Thanh Ha - Da Nhat resort project stalled after 15 years

CÔNG SÁNG |

Quang Binh - The Thanh Ha - Da Nhat resort project has been abandoned for many years, with no signs of construction.

Du an Khu du lich nghi duong Thanh Ha - Da Nhay (Du an) duoc cap giay chung nhan dau tu vao ngay 2.10.2009, voi tong dien tich gan 17ha va tong muc dau tu ban dau 230 ti dong. Du an nam tai xa Thanh Trach (huyen Bo Trach, tinh Quang Binh), cach bai bien Da Nhay khoang 300m. Voi mat tien sat Quoc lo 1A va phia sau huong ra bien, khu vuc nay duoc xem la “khu dat vang” co tiem nang phat trien du lich lon cua tinh Quang Binh. Anh: Cong Sang
The Thanh Ha - Da Nhay Resort Project (Project) was granted an investment certificate on October 2, 2009, with a total area of nearly 17 hectares and a total initial investment of VND 230 billion. The project is located in Thanh Trach commune (Bo Trach district, Quang Binh province), about 300m from Da Nhat beach. With the frontage close to National Highway 1A and the back facing the sea, this area is considered a "golden land" with great potential for tourism development in Quang Binh province. Photo: Cong Sang

Theo quy hoach, du an duoc chia thanh 8 phan khu chuc nang chinh va trien khai qua hai giai doan. Giai doan I (2009 - 2012) tap trung vao viec chuan bi dau tu, xay dung khu dich vu 3 sao, khu vuc ven Quoc lo 1A, khu nha nghi duong VIP va hoan thien ha tang du lich. Anh: Cong Sang
According to the plan, the project is divided into 8 main functional subdivisions and implemented through two phases. Phase I (2009 - 2012) focuses on preparing for investment, building a 3-star service area, the area along National Highway 1A, the VIP resort area and completing tourism infrastructure. Photo: Cong Sang
Giai doan II (2012 - 2015) du kien xay dung khu khach san cao cap va nghi duong 5 sao, hoan thien he thong ha tang ky thuat, xa hoi, gia co ke bo song, suoi, bo bien va phat trien canh quan xanh cho khu vuc. Anh: Cong Sang
Phase II (2012 - 2015) plans to build a 5-star luxury hotel and resort area, complete the technical and social infrastructure system, reinforce riverbank, stream, coastal embankment and develop a green landscape for the area. Photo: Cong Sang

Tuy nhien, theo ghi nhan cua PV Bao Lao Dong vao giua thang 3, du an dang trong tinh trang bo hoang. Khong co dau hieu cua hoat dong xay dung, cong nhan lam viec. Anh: Cong Sang
However, according to the reporter of Lao Dong Newspaper in mid-March, the project is in a state of abandonment. There are no signs of construction activities or workers working. Photo: Cong Sang

Ben trong khu dat, mot so ong bi be tong duoc dat san nhung khong co dau hieu su dung. Hang rao bao quanh khu vuc cung khong con nguyen ven, loi vao du an bi bo mac trong tinh trang nham nho. Anh: Cong Sang
Inside the land, some concrete pipes were placed in advance but there were no signs of use. The fence around the area is no longer intact. Photo: Cong Sang
Du duoc ky vong se tro thanh mot diem nhan du lich cua tinh, nhung den nay, sau 15 nam, du an van chi la mot khu dat trong. Nguon tin cua Bao Lao Dong cho biet, hien co quan chuc nang dang dieu tra, lam ro nhung van de lien quan den du an nay. Anh: Cong Sang
Although expected to become a tourist highlight of the province, up to now, after 15 years, the project is still just an empty lot. A source from Lao Dong Newspaper said that the authorities are currently investigating and clarifying issues related to this project. Photo: Cong Sang

CÔNG SÁNG
RELATED NEWS

Island commune in Binh Dinh will transform with a series of resort projects

|

Binh Dinh - Nhon Chau island commune will be invested with more than 400 billion VND to develop 4 tourist attractions with a resort system, marine parks and many service utilities.

Resolving difficulties for 5 component projects of the North - South Expressway project

|

The Deputy Prime Minister has directed a series of solutions to remove difficulties and obstacles for 5 component projects of the North-South Expressway to soon reopen the route.

Investing in the Suoi Cai road expansion project in Binh Duong

|

Binh Duong - The Provincial People's Committee agreed on the investment policy for the Suoi Cai road expansion project in Tan Uyen city, Binh Duong province.

Cold air strengthens, forecast for rain in the area on January 3-4.1

|

It is forecasted that the south of the North Central region will have rain, showers, locally moderate rain, heavy rain and thunderstorms on January 3 - 4 due to the impact of cold air.

After a New Year's Eve drinking party, a series of drivers violated the maximum alcohol concentration limit

|

Hanoi - Many drivers believe that they have been drinking alcohol since last night, drinking little, but the measurement results show that the alcohol concentration is very high.

Tan Beo's family responds to the case of not inviting Tan Bo to his grandson's wedding

|

According to the reporter's investigation, it is true that artist Tan Beo's family did not invite Tan Bo to Tan Loc's wedding ceremony, but there is a deep reason.

Vietnamese organ transplants mark the world medical map

|

From multiple organ transplants to the first heart-lung transplant, 2025 marked a strong breakthrough for Vietnamese organ transplantation on the world medical map.

Hanoi is about to recover land to build Ring Road 3.5, Provincial Road 70

|

Hanoi - In 2026, Dai Thanh commune will deploy land acquisition and site clearance to deploy the construction of Ring Road 3.5 and Provincial Road 70.

Island commune in Binh Dinh will transform with a series of resort projects

Thảo Phương |

Binh Dinh - Nhon Chau island commune will be invested with more than 400 billion VND to develop 4 tourist attractions with a resort system, marine parks and many service utilities.

Resolving difficulties for 5 component projects of the North - South Expressway project

PHẠM ĐÔNG |

The Deputy Prime Minister has directed a series of solutions to remove difficulties and obstacles for 5 component projects of the North-South Expressway to soon reopen the route.

Investing in the Suoi Cai road expansion project in Binh Duong

ĐÌNH TRỌNG |

Binh Duong - The Provincial People's Committee agreed on the investment policy for the Suoi Cai road expansion project in Tan Uyen city, Binh Duong province.