Van Thanh Bridge project worth 225 billion VND is stuck with land clearance, construction site has few workers

Duy Tuấn |

Lam Dong - The Van Thanh bridge project connecting the two banks of the Ca Ty river is stuck in site clearance, and has only disbursed 10% of the annual plan.

The Van Thanh bridge project connecting the two banks of the Ky Ty river in Tien Thanh ward and Binh Thuan ward, Lam Dong province with an investment of about 225 billion VND, started in January 2023 and is expected to be completed in 2025.

On the morning of October 22, a barge carrying 2 cranes was recorded at the construction site anchored under the river. About 6 workers are working at the locations on the bridge. The contractor is currently constructing underwater items and areas near the shore.

Sa lan cho 2 can cau neo dau tai du an cau Van Thanh, sang 22.10. Anh: Duy Tuan
The barge carrying 2 cranes anchored under the Ca Ty River at the Van Thanh bridge project, on the morning of October 22. Photo: Duy Tuan

Lam Dong Provincial Department of Construction said that to date, the project has reached about 55% of the contract volume. The project has completed 1 bridge abutment, 5 bridge piers, completed 114 girders and installed 43/114 girders...

However, site clearance is the biggest "bottleneck". Contractors are forced to adjust construction progress and plans to suit the situation of land clearance problems and actual conditions.

Thua thot cong nhan tai cong trinh, sang 22.10. Anh: Duy Tuan
Dear workers at the construction site, morning of October 22. Photo: Duy Tuan
2 tru cau ben phia bo thuoc phuong Tien Thanh. Anh: Duy Tuan
2 bridge piers on the bank of Tien Thanh ward. Photo: Duy Tuan

The main reason is the problem of alluvial land and the difference in compensation prices. Some households near the river have been granted red books, while the previous households have not been granted land use right certificates, leading to different compensation levels. People have not agreed, causing construction progress to be delayed.

To date, the project's investment capital disbursement rate has only reached about 10.28% of the 2025 capital plan.

Faced with the above reality, Vice Chairman of Lam Dong Provincial People's Committee - Nguyen Hong Hai noted that the project has been implemented for nearly 2 years but the site clearance work is still slow.

Toan canh tien do du an cau Van Thanh. Anh: Duy Tuan
Overview of the progress of the Van Thanh bridge project. Photo: Duy Tuan

To promptly resolve the difficulties, Mr. Hai assigned the People's Committee of Tien Thanh Ward to review and apply the compensation price for 8 households according to regulations. The Department of Agriculture and Environment and the Branch of the Land Fund Development Center need to coordinate to complete the compensation and site clearance work of the project, and promptly hand over the clean site to the construction unit.

Mr. Hai also requested the construction unit to speed up the progress, do it as soon as the site is available, ensure the disbursement progress and meet the expectations of local people.

The Van Thanh Bridge project is designed as a reinforced concrete bridge, with a prescribed load capacity of 6 spans, a global length of about 179m, and a bridge width of 19m. The goal of the Van Thanh bridge project is to serve the needs of travel, goods exchange between the Van Thanh residential area and Phan Thiet area and complete traffic infrastructure and urban beautification.

Duy Tuấn
RELATED NEWS

Hanoi starts construction of underpasses, bridges across the Red River and many projects from October 4 to 10

|

Hanoi - From October 4 to 10, the city will organize the groundbreaking ceremony for many projects such as the Co Linh underpass, the Thuong Cat and Tran Hung Dao bridges across the Red River, metro line 2...

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

|

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

50-year-old casuarina forest in Quang Ngai cut down to build coastal road

|

Quang Ngai - Nearly 400 50-year-old casuarina forest trees in Mo Cay commune were cut down to build coastal roads, causing "steel shields" protecting houses and land to be eroded.

Russia launches long-range satellite UAV to destroy Ukrainian helicopters for the first time

|

For the first time, a Russian Geran UAV was controlled by satellite, destroying Ukrainian military helicopters.

Bad news

|

Comrade: Tran Chan; born on January 15, 1933, Former Head of the Department of Education and Training of Quang Trach district, Title of Meritorious Teacher, Badge of 65 years of Party membership. Comrade Tran Thang's biological father - Deputy Secretary of the Party Committee of the Fatherland Front and Central Agencies. Original residence: Quang Trach Commune, Quang Tri Province. Residence: Quarter 3, Ba Don Ward, Quang Tri Province. Passed away at: 9:27 PM, January 26, 2026. (December 8 of the year of At Ty) At the age of 93.

Can Gio - Vung Tau sea crossing reveals underground tunnel design of more than 2 km

|

Ho Chi Minh City - Can Gio - Vung Tau sea crossing is more than 14 km long, designed with overpasses and undersea tunnels about 2.1 km long.

Verifying the enjoyment of mental illness benefits after suspected abnormalities in a commune in Nghe An

|

Nghe An - Nghe An Psychiatric Hospital has re-verified the procedure and checked the records of mental patients who were reported to have abnormal signs.

Nipah virus returns, mortality rate up to 75%, Vietnam tightens epidemic prevention

|

The Nipah virus is being recorded again in India, causing Vietnam to proactively tighten surveillance and epidemic prevention measures.

Đắk Lắk yêu cầu chấm dứt chậm trễ tại dự án cao tốc Khánh Hòa - Buôn Ma Thuột

BẢO LÂM |

Đắk Lắk - Chủ tịch tỉnh Đắk Lắk yêu cầu khẩn trương tháo gỡ vướng mắc, chấm dứt tình trạng chậm trễ tại Dự án thành phần 3 cao tốc Khánh Hòa - Buôn Ma Thuột.

Hanoi starts construction of underpasses, bridges across the Red River and many projects from October 4 to 10

SÓNG HỮU |

Hanoi - From October 4 to 10, the city will organize the groundbreaking ceremony for many projects such as the Co Linh underpass, the Thuong Cat and Tran Hung Dao bridges across the Red River, metro line 2...

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

Duy Tuấn |

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.