Hanoi is focusing its efforts on implementing a project to expand the road to 10 lanes

HỮU CHÁNH |

Hanoi is focusing resources to speed up site clearance progress to expand National Highway 6 to 21.7km long, with an investment of VND 8,000 billion.

National Highway 6 is a radial axis, connecting the Northwest provinces, important belts, satellite urban areas and many industrial parks along the route with the central core area of ​​Hanoi City.

As soon as it passes Yen Nghia bus station, Highway 6 begins to narrow, while the traffic volume is large, often congested during rush hours.

Highway 6 currently passes through Ha Dong and Chuong My districts with a narrow cross-section and is often congested. Photo: Huu Chanh
Highway 6 currently passes through Ha Dong and Chuong My districts with a narrow cross-section and is often congested. Photo: Huu Chanh
Highway 6, the section passing through Ha Dong district and Chuong My district (Hanoi), has a narrow cross-section and is often congested. Photo: Huu Chanh

To solve the above situation, in December 2022, the Hanoi People's Committee started to renovate 21.7km of National Highway 6 through Ha Dong and Chuong My districts, of which the section through Chuong My district is 15.8km long, Ha Dong is 5km long, 9km.

The project's starting point is located at km14 in Ba La territory, Ha Dong district; End point km38, Xuan Mai town, Chuong My district.

The project has a total investment of 8,000 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

Highway 6 section through Phu Nghia commune (Chuong My district) is being expanded. Photo: Huu Chanh
Highway 6 passing through Phu Nghia commune (Chuong My district) is being expanded to 60m, 10 lanes. Photo: Huu Chanh

As noted by Labor on August 2, the contractor is focusing on constructing a number of route sections with a length of several kilometers through Chuong My district. Some sections are currently graded with crushed stone.

The remaining 15km has not been expanded because of land problems.

According to a report from the Hanoi Statistics Department, by the end of July 2024, the project to upgrade and expand National Highway 6 section Ba La - Xuan Mai has disbursed 7.7% of the capital plan.

The parking lot makes it impossible for the project to be constructed synchronously across the entire route. Photo: Huu Chanh
The parking lot makes it impossible for the project to be constructed synchronously across the entire route. Photo: Huu Chanh

To implement the above project, Chuong My district needs to recover about 85 hectares of land. Of which, there are 39.96 hectares of land for rice cultivation and aquaculture; 27.99 hectares of public land; 15.28 hectares of residential land; 1.42 hectares of agency and unit land and 0.35 hectares of cemetery land.

To stabilize the lives of people whose land is subject to recovery, Chuong My district needs to build 5 resettlement areas.

Leaders of Chuong My District People's Committee affirmed that the project plays a particularly important role for the district. Therefore, the locality has proactively coordinated with the investor to take steps to clear the site right from the first days.

With the drastic involvement of the entire political system and synchronous implementation of solutions, many obstacles in the liberation work have been resolved.

To date, Chuong My district has handed over 23.2 hectares of land to the investor for construction projects in the communes of Phu Nghia, Truong Yen, Dong Son, Thuy Xuan Tien, and Xuan Mai town.

Chuong My district strives to hand over about 80% of agricultural land and public land to investors by the end of 2024. It is expected that by 2025, the district will complete site clearance for project construction.

Ha Dong district and Chuong My district are focusing on removing problems with site clearance for the construction of expanding National Highway 6. Photo: Huu Chanh
Ha Dong district and Chuong My district are focusing on removing problems with site clearance for the construction of expanding National Highway 6. Photo: Huu Chanh

Ha Dong District People's Committee is also coordinating with city departments and branches to urgently carry out site clearance for the National Highway 6 expansion project.

The district has submitted to the Department of Planning and Investment for appraisal a plan to select a contractor to advise on moving design and setting up landmarks for site clearance across the district. Initially, more than 300 households were temporarily determined to have to move out of the premises.

The investor, Hanoi Traffic Construction Investment Project Management Board, also said that it has directed contractors to speed up the construction progress of the project as soon as the site is received and qualified for construction.

According to the plan, the project will be completed in 2027, overcoming congestion, synchronously connecting technical infrastructure, contributing to socio-economic development of Ha Dong district, Chuong My district in particular and Ha City. Interior in general.

In addition, upgrading the route will strengthen links and trade between Hanoi and the Northwest provinces (Hoa Binh, Son La, Dien Bien, Lai Chau) and Laos.

HỮU CHÁNH
TIN LIÊN QUAN

Sắp hoàn thành mở rộng đường 1,1km ở trung tâm Hà Nội

Hữu Chánh |

Hà Nội - Dự án nâng cấp đường Xuân Diệu dài 1,1km, tổng mức đầu tư gần 400 tỉ đồng đang được gấp rút thi công hoàn thiện sau nhiều năm chậm trễ.

Tháng 10, Hà Nội thi công mở rộng đường huyết mạch lên 40m

HỮU CHÁNH |

Hà Nội - Sau khi hoàn thành giải phóng mặt bằng vào tháng 10.2024, quận Hoàng Mai sẽ triển khai thi công mở rộng đường Tam Trinh lên 40m, 6 làn xe.

Dự án chống ùn tắc cửa ngõ Nam Hà Nội sau một năm thi công

HỮU CHÁNH |

Hà Nội - Dự án đường nối cao tốc Pháp Vân - Cầu Giẽ với Vành đai 3 triển khai 1 năm nhưng tiến độ không được như kỳ vọng do thiếu mặt bằng.

Nga dồn ép quân Ukraina khỏi Kursk theo nhiều hướng

Song Minh |

Lực lượng Ukraina ngày càng bị đẩy lùi khỏi nhiều khu định cư ở tỉnh Kursk của Nga.

Cho thôi việc Bí thư huyện Vĩnh Cửu theo nguyện vọng

MINH CHÂU |

Ông Nguyễn Văn Thuộc - Bí thư Huyện ủy Vĩnh Cửu được Ban Thường vụ Tỉnh ủy Đồng Nai chấp thuận cho thôi việc theo nguyện vọng.

Doanh nghiệp gồng mình hồi phục sau bão số 3

Anh Tuấn |

Sau khi bão số 3 (Yagi) đi qua, nỗ lực phục hồi sản xuất - kinh doanh là công việc được nhiều doanh nghiệp ưu tiên thực hiện.

Tinh giản biên chế 82.295 công chức, viên chức

LƯƠNG HẠNH |

Theo Thứ trưởng Bộ Nội vụ Trương Hải Long, từ năm 2016 đến năm 2023, đã tinh giản biên chế 82.295 người.

Phê chuẩn ông Lê Ngọc Châu làm Chủ tịch UBND tỉnh Hải Dương

PHẠM ĐÔNG |

Thủ tướng Chính phủ đã phê chuẩn kết quả bầu chức vụ Chủ tịch UBND tỉnh Hải Dương đối với ông Lê Ngọc Châu.

Nearly completing 1.1km road expansion in central Hanoi

Hữu Chánh |

Hanoi - The project to upgrade Xuan Dieu street, 1.1km long, with a total investment of nearly 400 billion VND, is being urgently completed after many years of delay.

In October, Hanoi expanded the arterial road to 40m

HỮU CHÁNH |

Hanoi - After completing site clearance in October 2024, Hoang Mai district will deploy construction to expand Tam Trinh street to 40m, 6 lanes.

Anti-congestion project at South Hanoi gateway after one year of construction

HỮU CHÁNH |

Hanoi - The Phap Van - Cau Gie Expressway project with Ring Road 3 has been implemented for 1 year but progress is not as expected due to lack of space .