacles in site clearance. Implement solutions to propagate and mobilize people to promptly hand over the site to the construction unit.

Project to upgrade and renovate Ban Xeo - Y Ty road (Bat Xat district)

The project to renovate and upgrade the Ban Xeo - Den Sang - Y Ty road has a total length of 33.58 km, starting at the Can Ty intersection and ending at the intersection with Trinh Tuong - Y Ty road.

The project has a total investment of 200 billion VND from the central and local budgets. The Bat Xat District Construction Investment Project Management Board is the investor representative. Construction will start in early 2022 and will be completed and put into use in 2025.

Mot doan thuoc du an cai tao, nang cap duong Ban Xeo – Den Sang – Y Ty. Anh: Dinh Dai
A section of the project to renovate and upgrade the Ban Xeo – Den Sang – Y Ty road. Photo: Dinh Dai

Currently, workers and machinery are being deployed urgently to construct and complete the road.

Mr. Vu Van Sinh - Director of Bat Xat District Construction Investment Project Management Board said: "In 2025, a series of traffic projects in the district will be required to be completed. Therefore, the unit is urging contractors to take advantage of favorable weather to mobilize human resources and machinery to work."

Investment project to build Ring Road 2

Through research, the investment project to build Ring Road 2 (section DT 153 to the People's Committees of Na Hoi, Na Kim and Ta Chai communes) is invested by the People's Committee of Bac Ha district, with a capital of more than 300 billion VND.

Construction began in 2019 and was expected to be completed in 1,000 days. However, as of January 13, 2025, due to site clearance issues, the road is still under construction.

Tuyen duong vanh dai 2 tai Bac Ha se hoan thien vao giua nam 2025 sau khi duoc gia han thi cong. Anh: Dinh Dai
The second beltway in Bac Ha will be completed in mid-2025 after the construction period is extended. Photo: Dinh Dai

Regarding this issue, Mr. Ha Duc Thanh - Director of the Bac Ha District Construction Investment Project Management Board - said that the Ring Road 2 project has been extended and the completion date has been postponed to May 2025.

Đinh Đại
TIN LIÊN QUAN

42 Lao Cai students violated alcohol concentration in 2024

|

In 2024, Lao Cai authorities recorded and handled over 1,700 cases of students violating the provisions of the Road Traffic Law.

Panoramic view of the newly opened dry port industrial park in Lao Cai

|

Lao Cai - Dong Pho Moi Industrial Park in Lao Cai city has just been chosen as the location to open a dry port.

Accelerating site clearance for the 500kV Lao Cai - Vinh Yen project

|

The 500kV Lao Cai - Vinh Yen transmission line project will officially start construction in February 2025 and be completed and energized no later than September 2, 2025.

Hanoi's low-emission zone is not a "magic wand"

|

The Chairman of the Vietnam Clean Air Network said that low emission zones are not a magic wand in Hanoi's fight against pollution.

Disciplinary action against Vice Chairman of Binh Phuoc Provincial People's Committee

|

The Prime Minister decided to impose a disciplinary warning on Mr. Huynh Anh Minh, Vice Chairman of Binh Phuoc Provincial People's Committee.

2 Call Me by Fire concerts continue to sell out in 40 minutes

|

Call Me by Fire's two sold-out concerts in a short time continue to make miracles in Vietnamese showbiz.

Russia believes the US holds the key to shaping world order

|

With many countries around the world aligning their stance with the White House, Russia believes that the future world order will depend largely on the United States.

Deputy Director of Can Tho Police becomes Director of Soc Trang Police

|

Soc Trang - Colonel Tran Van Duong was transferred and appointed to the position of Director of Soc Trang Provincial Police.

42 Lao Cai students violated alcohol concentration in 2024

Đinh Đại |

In 2024, Lao Cai authorities recorded and handled over 1,700 cases of students violating the provisions of the Road Traffic Law.

Panoramic view of the newly opened dry port industrial park in Lao Cai

Đinh Đại |

Lao Cai - Dong Pho Moi Industrial Park in Lao Cai city has just been chosen as the location to open a dry port.

Accelerating site clearance for the 500kV Lao Cai - Vinh Yen project

NHÓM PV |

The 500kV Lao Cai - Vinh Yen transmission line project will officially start construction in February 2025 and be completed and energized no later than September 2, 2025.