Red River bridge projects take advantage of every hour to accelerate progress

Minh Hạnh |

Hanoi mobilizes maximum manpower and machinery, accelerates the construction of bridges over the Red River, determined to exceed the "highway" schedule before the flood season.

Taking advantage of favorable weather at the beginning of the year, contractors constructing a series of bridge projects over the Red River are mobilizing maximum manpower and machinery, organizing many parallel construction teams, determined to stick to the "track" of progress to bring the project to the finish line as committed.

On February 25, records at the Tran Hung Dao bridge construction site showed that the construction atmosphere is very urgent. Currently, 10 construction teams are simultaneously operating, including 6 teams constructing main bridge pillars and 4 teams constructing the approach road on the Long Bien side. The main pillars have completed drilled piles and are moving to the stage of constructing steel plank piles.

Tranh thủ thời tiết thuận lợi đầu năm, các nhà thầu thi công loạt ra quân. Ảnh: Minh Hạnh
Taking advantage of favorable weather at the beginning of the year, construction contractors simultaneously launched operations. Photo: Minh Hanh

Worker Tran Dinh Kiem (Trung Chinh Joint Stock Company) said that from the morning of the 5th day of Tet, after short New Year wishes, workers returned to work. "About 70% of the brothers stayed at the construction site throughout Tet, the rest returned to their hometowns to reunite but all returned to work right from the 5th day, determined to celebrate spring but not forget their duties," Mr. Kiem shared.

Similarly, worker Luong Thanh Do (Dat Phuong Joint Stock Company) said that the force working throughout Tet only takes leave on the 29th day of the twelfth lunar month, and has returned to construction since the afternoon of the 1st day. "Progress is urgent, with the leadership's concern and family encouragement, the brothers are all ready to stay," Mr. Do said.

Tận dụng từng giờ đẩy nhanh tiến độ cầu Trần Hưng Đạo. Ảnh: Minh Hạnh
Taking advantage of every hour to speed up the progress of Tran Hung Dao bridge. Photo: Minh Hanh

According to Mr. Tran Trong Huy - Deputy Director of the Tran Hung Dao Bridge Construction Investment Project Board (Sun Group), the construction site currently mobilizes about 140 people, including 100% field engineers, mechanics, electricians... All machinery and equipment such as cranes and drills have been fully gathered. It is expected that by February 26, the contractor will add 45 more workers to accelerate construction.

To date, all underwater drilled piles of TC2 to TC6 pillars have been basically completed, each pillar consisting of 20 piles with a diameter of 2m, more than 50m deep, exceeding the schedule by about 1 month compared to the plan. Pillar TC7 has completed the bottom blocking concrete, and the foundation and piles are expected to be completed in March 2026. The goal is to complete all piles and foundations before May 2026 - the time when the minimum flood starts - to ensure conditions for construction of the pillar body.

Chạy đua vượt “đường găng”, các công trình cầu vượt sông Hồng tăng tốc thi công. Ảnh: Minh Hạnh
Racing to overcome "roads", bridge projects across the Red River accelerate construction. Photo: Minh Hanh

In the approach bridge section on Long Bien side, bored piles are also being deployed simultaneously, striving to complete the entire project in April 2026. According to Mr. Huy, if the minimum flood level is not exceeded by the end of May 2026, the project is at risk of being delayed by 3-4 months due to rising water levels, making it impossible to construct under the river.

Parallel to Tran Hung Dao bridge, the Ngoc Hoi bridge and approach roads at both ends of the bridge connecting Hanoi with Hung Yen are also being accelerated. Currently, 100% of personnel are present at the construction site, and contractors are organizing 10 construction teams, including 2 teams under the river and 8 teams on the shore.

Công trường cầu vượt sông Hồng làm việc xuyên Tết để kịp tiến độ. Ảnh: Minh Hạnh
The Hong River overpass construction site is working throughout Tet to meet the schedule. Photo: Minh Hanh

On the construction site stretching through Bat Trang commune (Hanoi) and Van Giang commune (Hung Yen), units are focusing on leveling the ground, processing steel cages, and constructing drilled piles for the main bridge piers and approach bridge piers. The project has a total length of about 7.5km, of which the main bridge over the Red River is about 680m long with 2 tower pillars identified as the "stepping stone" of progress.

Hà Nội tăng tốc thi công các công trình cầu vượt sông Hồng. Ảnh: Minh Hạnh
Hanoi accelerates construction of bridges over the Red River. Photo: Minh Hanh

After 6 months of implementation, the contractor has completed 26/80 bored piles for tower piers. At package 07/TP3-EPC, the processing of steel cages and bored pile construction have been continuously deployed since mid-February. According to the construction site commander, the construction teams are organized flexibly, striving to complete the piles and main pier bases in accordance with key milestones so as not to affect the overall progress.

According to the approved plan, the Ngoc Hoi bridge project is expected to be completed in the first quarter of 2028. However, the Project Management Board and consulting units, contractors are researching technical solutions to shorten the progress by about 6 months, striving to complete in the second quarter of 2027 according to the direction of the City Party Committee and Hanoi People's Committee.

Minh Hạnh
RELATED NEWS

Tay Thang Long road project: There is a land acquisition decision, but still intentionally building works

|

Hanoi - Dong Ngac Ward thoroughly grasps the task of site clearance for the Tay Thang Long road project immediately after the Binh Ngo Lunar New Year 2026.

Emergency project in Hanoi: Caring for the lives of workers working throughout Tet

|

Hanoi - Tay Tuu Ward requests the Project Management Board and contractors to pay attention to and care for workers working throughout Tet at the Pheo River landslide emergency treatment project.

Hanoi Party Secretary inspects the construction progress of Hong Ha bridge

|

Politburo member, Secretary of the Hanoi Party Committee Nguyen Duy Ngoc highly appreciated the efforts of the forces working at the Hong Ha bridge construction site.

People in Hanoi dismantle constructions, hand over land to build roads 120-180m wide

|

Hanoi - Many households have proactively dismantled works and handed over land to the locality to build a 6.7km long road with a cross-section of 120-180m.

Trade union news: Cases of receiving pension and receiving an additional 500,000 VND pension allowance

|

Trade union news: Cases of receiving pensions and receiving an additional 500,000 VND social pension allowance; 4 strongest recruiting industries in Hanoi...

Early elections at 4 locations in Ho Chi Minh City this morning

|

Ho Chi Minh City - Voting to elect National Assembly Deputies of the 16th term and People's Council Deputies at all levels took place at 4 early polling stations.

Russia evacuates all 4,300 tourists from Cuba, freezes flights

|

Russia announced that it has completed the evacuation of nearly 4,300 tourists from Cuba and has not resumed flights to this island nation.

God of Wealth Day, surprised by the atmosphere of buying gold in Ho Chi Minh City

|

On God of Wealth Day, in Ho Chi Minh City, there is no scene of people queuing in long lines from early morning.

Tiến độ giải phóng mặt bằng làm quảng trường phía Đông hồ Hoàn Kiếm

HOÀI ANH |

Hà Nội - Phường Hoàn Kiếm đã tiếp nhận mặt bằng của 12/17 tổ chức, 38/43 hộ dân và đang phá dỡ để làm quảng trường phía Đông hồ Hoàn Kiếm.

Tay Thang Long road project: There is a land acquisition decision, but still intentionally building works

Anh Tuấn |

Hanoi - Dong Ngac Ward thoroughly grasps the task of site clearance for the Tay Thang Long road project immediately after the Binh Ngo Lunar New Year 2026.

Emergency project in Hanoi: Caring for the lives of workers working throughout Tet

SÓNG HỮU |

Hanoi - Tay Tuu Ward requests the Project Management Board and contractors to pay attention to and care for workers working throughout Tet at the Pheo River landslide emergency treatment project.

Hanoi Party Secretary inspects the construction progress of Hong Ha bridge

KHÁNH AN |

Politburo member, Secretary of the Hanoi Party Committee Nguyen Duy Ngoc highly appreciated the efforts of the forces working at the Hong Ha bridge construction site.

People in Hanoi dismantle constructions, hand over land to build roads 120-180m wide

SÓNG HỮU |

Hanoi - Many households have proactively dismantled works and handed over land to the locality to build a 6.7km long road with a cross-section of 120-180m.