Land clearance problems, Mo Cay bridge project is about 40% behind schedule

Thành Nhân |

Ben Tre - Due to land clearance problems, the construction volume of the Mo Cay bridge project has only reached about 18% of the contract value, about 40% behind schedule compared to the plan.

The Mo Cay Bridge project is part of a project to improve the clearance of road bridges across the national inland waterway - phase 1 (Southern area) is facing land clearance problems in Quarter 5 (Mo Cay town, Mo Cay Nam district, Ben Tre province).

As a household affected by the project, Mr. Nguyen Van Hung said that the total compensation for his land and house is about 800 million VND.

"This amount of money is not enough for me to buy land and rebuild a house, while the authorities also did not consider approving my family to buy resettlement land. For that reason, I have not yet handed over the site to the contractor for the above project, said Mr. Hung.

Mr. Hung said that his family has a total of 6 members, the recovered land area is more than 68 m2, the remaining 40 m2 is outside the project boundary, not enough for the family to live on.

"I hope that the authorities will review and have a reasonable solution so that people can settle down and make a living," said Mr. Hung.

Similarly, Mr. Truong Thanh Nhan (residing in Quarter 5, Mo Cay Town) said that he had previously proposed to buy a resettlement plot but it had not been resolved. Therefore, his family has not yet handed over the site to the investor to construct the project.

"Recently, I continued to petition the authorities of Mo Cay Nam district to request the purchase of a resettlement plot. They promised to consider it in the near future, but there is still no official document, said Mr. Nhan.

Du an cau Mo Cay bi vuong mat bang tai dia ban thuoc khu pho 5 (thi tran Mo Cay, huyen Mo Cay Nam, tinh Ben Tre). Anh: Thanh Nhan
The Mo Cay bridge project is stuck in the area of Quarter 5 (Mo Cay town, Mo Cay Nam district, Ben Tre province). Photo: Thanh Nhan

Talking to Lao Dong, Mr. Cao Xuan Linh - representative of the project investor - said that the Mo Cay bridge project started construction on March 19, 2024. Up to now, this project is about 40% behind schedule compared to the set plan.

According to Mr. Linh, the reason for the project's delay is due to land clearance problems, so the current construction volume has only reached about 18% of the contract value.

"The slow site clearance work is affecting the project's construction progress, especially the section in Quarter 5 (Mo Cay town, Mo Cay Nam district, Ben Tre province).

In the coming time, the investor hopes that the People's Committee of Mo Cay Nam district will speed up the site clearance progress, and hand over the remaining part in April 2025 to the contractor for construction. If the site handover progress is even slower, the project is at risk of not being completed by the end of 2025," said Mr. Linh.

Talking to Lao Dong Newspaper reporters over the phone on March 27, Mr. Nguyen Quoc Hung - Vice Chairman of Mo Cay Nam District People's Committee - said that the Mo Cay Bridge project is invested by the Waterway Project Management Board (Ministry of Construction), the total number of affected households is 119 households. Currently, the site has been cleared for 102 households and handed over to the construction contractor.

Mr. Hung said that 118 households have agreed to the compensation and support plan, only one household has not agreed to the compensation and land and house support plan.

"For the remaining households that have not yet handed over the land, it is because they have not been granted resettlement, and the locality is carrying out procedures to hand it over to the people soon," said Mr. Hung.

According to Mr. Hung, for households that have not agreed to the compensation and support plan for land and houses, in the coming time, the District People's Committee will work directly to resolve opinions and recommendations for the last time. If the land allocation is mobilized without complying, the land will be forcibly reclaimed.

Thành Nhân
RELATED NEWS

Wearily waiting for the handover of the resettlement land for the Rach Mieu 2 bridge project

|

Tien Giang - Many households in Tien Giang affected by the Rach Mieu 2 bridge project have not yet received resettlement land.

Rach Mieu Bridge is congested, traffic police of 2 provinces are trying to regulate

|

Tien Giang - At noon on February 1, traffic congestion occurred at Rach Mieu Bridge. Traffic police from two localities coordinated and worked hard to regulate traffic.

Workers work through Tet on Rach Mieu 2 Bridge project

|

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.

Accelerating site clearance, Ring Road 1 gradually emerges

|

Hanoi - The site clearance of Ring Road 1 from Hoang Cau to Voi Phuc is in the acceleration phase, with continuous machinery and openings.

The Standing Vice President of the Vietnam General Confederation of Labor suggested 4 issues at the Vinh Long Provincial Trade Union Congress

|

Vinh Long - Ms. Thai Thu Xuong - Permanent Vice President of the Vietnam General Confederation of Labor suggested a number of issues at the Provincial Trade Union Congress.

After 7 years of sluggish progress, the Cho Mai - Tan My road project in Hue has just completed the asphalt paving

|

HUE - The Cho Mai - Tan My road project with a total investment of nearly 200 billion VND, over 4km long, has just completed asphalt paving after many years of slow construction.

emotional performance of the Vietnam women's volleyball team

|

The Vietnam women's volleyball team left an impression on Thai and Vietnamese fans with their valuable performance in the 33rd SEA Games final.

A canteen wall collapsed at a driving test center in Lam Dong, 1 student died

|

Lam Dong - Lying in a hammock resting at a canteen in the premises of a driving test center, a student was killed by a wall collapsed.

Wearily waiting for the handover of the resettlement land for the Rach Mieu 2 bridge project

Thành Nhân |

Tien Giang - Many households in Tien Giang affected by the Rach Mieu 2 bridge project have not yet received resettlement land.

Rach Mieu Bridge is congested, traffic police of 2 provinces are trying to regulate

Thành Nhân |

Tien Giang - At noon on February 1, traffic congestion occurred at Rach Mieu Bridge. Traffic police from two localities coordinated and worked hard to regulate traffic.

Workers work through Tet on Rach Mieu 2 Bridge project

Thành Nhân |

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.