On October 13, Khanh Hoa Provincial People's Committee said it had worked with Ninh Hoa Town People's Committee on supporting and supervising site clearance for key projects.
Mr. Tran Hoa Nam - Vice Chairman of Khanh Hoa Provincial People's Committee - requested Ninh Hoa Town People's Committee to develop a detailed roadmap on work content, implementing units, and deadline for completing compensation, support, and resettlement of the Khanh Hoa - Buon Ma Thuot Expressway project to have a basis for monitoring, urging work and having plans to promptly remove difficulties and obstacles.
In addition, Ninh Hoa town needs to divide the remaining cases affected by the project but the compensation plan has not been approved (cases not subject to resettlement consideration and cases subject to resettlement consideration) to implement the next steps to ensure the time and content according to the provisions of the 2024 Land Law...
For the Van Phong - Nha Trang component project, the leaders of Khanh Hoa province have assigned the People's Committee of Ninh Hoa town to urgently hand over the sites of the 220kV transmission line foundations affected by the project; speed up the progress of site clearance to construct the rest stop at Km334+900...
According to the report of Ninh Hoa Town People's Committee, as of October 8, 2024, the locality has basically completed the site clearance work for the main route of the Van Phong - Nha Trang component project under the North - South Expressway Construction Project, Eastern phase 2021 - 2025; handed over the site for 15/16 220kV line foundation positions affected by the Van Phong - Nha Trang component project; is implementing site clearance work to construct a rest stop at Km334+900...
For Component Project 1 of the Khanh Hoa - Buon Ma Thuot Expressway Project, the Ninh Hoa Town People's Committee has approved the compensation plan for 846/1,038 affected cases. The remaining cases are undergoing compensation, support and resettlement procedures.
The Khanh Hoa - Buon Ma Thuot Expressway Project is approximately 117.5km long, connecting Khanh Hoa - Dak Lak provinces. The starting point is at the intersection between National Highway 26B and National Highway 1, Nam Van Phong port area, Khanh Hoa province; the end point is at km12+450 of Ho Chi Minh Road, avoiding the East of Buon Ma Thuot city, Dak Lak province.
The project scale has 4 lanes, investment phase from 2021 - 2025, design speed 80 - 100km/h.
The total investment of the project is 21,935 billion VND from the budget. The project is divided into 3 component packages, including package 1 invested by Khanh Hoa Provincial People's Committee; package 2 built by the Ministry of Transport; and package 3 implemented by Dak Lak Provincial People's Committee.
Van Phong - Nha Trang Expressway, part of the North - South Eastern Expressway in the 2021 - 2025 period, is more than 83km long and is expected to be basically completed by April 30, 2025.