Landslide prevention project worth over 17 billion VND in Quang Ngai is stalled

VIÊN NGUYỄN |

Quang Ngai - The project to overcome landslides on DT. 624B route with a total investment of more than 17 billion VND is stagnant, the investor continuously urges the contractor to accelerate construction.

Slow progress, many items not completed according to plan

Provincial Road 624B is an important traffic route connecting National Highway 1 with western communes of Quang Ngai province. The flood in late 2024 caused serious landslides at Km14 + 500, the section passing through Dinh Cuong commune, damaging the roadbed and surface and affecting people's travel.

To ensure traffic safety, the project to overcome negative taluy landslides, foundation, and road surface at Km14+500, DT. 624B route was started on January 25, 2026, with a total investment of more than 17 billion VND.

Không chỉ chậm tiến độ, biện pháp tổ chức thi công của nhà thầu cũng chưa tuân thủ chỉ đạo của chủ đầu tư. Ảnh: Đông Giang
Not only is it behind schedule, the contractor's construction organization measures have also not complied with the investor's instructions. Photo: Vien Nguyen

According to the plan, the project will be completed and put into use on July 30, 2026. However, the project is currently quite struggling.

Faced with this situation, Mr. Mai Van Ha - Deputy Director of Quang Ngai Provincial Department of Construction has just signed a document requesting urgently to accelerate the project construction progress.

According to the direction of the Department of Construction, Thanh Dat Construction Co., Ltd. - the construction unit, must mobilize maximum manpower, machinery, and equipment; organize many construction teams at the same time in a rolling manner, maximizing favorable weather conditions, increasing shifts to compensate for the delayed volume.

The Department of Construction especially requests contractors to focus on thoroughly handling the items of drilled piles and retaining walls to prevent the risk of continued landslides of existing taluy slopes, ensuring safety for traffic works and surrounding areas; at the same time, urgently increase labor for retaining wall construction, immediately deploy sand filling behind the retaining wall - an item that has been delayed compared to the plan from May 21.

Dự án chưa đáp ứng yêu cầu theo kế hoạch được phê duyệt. Ảnh: Đông Giang
The project has not met the requirements according to the approved plan. Photo: Vien Nguyen

For Thien Phuc Construction Consulting Joint Stock Company - the design consulting unit, the Department of Construction directed to continue to arrange professional personnel to be on duty at the site; closely coordinate with the investor, project management unit, supervision consultant and construction contractor to promptly handle technical issues.

In addition, Binh Minh General Consulting Co., Ltd. (supervision consultant) and Tam Anh ATP Co., Ltd. (project management consultant) are assigned to strengthen inspection and regularly be on duty at the construction site to urge progress.

The risk of slow planning is unavoidable

According to the report of the supervision consulting unit, as of June 12, the actual construction volume value outside the site only reached more than 8.6 billion VND, equivalent to about 50.2% of the contract value (more than 17.2 billion VND). Although the project has passed more than half of its implementation time, the construction progress to date has not yet met the requirements according to the approved plan.

Sở Xây dựng yêu cầu nhà thầu tăng cường nhân lực thi công tường chắn, triển khai ngay việc đắp cát phía sau tường chắn - hạng mục đã chậm so với kế hoạch từ ngày 21.5. Ảnh: Đông Giang
The Department of Construction requested the contractor to increase manpower to construct the retaining wall, immediately deploy the sand filling behind the retaining wall - an item that has been delayed compared to the plan from May 21. Photo: Vien Nguyen

Mr. Ho Anh Viet - Deputy Director of Binh Minh General Consulting Co., Ltd. informed that the drilled pile item as required must be completed before June 12. However, up to now, there are still 11 piles at the construction site that have not been completed.

Meanwhile, the retaining wall item is required to be completed before July 6, but with the slow progress of implementation as it is now, the risk of delaying the plan is unavoidable.

Not only is it behind schedule, but the contractor's construction organization measures have also not complied with the investor's instructions. For the bored pile item, the construction unit continues to use the cable drilling method, even adding an additional cable drilling equipment at the construction site, contrary to the direction of the Department of Construction (rotation drilling).

Continuing to apply this construction method not only potentially affects the safety of neighboring infrastructure projects and road projects, but also does not meet the requirements of accelerating progress.

VIÊN NGUYỄN
RELATED NEWS

Seven households in Quang Ngai languidly wait for compensation and resettlement for 7 years

|

Quang Ngai - Tinh Phong Industrial Park project has been delayed for 7 years, causing 7 households in Tho Phong commune not to receive compensation and resettlement.

Quang Ngai starts construction to upgrade and expand National Highway 24B

|

Quang Ngai - National Highway 24B will be upgraded synchronously with 4 lanes, building many new bridges and railway overpasses, expected to be completed in 2027.

A gold shop in Thu Dau Mot temporarily suspends operations, buyers worried

|

Ho Chi Minh City - Gold shop in Kim Hong (on Cach Mang Thang Tam street, Thu Dau Mot ward) closed and temporarily suspended operations.

Building a Visionary Press System Development and Management Strategy to 2045

|

On June 15, in Hanoi, the Ministry of Culture, Sports and Tourism organized a workshop to contribute opinions on building a dossier on the Strategy for development and management of the press system to 2030, with a vision to 2045.

Localities are allowed to sign contracts to support commune-level civil servants, not included in the payroll

|

The Ministry of Home Affairs requests localities to sign contracts to support commune-level civil servants, and people working under contracts are not included in the payroll.

Trade unions get involved, seafood processing workers receive late-paying salaries

|

Lam Dong - After the trade union and police worked with businesses, workers at a seafood processing company were paid the delayed salary.

Seven households in Quang Ngai languidly wait for compensation and resettlement for 7 years

ĐÔNG GIANG |

Quang Ngai - Tinh Phong Industrial Park project has been delayed for 7 years, causing 7 households in Tho Phong commune not to receive compensation and resettlement.

Quang Ngai starts construction to upgrade and expand National Highway 24B

ĐÔNG GIANG |

Quang Ngai - National Highway 24B will be upgraded synchronously with 4 lanes, building many new bridges and railway overpasses, expected to be completed in 2027.

Mưa lớn kéo dài nhiều tuyến đường ở Quảng Ngãi sạt lở nặng

VIÊN NGUYỄN |

Nhiều tuyến đường miền núi Quảng Ngãi sạt lở, đất đá tràn xuống gây chia cắt giao thông, tiềm ẩn tai nạn, trở thành nỗi ám ảnh người dân.