Speedy site clearance for the Ca Mau - Dat Mui expressway

NHẬT HỒ |

Ca Mau - The Ca Mau - Dat Mui expressway project has been handed over land after only 3 months of urgent implementation.

On the afternoon of December 31st, Ca Mau province summarized the site clearance work of key projects and works in 2025; the peak emulation movement to complete site clearance work for the Ca Mau - Dat Mui expressway project and key projects in the area.

Giam doc Trung tam Phat trien quy dat tinh Ca Mau Tang Vu Em phat bieu tai hoi nghi. Anh: Nhat Ho
Director of Ca Mau Provincial Land Fund Development Center Tang Vu Em speaks at the conference. Photo: Nhat Ho

At the summary meeting, Mr. Tang Vu Em - Director of the Ca Mau Provincial Land Fund Development Center - said that in just 2 weeks, nearly 1,600 billion VND was paid to affected households, which is a miracle.

Mr. Vu Em said that to achieve this result, the Board has arranged local banks, disbursed cash immediately to the people, so in a short time, nearly 1,600 billion VND has been spent. This is valuable experience for the project to be implemented.

In the process of implementation, the investor proactively coordinates with departments and branches, and issues beyond authority are immediately consulted. This is a project that is of concern to leaders, with priority mechanisms to resolve, and difficulties and obstacles are resolved within the day.

The launch of the emulation movement has made a great contribution to accelerating the progress of the project. Leaders of communes with projects passed through directing drastically and effectively, especially the heads of Party committees and authorities.

Ong Nguyen Van Van, xa Ho Thi Ky, Ca Mau nguoi dan bi anh huong cua du an cao toc Ca Mau - Dat Mui cho rat minh ung ho het minh de nha nuoc lam cao toc. Anh: Nhat Ho
Mr. Nguyen Van Van - a resident affected by the Ca Mau - Dat Mui expressway project - said he wholeheartedly supports the state to build the expressway. Photo: Nhat Ho

Mr. Nguyen Van Van (Ho Thi Ky commune), whose land is affected by the project, said: "Giving land to the state to build the expressway is very happy, I feel there is a small contribution to contributing to the development of the country's transport infrastructure.

The project to recover land, compensate, support, and resettle the above-mentioned works with a total investment of 2,028 billion VND, using state budget capital (including central budget support of 50% and provincial budget of 50%), site clearance area of about 713.09ha. Up to now, compensation and support plans have been approved with a total of 1,646 households and 5 affected organizations, through 10 communes, total amount of 1,532.9 billion VND, area of 662.78 ha. 1,554.58 billion VND has been disbursed, reaching 100% of the approved plan. Achieving 97.16% of the 2025 capital plan and 2026 budget advances (total of 1,600 billion VND).

UBND tinh Ca Mau tang bang khen cho nhieu to chuc, ca nhan hoan thanh giai phong mat bang cac cong trinh trong diem. Anh: Nhat Ho
Ca Mau Provincial People's Committee awarded certificates of merit to many organizations and individuals who completed site clearance of key projects. Photo: Nhat Ho

Speaking at the conference, Secretary of Ca Mau Provincial Party Committee Nguyen Ho Hai thanked the enthusiasm and support of people with projects passing by.

The Secretary of the Ca Mau Provincial Party Committee also noted that the compensation and resettlement support project for the above-mentioned works needs to draw lessons for site clearance work. Quick implementation (only 3 months), effectiveness meets people's trust. Therefore, it is necessary to promote it to implement projects later in Ca Mau province.

NHẬT HỒ
RELATED NEWS

Ca Mau - Dat Mui Expressway will not worry about sand shortage

|

Ca Mau - The Ca Mau - Dat Mui Expressway Project Management Board said that the project is not too worried about lack of sand and stone. Contractors are urgently implementing when the site is available.

Efforts to hand over the site for the Ca Mau - Dat Mui expressway project

|

Ca Mau - The Ca Mau - Dat Mui Expressway project is supported by the people of the province. By the afternoon of December 15, many localities had handed over the site to the construction unit.

Handover of the Ca Mau - Dat Mui expressway site in Dat Mui commune

|

Ca Mau - Ca Mau - Dat Mui Expressway affects 133 households in Dat Mui commune and has been supported with compensation according to regulations.

Metro Line 1 in Ho Chi Minh City runs all night, free tickets to welcome New Year's Day

|

Ho Chi Minh City - Metro Line 1 increases trips, running overnight on December 31st and free tickets on January 1st, 2026 to serve people celebrating the New Year 2026.

Parking a motorbike for Countdown is quoted as a price of 100,000 VND

|

Hanoi - A sea of people flocking to Hoan Kiem Lake area to welcome Countdown 2026 makes parking areas crowded, in some places asking for prices up to hundreds of thousands of dong.

9th Hour: The price of choice - Part 1

|

9th hour number 183 - A boring marriage suddenly erupts when the husband demands a divorce. Finding clues behind it, how will the wife handle it when the truth is exposed?

Business ecosystem of the director of the program "Come here, four birds of the sky

|

The director of the program "Come here, four birds of the sky" is representing and participating in operating the business ecosystem operating in the entertainment and training fields.

The truth about the school recovering teachers' bonuses in Ninh Binh

|

Ninh Binh - Ha Nam Vocational College admitted to collecting a portion of the bonus money from officials and teachers, but that is a non-compulsory donation campaign.

Ca Mau - Dat Mui Expressway will not worry about sand shortage

NHẬT HỒ |

Ca Mau - The Ca Mau - Dat Mui Expressway Project Management Board said that the project is not too worried about lack of sand and stone. Contractors are urgently implementing when the site is available.

Efforts to hand over the site for the Ca Mau - Dat Mui expressway project

NHẬT HỒ |

Ca Mau - The Ca Mau - Dat Mui Expressway project is supported by the people of the province. By the afternoon of December 15, many localities had handed over the site to the construction unit.

Handover of the Ca Mau - Dat Mui expressway site in Dat Mui commune

NHẬT HỒ |

Ca Mau - Ca Mau - Dat Mui Expressway affects 133 households in Dat Mui commune and has been supported with compensation according to regulations.