Lam Dong requests to change the way of project management, tighten the progress of coastal roads

Duy Tuấn |

Lam Dong requires units to focus on removing obstacles in the site and disbursing capital to speed up the progress of coastal road projects DT.719B and Van Thanh bridge.

On September 6, the Lam Dong Provincial Traffic Project Management Board said that the DT.719B coastal axis road project, Phan Thiet - Ke Ga section (25.61 km long), has completed 80% of the volume.

Of which, 17.8 km from National Highway 1A to Suoi Nhum Bridge has been exploited, while 3.88 km of the titanium mine of Tan Quang Cuong Company Limited has not yet handed over the site.

Du an duong truc ven bien DT.719B doan Phan Thiet - Ke Ga. Anh: Duy Tuan
DT.719B coastal axis road project Phan Thiet - Ke Ga section. Photo: Duy Tuan

The DT.719B road project, Hon Lan - Tan Hai section (8.7 km of main route and 1.7 km of branch route) has only reached 32% of the volume. Although more than 90% of the site has been cleared, the construction is slow mainly due to a lack of sand for the roadbed.

The Van Thanh Bridge project has been extended until December 2025. Currently, the volume has reached 54% but the new disbursement is more than 10.6 billion VND (10% of the plan). The main reason is the slow site clearance work, causing the progress to not meet requirements.

Du an Cau Van Thanh. Anh: Duy Tuan
Van Thanh Bridge project. Photo: Duy Tuan

Given the progress of 3 key transport projects in the Southeast of Lam Dong province, Mr. Nguyen Hong Hai - Vice Chairman of the Provincial People's Committee assessed that the projects still have many problems due to both subjective and objective reasons.

Mr. Hai requested the Provincial Traffic Project Management Board to change the management method, strengthen contractor urging, immediately handle the problems, not to let the existing and existing site conditions continue to be sluggish.

Vi tri vuong mo titan khien
The location of the titanium mine makes it impossible for the DT.719B road project, Phan Thiet - Ke Ga section, to continue construction. Photo: Duy Tuan

Directing the removal of obstacles for each project, for the DT.719B road project, Phan Thiet - Ke Ga section, Vice Chairman of Lam Dong Provincial People's Committee requested Tan Quang Cuong Company to complete the procedures to close the mine in area 1.4 and submit to the Ministry of Agriculture and Environment before September 10, 2025 to hand over the site.

In areas 2-3, units must focus on construction to ensure progress. Tan Thanh Commune People's Committee and the Land Fund Development Center must complete the compensation dossier in October 2025.

Du an duong DT.719B doan Hon Lan - Tan Hai dang thi cong. Anh: Duy Tuan
The DT.719B road project, Hon Lan - Tan Hai section, is under construction. Photo: Duy Tuan

For DT.719B road section Hon Lan - Tan Hai, the leaders of the Provincial People's Committee requested to speed up site clearance, disburse all allocated capital, and assigned the provincial Department of Agriculture and Environment to complete mineral recovery procedures in October 2025.

For Van Thanh Bridge, the Project Management Board must closely coordinate with local authorities to receive the handover of the site and implement it as soon as possible, ensuring completion in October 2025.

Duy Tuấn
RELATED NEWS

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

|

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Progress of Nguyen Trai bridge project worth over VND6,200 billion in Hai Phong

|

Hai Phong - After 7 months of construction, the Nguyen Trai Bridge Construction Investment and Urban Renovation Project in the surrounding area has reached nearly 22,2% of the workload.

Can Tho speeds up the progress of social housing projects, requiring price and quality control

|

Can Tho - The relevant industry requires investors to speed up progress, comply with regulations on selling social housing, and ensure no speculation.

Parks under bridges in Hanoi have stopped operating simultaneously

|

Hanoi - The parking lot under the Nga Tu Vong overpass and Chuong Duong bridge have simultaneously stopped operating.

Mr. Pham Duc An is introduced to be elected Chairman of the People's Committee of Da Nang City

|

Mr. Pham Duc An - Chairman of the People's Committee of Quang Ninh province, was transferred and appointed as Deputy Secretary of the Da Nang City Party Committee to introduce and elect the Chairman of the Da Nang City People's Committee.

Gold price increases sharply, surpassing 135 million VND/tael

|

On September 6, domestic gold prices continued to escalate, gold bars hit a new peak of over 135 million VND/tael, the highest level ever.

Ho Chi Minh City soldiers tell about beautiful memories when participating in A80 in Hanoi

|

HCMC - Returning after the A80 mission, the soldiers are not only proud, but also carry the memories and love of the people of the North for them.

Hanoi starts construction of nearly VND56,300 billion expressway, to be completed in 2028

|

Hanoi - Component project 3, construction of the 113km Ring Road 4 expressway in the Capital region, with a total investment of nearly VND 56,300 billion, is expected to be completed in 2028.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

Viên Nguyễn |

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Progress of Nguyen Trai bridge project worth over VND6,200 billion in Hai Phong

Hoàng Khôi |

Hai Phong - After 7 months of construction, the Nguyen Trai Bridge Construction Investment and Urban Renovation Project in the surrounding area has reached nearly 22,2% of the workload.

Can Tho speeds up the progress of social housing projects, requiring price and quality control

PHƯƠNG ANH |

Can Tho - The relevant industry requires investors to speed up progress, comply with regulations on selling social housing, and ensure no speculation.