1,400 billion VND project to renovate National Highway 28B in Lam Dong is stuck with more than 6km of site clearance

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B is stuck with more than 6km of site clearance. The Department of Construction has inspected and committed to promptly reporting to remove obstacles and speed up progress.

The inspection team of Lam Dong Provincial Department of Construction has just inspected the progress of the project to renovate and upgrade National Highway 28B.

The delegation noted the current status of the sections where the site has not been handed over and clarified the reason for the delay.

Mot doan thi cong mat bang tren Quoc lo 28B. Anh: Duy Tuan
A section of construction site on National Highway 28B. Photo: Duy Tuan

Mr. Bui Sy Cuong - Executive Director of the XD-01 package said that the lack of full handover of clean land has greatly affected the construction progress. Meanwhile, the weather is in the rainy season, the remaining construction time is only about 5 months.

Currently, the entire route is still stuck with about 6.3km of site clearance. In which, the power line system, water pipes, many electric poles have not been relocated...

Kiem tra tai cong trinh thi cong mot cay cau trong du an. Anh: Duy Tuan
The inspection team at the construction site of a bridge in the project. Photo: Duy Tuan

Nearly 1km of the first section of the route through Luong Son intersection has not been handed over the site, causing the contractor to not be able to construct the main route and bridge.

Mr. Cuong added: "To basically complete the project in 2025, Project Management Board 5 has proposed that Lam Dong Provincial People's Committee direct relevant units to promptly complete the procedures and hand over the site to the project before August 15".

Doan kiem tra cua So Xay dung tinh Lam Dong tai hien truong thi cong. Anh: Duy Tuan
The inspection team of Lam Dong Provincial Department of Construction at the construction site. Photo: Duy Tuan

At the on-site inspection, Mr. Le Minh Tien - Deputy Director of the Department of Construction of Lam Dong province said that after the on-site inspection, the Department will have a comprehensive report on the project progress to promptly remove obstacles and speed up the project progress.

May moc thi cong tren deo Dai Ninh. Anh: Pham Duy
Construction machinery on Dai Ninh Pass. Photo: Pham Duy

Previously, the Ministry of Construction sent a document to the People's Committee of Lam Dong province, requesting to speed up the site clearance progress for the National Highway 28B renovation and upgrade project.

The Ministry of Construction also warned of risks for the project if the locality does not complete the handover of the site in August 2025 for construction.

The project to renovate and upgrade National Highway 28B is over 68km long. The total investment is more than 1,400 billion VND and is expected to be completed before December 31, 2025. To date, the project has been handed over about 61km of site, reaching 91%.

The project is invested by the Vietnam Road Administration, assigning Project Management Board 5 to directly manage the project.

Duy Tuấn
RELATED NEWS

Near the end of the construction period, the 1,400 billion VND project in Lam Dong is still stuck with site clearance

|

Lam Dong - The project to renovate and upgrade National Highway 28B with a total cost of VND1,400 billion is expected to be completed by the end of 2025, but there are still problems with site clearance.

The final stage on National Highway 28B, creating inter-regional connectivity after the merger

|

Lam Dong - The project to renovate and upgrade National Highway 28B will speed up construction after basically completing the handover of the site, soon meeting the increased travel demand after the merger.

Busy construction of overpass in the middle of the Dang Ninh Pass is difficult for National Highway 28B to be completed soon

|

Binh Thuan - Construction of overpasses on Dai Ninh Pass is considered the sections with the most difficult construction conditions in the project to upgrade and renovate National Highway 28B.

Alcohol concentration test for a man in a chain collision in Hanoi

|

Hanoi - Functional forces conduct an alcohol concentration test on a man in a chain collision on Nguyen Chanh street.

Ho Chi Minh City Ao Dai Festival 2026 spreads identity and aspirations for integration

|

Ho Chi Minh City - The 2026 Ho Chi Minh City Ao Dai Festival with the theme "Golden Silk - Weaving Aspiration" officially opened on the evening of March 6.

VGCL President Nguyen Anh Tuan meets with voters in Da Nang

|

Da Nang - Candidates of the 16th National Assembly Deputies of constituency No. 5 participate in an online voter contact conference connecting many communes and wards.

U17 Vietnam enters a difficult group at the 2026 U17 Southeast Asian Championship

|

U17 Vietnam falls into a challenging group with Indonesia and Malaysia at the 2026 U17 Southeast Asian Championship.

Deputy Prime Minister requests proactive gasoline and oil reserves to regulate and stabilize the market

|

The Deputy Prime Minister requested to proactively manage gasoline and oil reserves to flexibly regulate and stabilize the market when fluctuations or supply disruptions arise.

Near the end of the construction period, the 1,400 billion VND project in Lam Dong is still stuck with site clearance

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B with a total cost of VND1,400 billion is expected to be completed by the end of 2025, but there are still problems with site clearance.

The final stage on National Highway 28B, creating inter-regional connectivity after the merger

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B will speed up construction after basically completing the handover of the site, soon meeting the increased travel demand after the merger.

Busy construction of overpass in the middle of the Dang Ninh Pass is difficult for National Highway 28B to be completed soon

Duy Tuấn |

Binh Thuan - Construction of overpasses on Dai Ninh Pass is considered the sections with the most difficult construction conditions in the project to upgrade and renovate National Highway 28B.