Can Tho resolves the backlog of the National Highway 91 expansion project

YẾN PHƯƠNG |

Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.

The project has stopped implementation, causing difficulties

The investment project to build the National Highway 91 Expansion Project (from Bus Station Intersection to Tra Noc) in Can Tho City was approved in 2008, with the goal of expanding National Highway 91, the section passing through Ninh Kieu and Binh Thuy districts.

However, due to many reasons, the project was suspended, delayed, and delayed the progress of some basic construction projects in 2011 and finally stopped implementation according to the Official Dispatch of the City People's Committee dated June 5, 2023. Currently, the authorities are focusing on resolving backlogs related to compensation, support and resettlement for people affected by the project.

Quoc lo 91 o TP Can Tho. Anh: Yen Phuong
The investment project to build the National Highway 91 expansion project has stopped implementation according to the Official Dispatch of the People's Committee of Can Tho City dated June 5, 2023. Photo: Yen Phuong

According to the Can Tho City Land Fund Development Center, Ninh Kieu District has approved compensation funds for 180/279 cases, with an amount of about 74 billion VND. Of which, compensation has been paid to 84 cases, with an amount of about 72.6 billion VND; there are 96 cases that have not received compensation due to lack of capital, with an amount of about 8.83 billion VND.

Binh Thuy District has approved compensation funds for 37/451 cases, with an amount of VND 23.49 billion. Of which, compensation has been paid to 25 cases, with an amount of 17.32 billion VND; there are 12 cases that have not received compensation due to lack of capital, with an amount of 4.57 billion VND.

Anh: Yen Phuong
Binh Thuy District has approved compensation funds for 37/451 cases. Photo: Yen Phuong

The project's suspension has caused difficulties and problems for local people and authorities. In particular, many households have received a portion of compensation but have not been resettled, many households have not received compensation due to the project being delayed, issues with resettlement land for affected households...

Focus on final payment of compensation

To resolve the project's backlog, the Can Tho City Land Fund Development Center has proposed solutions for each case. Accordingly, for cases that have received compensation, the approval decision will be kept unchanged and the City People's Committee will be requested to agree to review the resettlement policy according to regulations at the time of the land recovery decision.

For cases that have not received compensation due to the project's suspension or extension, respectfully request the City People's Committee to agree on the policy of canceling the land recovery decision and the decision approving funding; carry out land recovery, compensation, support and resettlement according to the project to upgrade and expand National Highway 91 (section Km0 - Km7) under implementation.

Anh: Ta Quang
National Highway 91 seen from above. Photo: Ta Quang

Regarding the resettlement land source, the People's Committee of Ninh Kieu District plans to arrange it in the An Binh Ward Resettlement Area and the Ninh Kieu District Resettlement Area. Binh Thuy District People's Committee will balance the land resources in the district to arrange for households.

In the coming time, the authorities will focus on paying compensation for cases that have received compensation and support but have not received enough additional funding and bonuses; preparing resettlement land (about 11 plots); coordinating to synthesize and prepare funding for cases of changes in houses, structures, and crops.

Can Tho City is making efforts to resolve the backlog of the National Highway 91 expansion project (from Ben Bus - Tra Noc Intersection), ensuring the rights of people and in accordance with the actual situation; at the same time, speeding up the implementation of the National Highway 91 Upgrade and Expansion project (Km0 - Km7) to soon complete the city's traffic system.

YẾN PHƯƠNG
TIN LIÊN QUAN

Speed up the compensation progress for a project worth over VND7,200 billion in Can Tho

|

Can Tho - Up to now, 73/101 cases have been compensated, with an amount of more than 268 billion VND.

Can Tho will start construction of a project to renovate 5 intersections in March

|

Can Tho - It is expected that intersection No. 1 will start construction in mid-March, while intersection No. 4 will start construction at the end of March.

Upgrading many central routes of Can Tho

|

Can Tho - The urgent construction atmosphere is covering many central roads of the city, aiming to bring a new look to the city.

Soil and rocks suddenly collapsed in Lai Chau, husband was swept away, wife got out of a car and escaped

|

Lai Chau - A serious landslide from the positive slope to the surface of National Highway 4D killed one person.

Recklessly overtaking in the middle of traffic jam, a passenger bus hit a male student in Lam Dong and killed him

|

Lam Dong - Recklessly overtaking while National Highway 20 was congested, a passenger bus crashed head-on into a motorbike, causing an 11th grade male student in Ward 3, Bao Loc to die on the spot.

The Ministry of Public Security promotes the rank of Traffic Police Captain who sacrificed his life in Lai Chau

|

Lai Chau - Captain Ha Van Minh - Traffic Police Department, Provincial Police - died while on duty in Muong So commune.

Tho Xuan Airport sets up additional barriers to prevent illegal access

|

Thanh Hoa - After the appearance of consecutive unmanned aerial vehicles illegally encroaching, Tho Xuan airport has set up barriers to prevent them.

Tight control from the border to prevent smuggled goods from entering the country

|

Quang Tri - The smugglers are sophisticated, finding every way to smuggle smuggled and banned goods from the border area into the inland for consumption.

Speed up the compensation progress for a project worth over VND7,200 billion in Can Tho

YẾN PHƯƠNG |

Can Tho - Up to now, 73/101 cases have been compensated, with an amount of more than 268 billion VND.

Can Tho will start construction of a project to renovate 5 intersections in March

YẾN PHƯƠNG |

Can Tho - It is expected that intersection No. 1 will start construction in mid-March, while intersection No. 4 will start construction at the end of March.

Upgrading many central routes of Can Tho

YẾN PHƯƠNG |

Can Tho - The urgent construction atmosphere is covering many central roads of the city, aiming to bring a new look to the city.