Concentrating construction efforts on a road worth more than 7,200 billion VND in Hanoi

Hữu Vũ |

Hanoi - Workers and machinery are mobilized to construct day and night on Ring Road 1 with more than 7,200 billion VND to keep up with the set schedule.

UBND TP Hà Nội vừa yêu cầu các sở, ngành và đơn vị liên quan khẩn trương tháo gỡ các khó khăn, vướng mắc để đẩy nhanh tiến độ dự án đường Vành đai 1, đoạn Hoàng Cầu - Voi Phục. Thành phố đặt mục tiêu thông xe toàn tuyến trước ngày 2.9 và hoàn thành dự án trong năm 2026.
Hanoi City People's Committee has just requested departments, branches and related units to urgently remove difficulties and obstacles to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section. The city sets a target to open the entire route before September 2 and complete the project in 2026.
Theo ghi nhận của Lao Động ngày 5.7, trên một số đoạn tuyến của dự án, các hạng mục hai bên tuyến đã cơ bản hoàn thiện.
According to Lao Dong's records on July 5, on sections of the project, many important items are gradually being completed.
Trên đường Đê La Thành, đơn vị thi công đang tiến hành đào đất và lắp đặt hệ thống cống từ phố Thành Công hướng về đường Nguyễn Chí Thanh.
On De La Thanh street, the construction unit is excavating soil and installing a sewer system from Thanh Cong street towards Nguyen Chi Thanh street.
Công nhân tập trung thi công hệ thống thoát nước, lu lèn nền đường và hoàn thiện các hạng mục kỹ thuật.
Workers focus on constructing the drainage system, compacting the roadbed and completing technical items.
Đất đá được tập kết dọc tuyến, nhiều máy xúc và xe ben liên tục hoạt động, chuẩn bị cho các công đoạn tiếp theo.
Soil and rocks are gathered along the route, many excavators are continuously operating, preparing for the next stages.
Tại hai nút giao Nguyễn Chí Thanh và Giảng Võ - Láng Hạ, công trường vẫn duy trì nhiều mũi thi công. Các trụ cầu vượt đã dần hoàn thành.
At the two intersections Nguyen Chi Thanh and Giang Vo - Lang Ha, the construction site still maintains many construction fronts. Overpass bridge pillars across the intersections have gradually been completed.
a
Photo taken at the Nguyen Chi Thanh intersection area.
a
Talking to Lao Dong on July 5, Mr. Le Ba Luong - Deputy Construction Site Commander of Ring Road 1 package, said that to ensure the progress according to the city's direction of opening the entire Ring Road 1 section, Hoang Cau - Voi Phuc before National Day September 2 and completing the entire project in 2026, the unit arranges workers to work continuously day and night. "With the spirit of working urgently and determinedly, the construction units are focusing their efforts, striving to complete the opening of the route on time as set by the city," Mr. Luong said.

Hữu Vũ
RELATED NEWS

DT 748 expansion project: Unremoved power grid, construction potentially risks accidents

|

Ho Chi Minh City - The project to upgrade and expand DT 748 road in Ho Chi Minh City is being implemented, and the construction process has many potential risk points for accidents.

Project of over 7,200 billion VND in Can Tho still has 369 cases of land not yet handed over

|

Can Tho - The National Highway 91 Upgrade and Expansion Project has had 691/1,060 cases of site handover, and the remaining 369 cases have not yet handed over the site.

Many items of Hanoi Ring Road 1 project are gradually being completed

|

Despite difficulties and holidays, Ring Road 1 project still maintains continuous construction, and many important items are gradually being completed.

Current status of a transport project worth more than 1,100 billion VND in Hue before changing investors

|

HUE will replace the investor and terminate the contract with the weak contractor, causing the key traffic project of To Huu extended road to Phu Bai airport to be delayed.

Vietnam national team wins big in first friendly match in Korea

|

The Vietnamese team had a favorable start in the training trip in Korea when they defeated Siheung FC with a score of 6-0 in the first practice match.

Strategy to register aspirations to increase chances of university admission in 2026

|

Choosing and arranging aspirations reasonably will help candidates increase their chances of being admitted to the desired university.

DT 748 expansion project: Unremoved power grid, construction potentially risks accidents

ĐÌNH TRỌNG |

Ho Chi Minh City - The project to upgrade and expand DT 748 road in Ho Chi Minh City is being implemented, and the construction process has many potential risk points for accidents.

Project of over 7,200 billion VND in Can Tho still has 369 cases of land not yet handed over

Tạ Quang |

Can Tho - The National Highway 91 Upgrade and Expansion Project has had 691/1,060 cases of site handover, and the remaining 369 cases have not yet handed over the site.

Many items of Hanoi Ring Road 1 project are gradually being completed

Hữu Vũ |

Despite difficulties and holidays, Ring Road 1 project still maintains continuous construction, and many important items are gradually being completed.