Close-up of the trillion-dollar waste-to-energy plant in Phu Tho, progress is slow

Lam Thanh |

Phu Tho - After nearly 8 years of implementation and several progress adjustments, the trillion-dollar waste-to-energy plant project in Phu Ninh district still cannot come into operation.

Xxx
The investment project to build a domestic waste treatment and power generation plant in Tram Than commune, Phu Ninh district, Phu Tho province was started in October 2017 with a total investment of more than VND 2,242 billion, covering an area of ​​10 hectares. The total power generation capacity is 18MW. Photo: Lam Thanh
Xxx
The project is invested by the joint venture of Au Viet Resources and Environment Joint Stock Company and Tianyu Phu Tho Environmental Energy Company Limited. According to the 2019 National Power Plan, this project must complete phase 1 with a power generation capacity of 9MW in 2020. Photo: Lam Thanh
Sau nhieu lan dieu chinh, theo tien do den thang 8.2023, nha may phai hoan thanh va di vao chay thu (giai doan 1). Tuy nhien, du an van trong qua trinh thi cong. Anh: Lam Thanh
However, the project failed to operate as planned and had to adjust its schedule several times. In early 2024, Phu Tho province required the project to complete construction and equipment installation by August 2024. Photo: Lam Thanh
Ghi nhan cua PV, cong tac thi cong van dang trien khai, nhieu cong nhan, phuong tien may moc duoc huy dong de day nhanh tien do.
Up to now, the above deadline has passed, the construction and equipment installation have not been completed. As of October 31, 2024, the construction work is still underway with many unfinished items. Photo by Lam Thanh
Z
The infrastructure connecting to the national grid is not yet complete. Previously, at the end of May 2024, when inspecting this delayed project, the Chairman of the People's Committee of Phu Tho province requested the investor to mobilize human resources, machinery and equipment, operate the factory, and equip garbage collection vehicles as committed. Photo: Lam Thanh
Phan tho cua du an van dang duoc hoan thien. Anh: Lam Thanh.
The rough part of the project is still being completed. Photo: Lam Thanh.
Nhieu hang tai du an van dang trong giai doan xay dung. Anh: Lam Thanh.
A local resident said: "It has been nearly 8 years since the construction started, and we still don't know when it will be completed. We also want the factory to operate soon, hoping to solve the pollution caused by the gathering and burying of garbage in the area." Photo: Lam Thanh.
::
It is expected that when it comes into operation, 70% of waste in Phu Tho province will be collected, transported and processed at this waste-to-energy plant. Photo: Lam Thanh
Trong 2 nam dau, nha may se thu gom, xu ly 400 tan rac/ngay, 500 tan rac/ngay cho nhung nam tiep theo. Anh: Lam Thanh
In the first 2 years, the factory will collect and process 400 tons of garbage/day, and 500 tons of garbage/day in the following years. Photo: Lam Thanh
Xx
Speaking to Lao Dong Newspaper, Mr. Le The Cuong - Chairman of Tram Than Commune People's Committee said that the waste-to-energy plant project is still under construction and it is unclear when it will be completed. Some households in the affected area have plans to relocate to a resettlement area. Photo: Lam Thanh
Phoi canh du an Nha may xu ly rac sinh hoat, phat dien tinh Phu Tho.
Perspective of the project of Domestic waste treatment and power generation plant in Phu Tho province.

On February 18, 2019, the Prime Minister issued Document No. 211/TTg-CN agreeing to add the Phu Tho Waste-to-Energy Plant project to the National Power Development Plan.

This project is also expected to reuse waste as a resource to recover energy for electricity generation, contributing to reducing environmental pollution caused by current household waste landfill activities.

Lam Thanh
TIN LIÊN QUAN

Da Nang approves partial adjustment of waste-to-energy plant project

|

The People's Committee of Da Nang City has just issued a decision on approving the local adjustment of the detailed planning TL 1/500 of the Solid Waste Incineration Power Plant project in Khanh Son.

Proposal to consider disciplining a series of officials in Bao Loc city

|

Lam Dong – The police agency proposed to review and discipline the Party and government for a series of officials involved in the land donation and subdivision case in Bao Loc city.

2-storey house in Hanoi suddenly collapsed

|

Hanoi - A 2-storey house with an attic in Son Tay town (Hanoi) suddenly tilted and collapsed completely.

Pho restaurant in a 30-year-old house is popular in Hanoi

|

Hanoi - Located right at the beginning of Quan Nhan Street, Thanh Xuan District, Pho Dung restaurant has never been empty of customers in the more than 30 years it has been open.

Discussion on proposal to increase retirement age of military officers

|

The government proposed to increase the retirement age of military officers at most ranks, and add regulations on early promotion and salary increase.

Israel launches airstrikes on Gaza, 16 people killed

|

The northern Gaza Strip continued to be attacked by Israel on November 4, killing 16 people and injuring many others. Tanks are occupying a series of areas.

Storm No. 7 forecast in the East Sea can be very unpredictable

|

Storm forecasts show that storm Yinxing (Marce) could become storm number 7 in the East Sea with extremely unpredictable and complicated developments.

Nhà máy điện rác 847 tỉ ở Bắc Ninh thiếu rác để xử lý

Vân Trường |

Bắc Ninh - Lượng rác cung cấp cho nhà máy đốt rác phát điện huyện Lương Tài đang thiếu so với quy mô thiết kế .

Da Nang approves partial adjustment of waste-to-energy plant project

Nguyễn Linh |

The People's Committee of Da Nang City has just issued a decision on approving the local adjustment of the detailed planning TL 1/500 of the Solid Waste Incineration Power Plant project in Khanh Son.

Dự án Nhà máy điện rác 60 triệu USD ở Ninh Bình gặp khó

NGUYỄN TRƯỜNG |

Mặc dù đã được UBND tỉnh Ninh Bình giao gần 37.000m2 đất để thực hiện Dự án Nhà máy điện rác Ninh Bình, nhưng đến nay dự án này vẫn chưa thể triển khai được do gặp khó khăn, vướng mắc trong việc hoàn thiện Hợp đồng dịch vụ xử lý chất thải rắn sinh hoạt giữa chủ đầu tư và UBND tỉnh Ninh Bình.