Near the end of the construction period, the 1,400 billion VND project in Lam Dong is still stuck with site clearance

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B with a total cost of VND1,400 billion is expected to be completed by the end of 2025, but there are still problems with site clearance.

On July 30, information from the investor of the National Highway 28B Renovation and Upgrade Project through Lam Dong province said that up to now, the project has been handed over the site for about 61km/68 km (reaching 91%).

However, there are still 6.3km of site that have not been handed over. Some technical infrastructure works that have not been relocated include: 4.3km of water pipes; 100 electric poles of all kinds and railway signal information lines.

There are still more than 23 hectares of land that have not been approved for site clearance.

Mot vi tri thi cong nang cap, mo rong Quoc lo 28B. Anh: Duy Tuan
A construction site to upgrade and expand National Highway 28B, in Lam Dong province. Photo: Duy Tuan

With the goal of completing the project in 2025, the construction and capital disbursement time is only about 5 months.

The Ministry of Construction has issued a document requesting the People's Committee of Lam Dong province to direct the People's Committees of Luong Son, Song Luy, Phan Son, Ta Hine, Ninh Gia communes and functional units, in which, requesting units to focus on completing compensation procedures, land acquisition, and relocation of technical infrastructure in August 2025 to hand over clean land to the contractor for construction.

Cong nhan thi cong cau can giua deo Dai Ninh. Anh: Duy Tuan
Workers constructing a overpass in the middle of Dai Ninh Pass. Photo: Duy Tuan

The Ministry of Construction also assigned the Vietnam Road Administration and Project Management Board 5 to coordinate with localities to completely resolve the problems, ensuring the set progress.

In case the locality does not complete the handover of the site according to the above schedule. The project is unlikely to be completed in 2025 and fully disbursed medium-term public investment capital for the period 2021-2025.

"At that time, the project is at risk of having to stop implementation to adjust capital for national key projects according to the direction of the Prime Minister" - the document of the Ministry of Construction stated.

The project to renovate and upgrade National Highway 28B through Lam Dong province is about 68km long. The total investment is more than 1,400 billion VND and is scheduled to be completed before December 31, 2025.

The project has a starting point intersecting with National Highway 1A (Luong Son commune), the end point intersecting with National Highway 20 (Ninh Gia commune). The project is invested by the Vietnam Road Administration and this unit assigned Project Management Board 5 to manage the project.

The project is invested according to the scale of a level III plain road, a 12m wide roadbed, a 11m wide road surface, and a design speed of 80 km/h.

Duy Tuấn
RELATED NEWS

Lam Dong accelerates infrastructure completion, attracting businesses to fill 2 industrial parks

|

Lam Dong - When the basic infrastructure is completed, the investment capital of thousands of billions is pouring into Ham Kiem 1 and 2 Industrial Parks, creating jobs for more than 5,000 workers.

The final stage on National Highway 28B, creating inter-regional connectivity after the merger

|

Lam Dong - The project to renovate and upgrade National Highway 28B will speed up construction after basically completing the handover of the site, soon meeting the increased travel demand after the merger.

Busy construction of overpass in the middle of the Dang Ninh Pass is difficult for National Highway 28B to be completed soon

|

Binh Thuan - Construction of overpasses on Dai Ninh Pass is considered the sections with the most difficult construction conditions in the project to upgrade and renovate National Highway 28B.

Adjusting land area in National Highway 28B upgrade project

|

Binh Thuan - Adjust to reduce 2.422 hectares of land use conversion and land acquisition area for the project to upgrade and renovate National Highway 28B.

Fire flares up after thunderstorms in Hai Phong, black smoke covers the entire street

|

Hai Phong - At about 6:40 p.m. on July 30, a fire broke out at a locomotive warehouse on Yet Kieu Street, Tran Hung Dao Ward, causing panic among local residents.

Can Tho Department of Agriculture and Environment informs about the issue of garbage collection and transportation

|

Can Tho - At the press conference for the second quarter of 2025 on the afternoon of July 30, the Department of Agriculture and Environment informed about the issue of waste collection and transportation to collection points.

Tighten online advertising, limit the activities of violating artists

|

As more and more online advertising violations involving celebrities increase, the Department of Radio, Television and Electronic Information (PTTH-TTDT) will apply strong measures.

Coach Kim Sang-sik holds the championship trophy, joins U23 Vietnam to celebrate the audience's welcoming

|

On the evening of July 30, U23 Vietnam took a flight back to Ho Chi Minh City after winning the 2025 U23 Southeast Asian Championship in Indonesia.

Lam Dong accelerates infrastructure completion, attracting businesses to fill 2 industrial parks

Duy Tuấn |

Lam Dong - When the basic infrastructure is completed, the investment capital of thousands of billions is pouring into Ham Kiem 1 and 2 Industrial Parks, creating jobs for more than 5,000 workers.

The final stage on National Highway 28B, creating inter-regional connectivity after the merger

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B will speed up construction after basically completing the handover of the site, soon meeting the increased travel demand after the merger.

Busy construction of overpass in the middle of the Dang Ninh Pass is difficult for National Highway 28B to be completed soon

Duy Tuấn |

Binh Thuan - Construction of overpasses on Dai Ninh Pass is considered the sections with the most difficult construction conditions in the project to upgrade and renovate National Highway 28B.

Adjusting land area in National Highway 28B upgrade project

Duy Tuấn |

Binh Thuan - Adjust to reduce 2.422 hectares of land use conversion and land acquisition area for the project to upgrade and renovate National Highway 28B.