Replacing contractors, the Vy Da bridge expansion project in Hue still does not ensure progress

PHÚC ĐẠT |

HUE - Although a new contractor has been replaced to continue construction, the project to upgrade and expand Vy Da bridge has not yet reached the set schedule, and the investor must request to speed up construction.

Progress is not guaranteed

On September 23, reporters of Lao Dong Newspaper recorded at the Vy Da bridge expansion construction site (Hue City), there were no workers working. Machinery and materials serving construction are lying motionless at the construction site in rainy weather conditions, many items are still unfinished.

After being restarted with a new contractor, the project has not had a clear change in progress. The construction atmosphere in some deserted areas, while many remaining tasks have not been deployed synchronously.

Previously, package No. 28 with a construction value of 114.111 billion VND was implemented by Hoa Binh Joint Stock Company 479. Because the contractor did not meet the progress according to the contract and commitments, the investor terminated the contract with this unit on April 13.

As of March 31, 2026, the accumulated disbursed value of the bidding package reached 79.794 billion VND, equivalent to 69.93% of the construction value.

After the contract with Hoa Binh 479 Joint Stock Company was terminated, Dong Thuan Ha Joint Stock Company was selected to carry out the remaining work.

Công nhân vắng bóng ở công trường thi công dự án. Ảnh: Phúc Đạt
The project construction site was recorded on September 23. Photo: Phuc Dat

On September 23, in an exchange with Lao Dong Newspaper, a representative of the Department of Finance of Hue City said that the contract value is 33.83 billion VND. Dong Thuan Ha Joint Stock Company started construction on August 1, 2026, the expected implementation time is 6 months, completion on February 1, 2027.

For Nhu Y bridge, the contractor has installed the remaining railing on the right branch. Currently, the unit is preparing materials to carry out the steps and expansion joints.

At Vy Da bridge, the contractor has completed the inspection of beam raising and lowering equipment at the 133m beam casting yard, and at the same time completed leveling the M2 bridge opening area on Pham Van Dong street.

However, according to a representative of the Department of Finance, the construction of Vy Da bridge is still slow compared to the plan identified in the bidding documents. The Project Management Board has issued a document requesting the contractor to rectify and accelerate the progress.

Up to now, 4 beams of Vy Da bridge have been cast and the Nhu Y bridge railing is continuing to be completed. From August 1 to now, after more than 1 month and 20 days, the actual progress is still slow compared to the plan," said a representative of the Department of Finance of Hue City.

Request to complete before Lunar New Year

On September 22, leaders of Hue City People's Committee inspected the actual situation of the Vy Da bridge project implementation.

In the Vy Da bridge area, approach roads at both ends of the bridge, Chairman of Hue City People's Committee Le Tri Thanh requested the investor and contractor to focus manpower and equipment to organize construction with higher intensity, including studying increasing shifts and crews at locations that meet the conditions.

According to the request of city leaders, the progress of each item must be closely monitored, units need to proactively develop construction plans suitable to actual conditions and maximize favorable weather conditions.

Các hạng mục còn ngổn ngang, tiến độ chưa đảm bảo. Ảnh: Phúc Đạt
On September 23, the construction site was deserted, items were still messy, and progress was not guaranteed. Photo: Phuc Dat

Areas that have land and are eligible for deployment must be organized for continuous construction. Difficulties and problems arising at the construction site are also required to be handled promptly, avoiding affecting the overall progress of the project.

The goal set by Hue City leaders is to complete Vy Da bridge and approach roads at both ends of the bridge before the Lunar New Year, while ensuring quality and safety requirements during construction.

The request to accelerate the progress is raised in the context that the project has experienced many delays and has to change the contractor for the remaining work.

Vy Da bridge is one of the important traffic projects in Hue City, with a large volume of people and vehicles passing through every day. The bridge expansion aims to increase traffic capacity, ensure traffic safety and complete connection with the new urban area of An Van Duong.

PHÚC ĐẠT
RELATED NEWS

Promoting the progress of site clearance for a trillion-dong urban project in Dak Lak

|

Dak Lak - Functional agencies are accelerating compensation and site clearance for the provincial eco-tourism, cultural and ethnic minority tourism urban area project.

Hung Yen reviews the progress of housing projects and urban areas in the province

|

Hung Yen - On September 22, Mr. Nguyen Hung Nam - Vice Chairman of the Provincial People's Committee - chaired a meeting to listen to the Department of Construction report on the implementation of housing projects and urban areas.

Progress of the project to create a land fund of 358ha in Nhon Trach ward for auction

|

Dong Nai City Land Fund Development Center is recovering land for the project to create a land fund in the vicinity of the 358ha area in Nhon Trach ward.

Red sand flows down the gateway to the tourist route to Mui Ne

|

Lam Dong - Heavy rain caused water to sweep away red sand from the hill and spill onto Nguyen Thong street, the gateway to Mui Ne, causing some motorcyclists to fall.

Stock market: Waiting for signals from large cash flow

|

Cash flow is not really ready for a new upward cycle of the stock market.

Hanoi studies building more large-scale reservoirs

|

Hanoi - According to the Director of the Department of Agriculture and Environment, it is necessary to build large-scale reservoirs to retain water and limit horizontal forest floods.

Replacing contractors, the Vy Da bridge expansion project in Hue still does not ensure progress

|

HUE - Although a new contractor has been replaced to continue construction, the project to upgrade and expand Vy Da bridge has not yet reached the set schedule, and the investor must request to speed up construction.

Live broadcast of the Vietnamese Sports Delegation competing in ASIAD 20 today (September 23)

|

Live update of developments and competition results of the Vietnamese Sports Delegation at ASIAD 20 today (September 23).

Promoting the progress of site clearance for a trillion-dong urban project in Dak Lak

BẢO TRUNG |

Dak Lak - Functional agencies are accelerating compensation and site clearance for the provincial eco-tourism, cultural and ethnic minority tourism urban area project.

Hung Yen reviews the progress of housing projects and urban areas in the province

Theo Cổng TTĐT tỉnh Hưng Yên |

Hung Yen - On September 22, Mr. Nguyen Hung Nam - Vice Chairman of the Provincial People's Committee - chaired a meeting to listen to the Department of Construction report on the implementation of housing projects and urban areas.

Progress of the project to create a land fund of 358ha in Nhon Trach ward for auction

MINH CHÂU |

Dong Nai City Land Fund Development Center is recovering land for the project to create a land fund in the vicinity of the 358ha area in Nhon Trach ward.