Quang Ngai focuses on handling obstacles to the 3,500 billion VND transportation project

ĐÔNG GIANG |

Quang Ngai - The Hoang Sa - Doc Soi road project with a total investment of 3,500 billion VND is accelerating after removing many site clearance problems.

According to the Provincial Traffic Construction Investment Project Management Board, the Hoang Sa - Doc Soi road project has a total investment of 3,500 billion VND, with implementation time from 2022 - 2027.

The route has a length of 26.88 km; the starting point intersects with Tri Binh - Dung Quat road, the ending point connects to Hoang Sa road. The total planned construction area of the main route is 172.16 ha, passing through 6 communes and wards: Binh Son, Van Tuong, Dong Son, Tho Phong, Tinh Khe and Truong Quang Trong.

Ông Nguyễn Công Hoàng - Phó Chủ tịch UBND tỉnh Quảng Ngãi kiểm tra tiến độ dự án đường Hoàng Sa - Dốc Sỏi. Ảnh: UBND tỉnh Quảng Ngãi
Mr. Nguyen Cong Hoang - Vice Chairman of Quang Ngai Provincial People's Committee inspects the progress of the Hoang Sa - Doc Soi road project. Photo: Quang Ngai Provincial People's Committee

Regarding compensation and site clearance for the main route, up to now, 79 compensation plans have been approved for more than 133 hectares (reaching more than 77%); site handover has reached more than 74%. Contractor selection has been completed; construction packages, construction supervision and construction insurance have been signed. Currently, contractors are preparing documents and procedures necessary to deploy construction.

In addition, the Provincial Land Fund Development Center is coordinating with the People's Committees of communes and wards to focus on accelerating the progress of site clearance in resettlement areas and cemetery relocation areas. Accumulated construction value to date has reached more than 31% of the construction value according to the contract.

According to Mr. Nguyen Cong Hoang - Vice Chairman of Quang Ngai Provincial People's Committee, the Hoang Sa - Doc Soi road project is of particular importance in completing the transport infrastructure system, creating motivation to promote socio-economic development of the province in the coming period.

Provincial leaders acknowledged and praised the spirit of responsibility, effort, and proactiveness of the Project Management Board, contractors, units and localities in the implementation process; and shared the difficulties and obstacles arising.

Quang Ngai Provincial People's Committee requests units to continue to promote the spirit of responsibility, focus resources, and be determined to implement, ensuring the progress and quality of works according to the plan and set goals.

In the coming time, departments, branches, units and related localities need to identify site clearance as a key task; focus on leading and directing throughout; implement legal regulations correctly, coordinate closely, and not let obstacles arise affecting the overall progress.

Regarding the adjustment of land prices, Mr. Nguyen Cong Hoang directed relevant agencies to urgently survey and advise on building appropriate coefficients, ensuring harmony of interests between parties, creating conditions for the project to be implemented smoothly; and at the same time proactively develop plans to ensure the supply of raw materials for construction.

Localities continue to maintain the effective operation of the Steering Committee for key projects; strengthen propaganda and mobilization, create consensus among the people; focus on thoroughly handling existing problems, creating favorable premises for implementing subsequent key projects.

ĐÔNG GIANG
RELATED NEWS

Quang Ngai proactively allocates resources to clear ground for the 11.1 trillion VND project

|

Quang Ngai - Proactively and fully utilize resources to carry out site clearance for the high-speed railway project on the North-South axis section passing through the province.

Quang Ngai - Hoai Nhon expressway has contractors receiving management and maintenance

|

Gia Lai - When the expressway project is about to be put into operation, functional agencies have completed the selection of contractors for management, operation and maintenance of the route.

Quang Ngai accelerates a series of key traffic projects worth trillions of VND

|

Quang Ngai - Right after Binh Ngo Tet 2026, dozens of key traffic projects in Quang Ngai simultaneously accelerated construction.

Fearing high gasoline prices, many people queue for 30 minutes to fill up their tanks

|

Before the information that gasoline and oil prices may increase due to the impact of the Middle East conflict, many Hanoi residents took the opportunity to queue to fill up their tanks.

Ho Chi Minh City expects the 10th grade entrance exam schedule on the 1st and 2nd of June

|

The Ho Chi Minh City Department of Education and Training submitted to the Ho Chi Minh City People's Committee a plan to organize the 10th grade exam in 2026 on June 1st and 2nd.

Forecast for tomorrow's gasoline and oil prices to increase sharply, increasing to a maximum of 3,220 VND/liter

|

It is predicted that gasoline and oil prices may increase sharply from 1,207 - 3,220 VND/liter in this week's price adjustment session.

The State Bank continues to request credit institutions to publicly disclose lending interest rates

|

Deputy Governor Pham Thanh Ha said that the State Bank will continue to require credit institutions to publicize lending interest rates.

Iranian ship attacked by submarine, at least 101 people missing

|

At least 101 people are missing after a submarine attacked an Iranian ship, the Sri Lankan navy reported.

Quang Ngai proactively allocates resources to clear ground for the 11.1 trillion VND project

VIÊN NGUYỄN |

Quang Ngai - Proactively and fully utilize resources to carry out site clearance for the high-speed railway project on the North-South axis section passing through the province.

Quang Ngai - Hoai Nhon expressway has contractors receiving management and maintenance

THANH TUẤN |

Gia Lai - When the expressway project is about to be put into operation, functional agencies have completed the selection of contractors for management, operation and maintenance of the route.

Quang Ngai accelerates a series of key traffic projects worth trillions of VND

Đông Giang |

Quang Ngai - Right after Binh Ngo Tet 2026, dozens of key traffic projects in Quang Ngai simultaneously accelerated construction.