HCMC has not yet finalized the height of Thu Thiem 4 bridge due to new planning

MINH QUÂN |

HCMC - The clearance plan for Thu Thiem 4 bridge has not been decided yet because it is related to the planning of Nha Rong - Khanh Hoi port (District 4).

According to the Department of Transport of Ho Chi Minh City, there have been 5 options for clearance (distance from the highest water surface to the bridge's underside) studied for Thu Thiem 4 Bridge.

Of these, the two options for building Thu Thiem 4 Bridge have fixed clearances of 10m and 15m, with investment costs of approximately VND4,365 billion and VND4,840 billion, respectively. These two options are in line with the planning, but the height does not meet the needs of large ships entering and leaving Nha Rong - Khanh Hoi port.

The other two options are the Thu Thiem 4 cable-stayed bridge with a fixed clearance of 45m or a tunnel under the Saigon River, with total investment of more than VND8,000 billion and nearly VND9,000 billion respectively. In addition to the large cost and difficulty in recovering capital for investors, these two options are difficult to implement due to the impact on planning in the Thu Thiem New Urban Area as well as District 7.

The remaining option is that Thu Thiem 4 Bridge has a normal operating clearance of 15m, but the main span can be raised to 45m, through two towers and a lifting system. However, operating the bridge lifting system will incur maintenance costs and may affect road traffic.

This project has a total capital of more than 6,000 billion VND and was proposed by the Ho Chi Minh City Department of Transport to help large ships easily cross the Saigon River.

Vi tri xay cau Thu Thiem 4. Anh: Anh Tu
Thu Thiem 4 Bridge construction site. Photo: Anh Tu

In August 2024, in a document sent to the Ministry of Transport, the Ho Chi Minh City People's Committee said it would choose the option of building Thu Thiem 4 bridge with a fixed clearance of 15m, because it believes this option is suitable for the operation of restaurant boats on the Saigon River.

These ships are under 12m in height and serve culinary tourism on the river, so 15m of clearance is enough for the ships to pass. At the same time, the Nha Rong - Khanh Hoi port area has planned 2 locations for inland passenger ports.

As for the downstream of Thu Thiem 4 bridge, in the adjustment of the general planning of Ho Chi Minh City to 2040 and vision to 2060, it is determined that there will be international passenger terminals at Mui Den Do (District 7) and Ben Nghe (District 7), capable of receiving large international passenger ships of up to 60,000 GT and 30,000 GT.

However, an unexpected factor appeared when Chairman of Ho Chi Minh City People's Committee Phan Van Mai directed to re-study the planning of Nha Rong - Khanh Hoi port location into "International Passenger Port".

The Department of Planning and Architecture of Ho Chi Minh City has been assigned to research and update this plan into the project to adjust the city's general planning.

This makes the construction of Thu Thiem 4 bridge with a fixed clearance of 15m inappropriate, because large passenger ships will have difficulty passing through the bridge to dock at Nha Rong - Khanh Hoi port.

The Department of Transport of Ho Chi Minh City has proposed that the Department of Planning and Architecture urgently study and update the planning of the international passenger port at Nha Rong - Khanh Hoi port into the general planning adjustment dossier of Ho Chi Minh City, to serve as a basis for determining the clearance of Thu Thiem 4 bridge.

Thu Thiem 4 Bridge is expected to have a total length of 2.16km, of which the main bridge is more than 1.6km long, with 6 lanes. The bridge starts from the intersection of Tan Thuan 2 Bridge - Nguyen Van Linh (District 7), connecting with Thu Thiem New Urban Area at the intersection of the North-South axis and Bui Thien Ngo Street.

Ho Chi Minh City aims to start construction of Thu Thiem 4 Bridge on April 30, 2025 and complete it in 2028.

MINH QUÂN
TIN LIÊN QUAN

Cố định tĩnh không cầu Thủ Thiêm 4, nguy cơ mất lợi thế về sông nước của TPHCM

MINH QUÂN |

TPHCM chọn phương án cầu Thủ Thiêm 4 vượt sông Sài Gòn (nối Khu đô thị mới Thủ Thiêm, TP Thủ Đức sang quận 7) có tĩnh không cố định 15m, thay vì nhịp chính có thể nâng hạ lên 45m như tính toán trước đây.

TPHCM muốn xây cầu Thủ Thiêm 4 với tĩnh không cố định 15m

MINH QUÂN |

TPHCM - Cầu Thủ Thiêm 4 dài hơn 2km, 6 làn xe, tĩnh không cố định 15m, không thể nâng mở nhịp chính lên 45m như đề xuất trước đó.

Thiết kế lạ mắt của cây cầu hơn 6.000 tỉ đồng sắp xây trên sông Sài Gòn

MINH QUÂN - Ảnh: Portcoast |

TPHCM - Cầu Thủ Thiêm 4 bắc qua sông Sài Gòn (nối liền Quận 7 và TP Thủ Đức) được Sở Giao thông vận tải (GTVT) TPHCM đề xuất xây dựng với thiết kế độc đáo, một phần của cầu có thể nâng lên độ cao khoảng 45 m để các tàu, thuyền lớn đi qua. Nếu được thông qua chủ trương, cầu Thủ Thiêm 4 sẽ khởi công năm 2025, thông xe năm 2028.

Lý do Bộ Giáo dục đề xuất xếp lương giáo viên cao nhất

Vân Trang |

Theo dự thảo Luật Nhà giáo, lương giáo viên được xếp cao nhất trong hệ thống thang bậc lương hành chính sự nghiệp.

Cập nhật giá vàng sáng 27.9: Vàng nhẫn hừng hực tăng

Khương Duy |

Cập nhật giá vàng sáng 27.9: Đà tăng giá của vàng chưa dừng lại. Vàng nhẫn tròn trơn 9999 phá đỉnh mới 83 triệu đồng/lượng.

Tại sao Man United từng từ chối Ivan Toney?

An An |

Ivan Toney từng được coi là bản hợp đồng lý tưởng với Man United nhưng cuối cùng, thương vụ này vẫn không thể xảy ra.

Chuyện về cô gái khiếm thính ở Việt Nam giành học bổng Mỹ

ĐÔNG DU |

Chương trình "Đời rất đẹp" mới đây kể lại câu chuyện về chị Nguyễn Trần Thủy Tiên - người nhận học bổng toàn phần ở Mỹ và trở về cống hiến cho cộng đồng người khiếm thính tại Việt Nam.

Cục Thuế Bình Định cưỡng chế nợ thuế đối với Bamboo Airways

Hoài Phương |

Theo Cục Thuế tỉnh Bình Định, trường hợp Bamboo Airways không nộp đủ số tiền thuế nợ, Cục sẽ cưỡng chế ngừng sử dụng hóa đơn đối với công ty này.