Deadline for granting red books for each plot of land according to detailed construction planning

Huy Hùng |

The time for issuing a Certificate of Land Use Rights (red book), ownership of assets attached to land according to the detailed construction plan shall not exceed 5 working days.

Decision 3380/QD-BNNMT dated August 25, 2025 of the Ministry of Agriculture and Environment stipulates the registration of changes in land use rights and ownership of assets attached to land due to division, separation, consolidation, merger of organizations or conversion of organizational models, conversion of business types according to the provisions of the law on enterprises; adjustment of detailed construction planning; granting Certificates for each plot of land according to detailed construction planning to project investors in need.

Components and quantity of documents

- Document composition

a) In case of change of land use rights, ownership rights of assets attached to land due to division, separation, consolidation, merger of organizations or conversion of organizational models, conversion of business types according to the provisions of the law on enterprises:

- Application for registration of changes in land and assets attached to land according to Form No. 18 issued with Decree No. 151/2025/ND-CP.

- issued certificate.

- Business registration certificate or document on the establishment of the organization after change.

- Decision of competent authority or organization or document on division, separation, consolidation, merger, conversion of organizational models, conversion of business types in accordance with the provisions of law on enterprises in accordance with the provisions of law, in which it is necessary to clearly identify the organization that is allowed to use land, own assets attached to land after division, separation, consolidation, merger, conversion of organizational models, conversion of business types.

- drawings for land division and consolidation according to Form No. 22 issued with Decree No. 151/2025/ND-CP in cases where land division and consolidation are required.

- Land plot cadastral map extracts for cases where land users need to measure to re-determine the size of the edges and area of the land plot.

- Documents on representation according to the provisions of civil law in cases of carrying out procedures for registration of land and assets attached to land through representatives.

b) In case of adjustment of detailed construction planning:

- Application for registration of changes in land and assets attached to land according to Form No. 18 issued with Decree No. 151/2025/ND-CP.

- issued certificate.

- Decision approving adjustment of detailed construction planning by competent authority accompanied by detailed construction planning adjustment map and cadastral map or cadastral map measurement piece; in case the land price must be re-determined, additional documents must be submitted proving fulfillment of financial obligations on land.

- Documents on representation according to the provisions of civil law in cases of carrying out procedures for registration of land and assets attached to land through representatives.

c) In the case of granting a Certificate for each plot of land according to the detailed construction planning to the project investor in need:

- Application for registration of changes in land and assets attached to land according to Form No. 18 issued with Decree No. 151/2025/ND-CP.

- issued certificate.

- The decision approving the detailed construction planning of the competent authority together with the detailed construction planning map and cadastral map or cadastral map measurement piece.

- Documents on representation according to the provisions of civil law in cases of carrying out procedures for registration of land and assets attached to land through representatives.

- Number of documents: 01 set.

Scope of settlement

- The time to resolve procedures for changing land use rights and ownership of assets attached to land due to division, separation, consolidation, merger, conversion of organizational models, and conversion of business types shall not exceed 08 working days.

For mountainous communes, islands, remote areas, areas with difficult socio-economic conditions, areas with especially difficult socio-economic conditions, the implementation period shall not exceed 18 working days.

- The time to resolve procedures for granting Certificates of land use rights and ownership of assets attached to land according to detailed construction planning or adjusting detailed construction planning is no more than 05 working days.

For mountainous communes, islands, remote areas, areas with difficult socio-economic conditions, areas with especially difficult socio-economic conditions, the implementation period shall not exceed 15 working days.

Huy Hùng
RELATED NEWS

Procedures for granting red books in cases of transferring investment projects using land

|

Register and issue a Certificate (red book) in the case of transferring investment projects using land in 3 steps.

Procedures for issuing first red books for individuals and people of Vietnamese origin residing abroad

|

Procedures for issuing red books for the first time for individuals and people of Vietnamese origin residing abroad follow 3 steps.

Organizing a ceremony to commemorate the one-year anniversary of the death of 67 victims of Lang Nu

|

Lao Cai - On September 10, local authorities and people held a memorial service for the victims of Lang Nu village who died due to storm No. 3 (Yagi).

Criticizing the Hai Phong Department of Construction after the incident of passengers being refused to board a ferry to leave the island

|

Hai Phong - Permanent Vice Chairman of the City People's Committee Le Anh Quan has just directed to overcome the operating situation at Dong Bai - Cai Vieng ferry terminal.

iPhone 17 Air, 17 Pro criticized for being expensive when launched

|

The newly launched iPhone 17 series did not receive many positive reviews, as Apple has not yet made improvements to AI, while the prices of some models are higher than previous years.

Protecting businesses from fake news and false information in the digital environment

|

Vingroup Corporation's civil lawsuit, reporting to the authorities and sending documents to the Embassies about 68 domestic and foreign organizations and individuals reporting false information about the corporation on the Internet is considered a timely act in self-defense and protection of the legitimate rights of enterprises. This incident also shows the need to increase the responsibility of management agencies and social media users in the context of Vietnam having many solutions to unblock the driving force for private economic development - becoming the most important driving force of the national economy in the spirit of Resolution 68 on private economic development.

online scams in Cambodia, Myanmar defraud tens of billions of USD of Americans

|

The US has sanctioned a series of online scams in Cambodia and Myanmar for appropriating tens of billions of dollars from the American people in 2024 alone.

Cán bộ Bộ Nông nghiệp và Môi trường xuống địa phương hỗ trợ thủ tục đất đai, cấp sổ đỏ

Nguyễn Hà |

Các cán bộ của Cục Quản lý đất đai, Bộ Nông nghiệp và Môi trường được giao xuống địa phương hỗ trợ thủ tục đất đai.

Procedures for granting red books in cases of transferring investment projects using land

Huy Hùng |

Register and issue a Certificate (red book) in the case of transferring investment projects using land in 3 steps.

Procedures for issuing first red books for individuals and people of Vietnamese origin residing abroad

Huy Hùng |

Procedures for issuing red books for the first time for individuals and people of Vietnamese origin residing abroad follow 3 steps.