The Dang Thai Mai Road Construction Project, Phase I, Quang An Ward, Tay Ho District, was approved by the Hanoi People's Committee for red line boundary, and the Tay Ho District People's Committee approved the project according to Decision No. 1434/QD-UBND dated August 26, 2024.
The project has a total length of 1,260km, starting from Tay Ho villa area, ending at the intersection with Xuan Dieu street, with a total investment of more than 550 billion VND.
Scale of cross -section of the wide road b = (20.5 ÷ 93.6) m includes: The wide spaces b = 93.6m (the road surface is 2x15m wide, the road on both sides is 2x6m wide, the landscape axis is 54.6m wide); The section through the Tay Ho villa area B = 20.5m (the road surface is 11.25m wide, the summer sides are 4,625m wide). Building a system of water supply, drainage and technical drainage; Organize traffic, install lighting systems and plant trees.
To implement the project, Tay Ho District will have to reclaim 36,482.5m2 of land from 183 households, individuals, and organizations.
As of March 27, there have been 160 cases of cooperation in investigation, of which 144 plans have been made public, and 28 out of 144 plans have ended in being made public.
For the remaining 23 cases that have not cooperated in investigation, the authorities have submitted and transferred the dossier to propose the Tay Ho District People's Committee to issue a decision to enforce the compulsory inventory according to regulations.
Tay Ho District strives to basically complete site clearance in June 2025; basically complete project construction in June 2026.
The completion of the project will help increase traffic connectivity between the Central Party Office villa, Tay Ho screen and neighboring areas to solve traffic congestion during holidays, Tet, National Assembly sessions, and Party Congresses.
Gradually complete the regional transport infrastructure according to the approved plan, develop the socio-economic - tourism - create a civilized - modern street; form the cultural space - ecological landscape axis of West Lake - Co Loa according to the orientation of Hanoi Capital Planning for the period 2021 - 2030, with a vision to 2050.