Resolving difficulties for 5 component projects of the North - South Expressway project

PHẠM ĐÔNG |

The Deputy Prime Minister has directed a series of solutions to remove difficulties and obstacles for 5 component projects of the North-South Expressway to soon reopen the route.

The Government Office has issued Document No. 100/TB-VPCP announcing the conclusion of Deputy Prime Minister Nguyen Chi Dung at the on-site inspection and meeting on reviewing and removing difficulties and obstacles of 5 component projects of the North-South expressway construction project in the East phase 2021-2025 sections: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo.

Accordingly, most projects with completed volume have reached over 75% and all set a goal of striving to complete the main expressway before April 30, 2025, completing all 5 projects before June 30, 2025.

The main difficulty and obstacle at present is site clearance for the Van Ninh - Cam Lo Expressway Component Road Project in Quang Tri province.

Quang Tri province has committed to completing site clearance by the end of 2024 and then early 2025; but to date, some locations have not yet handed over the site, affecting the progress of the entire project. The Deputy Prime Minister suggested that Quang Tri province seriously learn from experience in this work.

To ensure the completion of the entire North-South expressway in the East and the whole country has 3,000 km of expressway in 2025, for 5 expressway component projects, the Deputy Prime Minister requested:

The Ministry of Construction focuses on directing investors, contractors and relevant agencies and units not to be negligent or subjective, continue to proactively and actively implement further efforts, determined to complete the opening of the main expressway of all 5 projects before April 30, 2025.

Complete all 5 projects before June 30, 2025; complete rest stops and intelligent traffic management systems (ITS), toll collection systems (ETC), vehicle weight inspection (KTTTX) in 2025; at the same time, ensure the quality of the project, ensure supervision and construction in accordance with procedures and regulations.

Regarding the site clearance of the Van Ninh - Cam Lo Expressway Component Project in Quang Tri province, the Deputy Prime Minister requested the Provincial Party Secretary to focus on directing and mobilizing the entire political system of Quang Tri province to urgently participate, promote mobilization, persuasion, propaganda, create support, consensus and unity of the people.

Ensuring the handover of the site as soon as possible, requiring the whole site to be handed over to the contractor by the end of March 2025 at the latest so as not to affect the progress of the Van Ninh - Cam Lo expressway component project.

The Deputy Prime Minister assigned the Ministry of Agriculture and Environment to study and review the provisions of the Land Law and relevant decrees to guide the assessment of the direct impact on the lives and health of people due to the construction of component projects in the area according to the proposal of the People's Committee of Quang Binh province so that investors can implement it synchronously and consistently.

PHẠM ĐÔNG
TIN LIÊN QUAN

Investment in Tuy Loan intersection on Da Nang - Quang Ngai expressway

|

The Ministry of Transport is adjusting the Da Nang - Quang Ngai expressway project and submitting it to the Prime Minister for assignment to the Tuy Loan intersection management agency.

Removing difficulties for Ninh Binh - Hai Phong expressway project

|

The Deputy Prime Minister requested urgent resolution of the problems of the expressway project through Hai Phong and the 9km section in Thai Binh province.

Investment in expanding Ho Chi Minh City - Trung Luong - My Thuan expressway

|

The Deputy Prime Minister requested to urgently propose policies and funding needs for site clearance for the entire Ho Chi Minh City - Trung Luong - My Thuan expressway.

A special gift that female general Nguyen Thi Dinh gave Uncle Ho on his 79th birthday

|

Coming to the Ho Chi Minh Museum, visitors can admire the scarves sent by the first female general of Vietnam to the Doctor on his 79th birthday.

After more than 1 year of acquisition, the land in the heart of Ben Tre city is overgrown with grass

|

Ben Tre - The land was auctioned to build a hospital but failed. After 1 year of recovery, it is still an empty lot, overgrown with grass in Ben Tre City.

Ho Chi Minh City flooded, people look forward to completing the flood prevention project

|

Ho Chi Minh City is often deeply flooded due to rain and high tides, people hope to soon complete flood prevention projects to escape living with water.

927 Quang Nam enterprises closed after the first 4 months of 2025

|

Quang Nam - The number of enterprises withdrawing from the market has increased sharply, reflecting that the investment environment still has many difficulties and challenges.

Workers urgently repair damaged roads in Duyen Hai before heavy rain

|

Tra Vinh - Workers urgently repair a road about 6.5km long with 240 damaged points regardless of rain, sun or Saturday, Sunday.

Investment in Tuy Loan intersection on Da Nang - Quang Ngai expressway

PHẠM ĐÔNG |

The Ministry of Transport is adjusting the Da Nang - Quang Ngai expressway project and submitting it to the Prime Minister for assignment to the Tuy Loan intersection management agency.

Removing difficulties for Ninh Binh - Hai Phong expressway project

Phạm Đông |

The Deputy Prime Minister requested urgent resolution of the problems of the expressway project through Hai Phong and the 9km section in Thai Binh province.

Investment in expanding Ho Chi Minh City - Trung Luong - My Thuan expressway

PHẠM ĐÔNG |

The Deputy Prime Minister requested to urgently propose policies and funding needs for site clearance for the entire Ho Chi Minh City - Trung Luong - My Thuan expressway.