Speed up the compensation progress for a project worth over VND7,200 billion in Can Tho

YẾN PHƯƠNG |

Can Tho - Up to now, 73/101 cases have been compensated, with an amount of more than 268 billion VND.

Compensation payment of more than 268 billion VND

The project to upgrade and expand National Highway 91 (section from Km0 - Km7) with a total investment of nearly VND 7,238 billion is being urgently implemented by Can Tho City. This is a key project, of great significance in the city's socio-economic development.

Cot Km7 cua Quoc lo 91 o Can Tho. Anh: Ta Quang
Km7 column of National Highway 91 in Can Tho. Photo: Ta Quang

The project has a total planned land area of about 27.25 hectares; affecting about 1,066 households, individuals and organizations; with a need for resettlement of about 300 plots.

According to the Can Tho City Land Fund Development Center, up to now, the compensation, support and resettlement work of the project has achieved positive results. The locality has issued a notice of land recovery for 483/720 cases, counted and prepared compensation records for 1,066/1,066 cases (reaching 100%); submitted and issued a decision approving compensation, support and resettlement plans for 101/266 cases; paid compensation to 73/101 cases with an amount of more than 268 billion VND.

In Ninh Kieu district, the work of determining the origin of houses, land and compensation payments is being accelerated. Binh Thuy District has also issued a notice of land reclamation for 379/616 cases and paid compensation to 55/64 cases.

Nhieu vi tri tai Quoc lo 91 xuong cap, ngap nuoc khi trieu cuong. Anh: Yen Phuong
Many locations on National Highway 91 are degraded and flooded during high tides. Photo: Yen Phuong

However, the project is also facing some difficulties and problems such as: lack of resettlement land locations; no specific land prices to calculate compensation at some locations; cases of houses and construction works with construction permits with a term...

To solve these difficulties, Can Tho City has been implementing many synchronous solutions. Localities are speeding up the progress of determining land origin, holding legal meetings and approving compensation plans. At the same time, the city is also reviewing and adjusting compensation and resettlement policies to ensure the rights of the people.

Compensation expected to be approved before April 25

According to the Can Tho City Land Fund Development Center, in recent times, the project has been focused on by the entire political system in the implementation work; especially the consensus and response of the people, the coordination of households, and organizations affected by the project.

Truoc do, vao thang 11.2024, TP Can Tho da ung truoc hon 410 ti dong nang cap 7km Quoc lo 91. Anh: Ta Quang
Previously, in November 2024, Can Tho City advanced more than 410 billion VND for the 7km National Highway 91 upgrade project. Photo: Ta Quang

The upcoming plan, approved by the Board of Compensation for 41 cases and submitted to the approval of the remaining 42 cases in Ninh Kieu district before April 25. Submitting to approve 63 cases approved by the Compensation Council for projects in An Thoi ward and Tra An ward this March.

The locality focuses on site clearance for Binh Thuy bridge. Of which, An Thoi ward has 37 cases (13 cases have been approved, and 24 cases are completing documents to be approved by the Compensation Council), with a total amount of about 45 billion VND, equivalent to an area of 1,182m2.

Binh Thuy Ward has 40 cases (16 cases have been approved, and 24 cases are completing documents to be approved by the Compensation Council), with a total amount of about 110 billion VND, equivalent to an area of 2,566m2. Bui Huu Nghia Ward has 30 cases that are completing legal meeting documents to approve the Compensation Council. These cases are all expected to be approved before April 25.

The National Highway 91 Upgrade and Expansion Project (section from Km0 - Km7), Can Tho City is a Group A project, a level 1 road traffic project, with implementation period from 2023 - 2027. The overall goal of the project is to complete the transport infrastructure, striving to build Can Tho into a modern and civilized city, basically becoming an industrial city.

YẾN PHƯƠNG
TIN LIÊN QUAN

Project of over 7,200 billion VND in Can Tho compensates people

|

Can Tho - The total compensation cost for people affected by the National Highway 91 Upgrading and Expansion Project (Km0 - Km7) this time is about 410 billion VND.

Project worth over 7,200 billion in Can Tho will start construction before April 30, 2025

|

Can Tho - The project to upgrade and expand 7km of National Highway 91, section Km0 - Km7, with a total investment of more than 7,237 billion VND, will start construction before April 30, 2025.

Resolving difficulties in the project of over 7,200 billion in Can Tho

|

Can Tho - The project to upgrade and expand National Highway 91 (section from Km0 - Km7), Can Tho City has a total investment of nearly 7,238 billion VND, expected to start construction in the second quarter of 2025.

A wall collapsed in Can Tho when demolished, a worker injured

|

Can Tho - On the afternoon of March 15, a house wall collapse suddenly occurred near the Mau Than - 3 Thang 2 - Tran Hung Dao intersection, in Ninh Kieu district.

Despite the danger, people freely fish in prohibited waters

|

Hoa Binh - Although warning signs have been erected along the Hoa Binh Hydropower Plant area, many people are still calmly fishing right at the foot of the dam.

Transferring the Ministry of Public Security to consider investigating 2 projects in Vinh Long

|

The Government Inspectorate forwarded information and documents to the Ministry of Public Security for consideration and investigation of the two projects in Vinh Long.

Vietnam travels to the United Nations to map the Gulf of Tonkin base road

|

Vietnam has used the United Nations' basic golf and Tonkin route map and coordinates.

Forecast of heavy rain in the area due to increased cold air

|

According to the meteorological agency, tonight, March 15, due to the impact of cold air, the area from Quang Binh to Khanh Hoa will have local heavy rain.

Project of over 7,200 billion VND in Can Tho compensates people

Tạ Quang |

Can Tho - The total compensation cost for people affected by the National Highway 91 Upgrading and Expansion Project (Km0 - Km7) this time is about 410 billion VND.

Project worth over 7,200 billion in Can Tho will start construction before April 30, 2025

Tạ Quang |

Can Tho - The project to upgrade and expand 7km of National Highway 91, section Km0 - Km7, with a total investment of more than 7,237 billion VND, will start construction before April 30, 2025.

Resolving difficulties in the project of over 7,200 billion in Can Tho

YẾN PHƯƠNG |

Can Tho - The project to upgrade and expand National Highway 91 (section from Km0 - Km7), Can Tho City has a total investment of nearly 7,238 billion VND, expected to start construction in the second quarter of 2025.