Many localities in Hanoi urgently recover land to build roads worth more than 9,590 billion VND

SÓNG HỮU |

Hanoi - Many localities are urgently accelerating the progress of land acquisition and site clearance to expand National Highway 6, with a total capital of more than 9,590 billion VND.

The project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section passing through Phu Nghia commune has a length of about 7.8 km. The total area to be recovered for site clearance (GPMB) is 29.65 ha with 1,366 land plots.

According to Phu Nghia Commune People's Committee, in the last 2 days of the week (May 16, 17), in Phu Nghia commune, many households and individuals continued to dismantle works to hand over the site to the construction unit of the National Highway 6 expansion project, Ba La - Xuan Mai section.

In the area of villages: Doi 1, Doi 2, Doi 3 belonging to the old Dong Phuong Yen commune, there are a total of 314 households and individuals within the project site clearance area.

Recognizing the importance of the National Highway 6 expansion project for local development, nearly 200 households have agreed to hand over the site and so far nearly 60 households have dismantled the works and handed over the site.

d
People in Phu Nghia commune (Hanoi) dismantle works, move assets to hand over land for the National Highway 6 expansion project with a very urgent spirit. Photo: Kim Thoa

According to Phu Nghia Commune People's Committee, to date, the government has handed over to the investor over 86% of the total land area recovered for project implementation.

Local Party committees and authorities are highly focused on accelerating the site clearance progress and determined to complete the site clearance work for this key project in the second quarter of 2026.

The project to expand National Highway 6, Ba La - Xuan Mai section through Chuong My ward, has a length of 3.658 km, with a total recovered area of about 21.1 ha/814 land plots.

Chuong My Ward People's Committee said that on May 17, the ward continued to organize a conference to mobilize, dialogue, and receive opinions from households and individuals subject to site clearance to implement the National Highway 6 expansion project, Ba La - Xuan Mai section for households in Cao Son and Son Dong residential groups.

d
Chuong My ward dialogues and receives opinions from people in Cao Son and Son Dong residential groups to serve the National Highway 6 expansion project. Photo: Lan Oanh

The conference received 19 opinions from households, mainly focusing on proposing to review the origin of land, land compensation levels, resettlement support, resettlement arrangement conditions as well as the actual difficulties of households in the project implementation process...

Regarding the contents related to land prices, resettlement support and compensation plans, leaders of Chuong My ward said that the valuation, determination of land origin and development of compensation plans are carried out in accordance with State regulations, based on each location, current land use status and actual inventory results.

The resettlement land price is applied according to the land price list prescribed by the State for the locations of households eligible for resettlement by lottery.

Through the conference, many contents and recommendations of the people were answered, contributing to creating consensus in site clearance work, serving the implementation of the National Highway 6 expansion project, Ba La - Xuan Mai section in Chuong My ward.

d
Images of demolition of works, handover of land in Tan Binh village (Xuan Mai commune). Photo: Hoang Tinh

In Xuan Mai commune, the National Highway 6 expansion project is identified as an important traffic project, of great significance to the socio-economic development of the locality.

The project passing through the commune has a length of 6.53 km, affecting about 1,376 households and individuals. The total land area to be recovered is up to 38.58 ha with 1,804 land plots.

The Party Committee, Xuan Mai Commune People's Committee, the Steering Committee for Compensation, Support and Site Clearance regularly direct and urge progress; and at the same time continuously organize dialogues, propaganda, and mobilization to help agencies, units, organizations and people understand the meaning of the project, agree to hand over the site early to the investor for construction.

The project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section, has a total length of 21.7 km, passing through many communes and wards in Hanoi.

The project started construction at the end of 2022, with a total investment of more than 9,590 billion VND.

SÓNG HỮU
RELATED NEWS

Enforced land recovery to implement the project to upgrade Mang Nuoc road, Hai Phong

|

Hai Phong - On the morning of May 18, Thuy Nguyen ward organized coercive land recovery for the project to renovate and upgrade the Mang Nuoc road from the foot of Binh bridge connecting to road 359.

Enforced land recovery for a household in Hanoi to implement a project

|

Hanoi - Van Dinh Commune People's Committee is carrying out coercive land recovery for a household to implement a resettlement area construction project.

Deploying land recovery enforcement to implement the regulating lake project in Hanoi

|

Hanoi - Tu Liem Ward People's Committee has just held a meeting to deploy the work of coercive land recovery, serving the Phu Do regulating lake construction project.

Mud and dust overflow onto the Quang Ngai - Hoai Nhon expressway

|

Gia Lai - Muddy soil spills onto the road surface, dust arises in the construction area of Dinh Cuong rest stop on the Quang Ngai - Hoai Nhon expressway.

Ho Chi Minh City to pilot software for temporary management and use of roadways and sidewalks

|

Ho Chi Minh City - The Department of Construction proposes that the Ho Chi Minh City People's Committee approve the policy of piloting software to temporarily manage and use roadways and sidewalks in the city.

Strongly punish to prevent dangers at railway intersections

|

Hanoi - After the fine level increased sharply according to Decree 81/2026, the situation of crossing barriers and running red lights at railway intersections has decreased significantly.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Enforced land recovery to implement the project to upgrade Mang Nuoc road, Hai Phong

Hoàng Khôi |

Hai Phong - On the morning of May 18, Thuy Nguyen ward organized coercive land recovery for the project to renovate and upgrade the Mang Nuoc road from the foot of Binh bridge connecting to road 359.

Enforced land recovery for a household in Hanoi to implement a project

Anh Tuấn |

Hanoi - Van Dinh Commune People's Committee is carrying out coercive land recovery for a household to implement a resettlement area construction project.

Deploying land recovery enforcement to implement the regulating lake project in Hanoi

Anh Tuấn |

Hanoi - Tu Liem Ward People's Committee has just held a meeting to deploy the work of coercive land recovery, serving the Phu Do regulating lake construction project.