Resolving difficulties for 5 component projects of the North - South Expressway project

PHẠM ĐÔNG |

The Deputy Prime Minister has directed a series of solutions to remove difficulties and obstacles for 5 component projects of the North-South Expressway to soon reopen the route.

The Government Office has issued Document No. 100/TB-VPCP announcing the conclusion of Deputy Prime Minister Nguyen Chi Dung at the on-site inspection and meeting on reviewing and removing difficulties and obstacles of 5 component projects of the North-South expressway construction project in the East phase 2021-2025 sections: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo.

Accordingly, most projects with completed volume have reached over 75% and all set a goal of striving to complete the main expressway before April 30, 2025, completing all 5 projects before June 30, 2025.

The main difficulty and obstacle at present is site clearance for the Van Ninh - Cam Lo Expressway Component Road Project in Quang Tri province.

Quang Tri province has committed to completing site clearance by the end of 2024 and then early 2025; but to date, some locations have not yet handed over the site, affecting the progress of the entire project. The Deputy Prime Minister suggested that Quang Tri province seriously learn from experience in this work.

To ensure the completion of the entire North-South expressway in the East and the whole country has 3,000 km of expressway in 2025, for 5 expressway component projects, the Deputy Prime Minister requested:

The Ministry of Construction focuses on directing investors, contractors and relevant agencies and units not to be negligent or subjective, continue to proactively and actively implement further efforts, determined to complete the opening of the main expressway of all 5 projects before April 30, 2025.

Complete all 5 projects before June 30, 2025; complete rest stops and intelligent traffic management systems (ITS), toll collection systems (ETC), vehicle weight inspection (KTTTX) in 2025; at the same time, ensure the quality of the project, ensure supervision and construction in accordance with procedures and regulations.

Regarding the site clearance of the Van Ninh - Cam Lo Expressway Component Project in Quang Tri province, the Deputy Prime Minister requested the Provincial Party Secretary to focus on directing and mobilizing the entire political system of Quang Tri province to urgently participate, promote mobilization, persuasion, propaganda, create support, consensus and unity of the people.

Ensuring the handover of the site as soon as possible, requiring the whole site to be handed over to the contractor by the end of March 2025 at the latest so as not to affect the progress of the Van Ninh - Cam Lo expressway component project.

The Deputy Prime Minister assigned the Ministry of Agriculture and Environment to study and review the provisions of the Land Law and relevant decrees to guide the assessment of the direct impact on the lives and health of people due to the construction of component projects in the area according to the proposal of the People's Committee of Quang Binh province so that investors can implement it synchronously and consistently.

PHẠM ĐÔNG
RELATED NEWS

Investment in Tuy Loan intersection on Da Nang - Quang Ngai expressway

|

The Ministry of Transport is adjusting the Da Nang - Quang Ngai expressway project and submitting it to the Prime Minister for assignment to the Tuy Loan intersection management agency.

Removing difficulties for Ninh Binh - Hai Phong expressway project

|

The Deputy Prime Minister requested urgent resolution of the problems of the expressway project through Hai Phong and the 9km section in Thai Binh province.

Investment in expanding Ho Chi Minh City - Trung Luong - My Thuan expressway

|

The Deputy Prime Minister requested to urgently propose policies and funding needs for site clearance for the entire Ho Chi Minh City - Trung Luong - My Thuan expressway.

Horrifying earthquake risk from broken and sleeping for 12,000 years

|

The giant fault of Tintina, which has been silent for 12,000 years, is accumulating earthquake pressure, at risk of causing extremely strong earthquakes.

A crane fell into a house, two children escaped the accident

|

Hanoi - This afternoon, November 15, a crane about 30m long tilted and collapsed part of the house next door, the two children were lucky to escape.

Nearly half of Westerners feel overlooked by the government

|

A major survey shows that 45% of Westerners are dissatisfied with democracy, feel overlooked by the government and worry about a worsening future.

Car lost control and crashed into two vehicles traveling in the same direction in front

|

Hanoi While traveling on the elevated Ring Road 2, a car suddenly lost control and pushed forward, crashing into two other vehicles.

Buying and selling social housing diplomatic quotas is an act of taking advantage of policies and needs to be strictly handled

|

The investor of the social housing project (NOXH) believes that buying and selling diplomatic quotas for social housing is an act of taking advantage of policies, which needs to be condemned and strictly handled.

Investment in Tuy Loan intersection on Da Nang - Quang Ngai expressway

PHẠM ĐÔNG |

The Ministry of Transport is adjusting the Da Nang - Quang Ngai expressway project and submitting it to the Prime Minister for assignment to the Tuy Loan intersection management agency.

Removing difficulties for Ninh Binh - Hai Phong expressway project

Phạm Đông |

The Deputy Prime Minister requested urgent resolution of the problems of the expressway project through Hai Phong and the 9km section in Thai Binh province.

Investment in expanding Ho Chi Minh City - Trung Luong - My Thuan expressway

PHẠM ĐÔNG |

The Deputy Prime Minister requested to urgently propose policies and funding needs for site clearance for the entire Ho Chi Minh City - Trung Luong - My Thuan expressway.