The building of Hue City Information Technology Center is "covered with tarpaulins" waiting for a new contractor

PHÚC ĐẠT - NGUYỄN LUÂN |

The building of the Hue City Information Technology (IT) Center has completed the rough construction but is being "covered in tarpaulin" while the investor is looking for a new contractor.

Ghi nhận của phóng viên Báo Lao Động ngày 25.6 cho thấy, trong lúc chủ đầu tư đang thực hiện các thủ tục lựa chọn nhà thầu mới, dự án xây dựng tòa nhà Trung tâm Công nghệ thông tin (CNTT) TP Huế vẫn trong tình trạng dang dở. Hạng mục chính là khối nhà làm việc đã cơ bản hình thành nhưng công trường gần như không có hoạt động thi công.
Records of Lao Dong Newspaper reporters on June 25 show that while the investor is carrying out procedures to select a new contractor, the project to build the Hue City Information Technology (IT) Center building is still unfinished. The main item is the working block that has basically been formed but the construction site has almost no construction activities (the project in the area is circled red).
Dự án đã hoàn thành phần thô. Phần lớn diện tích tòa nhà được trát vữa hoàn thiện, các khu vực chưa trát chủ yếu nằm bên trong công trình và đang chờ tiếp tục thi công các hạng mục còn lại trước khi sơn hoàn thiện.
The project has completed the rough construction. Most of the building area has been plastered to complete, the areas that have not been plastered are mainly inside the construction site and are waiting to continue construction of the remaining items before finishing painting.
Toàn bộ khu vực dự án được quây tôn kín. Không ghi nhận dấu hiệu thi công tại công trường.
The entire project area is surrounded by corrugated iron. No signs of construction are recorded at the construction site.
Nhiều vật liệu xây dựng vẫn được tập kết ngổn ngang bên trong công trình sau thời gian dài phải tạm dừng để chờ lựa chọn nhà thầu thay thế.
Many construction materials are still gathered haphazardly inside the project after a long period of temporary suspension to wait for the selection of a replacement contractor.
Một số hạng mục kỹ thuật của tòa nhà đã được triển khai, trong đó hệ thống phòng cháy chữa cháy và đường ống cấp thoát nước cơ bản đã được lắp đặt, đấu nối.
Some technical items of the building have been deployed, in which the fire prevention and fighting system and basic water supply and drainage pipes have been installed and connected.
Bên trong dự án không một bóng người.
Inside the project, there is not a soul.
Sau nhiều tháng không thi công, cây mai dương và cỏ dại phát triển um tùm cả bên trong lẫn khu vực xung quanh dự án.
After many months of no construction, casuarina trees and weeds grew lushly both inside and around the project area.
Theo quyết định điều chỉnh, dự án được gia hạn thời gian thực hiện đến hết năm 2026. Tuy nhiên, việc lựa chọn nhà thầu mới vẫn đang trong quá trình hoàn tất, trong khi quỹ thời gian còn lại không nhiều và TP Huế chuẩn bị bước vào cao điểm mùa mưa bão.
According to the adjustment decision, the project's implementation time is extended until the end of 2026. However, the selection of new contractors is still in the process of completion, while the remaining time is not much and Hue City is preparing to enter the peak of the rainy and storm season.

The project to build the Hue City Information Technology Center building cannot continue construction because the investor is carrying out procedures to select a new contractor to replace the old contractor consortium that was terminated because it did not meet the requirements for progress and project implementation capacity.

The project was approved for investment policy by the People's Committee of Thua Thien Hue province (now Hue City) in 2021 and adjusted in 2025. The project is built on a land area of 3,569 m2 in Thanh Thuy ward, invested by the Hue City IT Center, with a total investment of about 50.5 billion VND.

In which, package No. 12 includes the construction and equipment part of phase 1 with a bidding price of nearly 41 billion VND, including working blocks, security houses, two-wheeled parking garages and technical systems and construction equipment.

In December 2023, the joint venture of Cong Thanh Construction Development Investment JSC and Hoang Nhat Phat Trading Co., Ltd. was selected to win the bid with a price of nearly 34.6 billion VND, implementation time until June 30, 2025.

However, the implementation process did not ensure progress. After implementing about 44% of the contract volume, including the incurred part, the main contractor, Cong Thanh Company, was determined to no longer have sufficient financial capacity to continue construction. On July 18, 2025, Hue City IT Center issued a decision to terminate the contract with this contractor consortium.

By the time the contract was terminated, the investor had disbursed nearly 18.68 billion VND, equivalent to about 54% of the contract value. Of which, more than 70% is the value of the completed volume accepted, the rest is the advance payment. Two enterprises in the joint venture were also penalized for violating the progress, disclosing information on the National Bidding Network System and confiscating more than 1 billion VND of contract implementation guarantee money.

After terminating the contract with the old joint venture, the investor organized a re-bidding for the remaining work. Currently, package No. 16, including the construction and equipment part that has not been implemented of package No. 12, has completed the bidding opening step.

This bidding package has an estimated price of 26.5 billion VND, and a bid security value of 700 million VND. According to the National Bidding Network System, there are 3 joint ventures participating in the bidding. Among them, the joint venture with the lowest bid price after the price reduction is 23.78 billion VND; the remaining two joint ventures bid more than 24.36 billion VND and 25.59 billion VND respectively.

PHÚC ĐẠT - NGUYỄN LUÂN
RELATED NEWS

Hanoi plans to build 7 rental buildings in Viet Hung, with a total investment of more than 3,500 billion VND

|

Hanoi - The city plans to build 7 new housing projects with 12 - 13 floors and 2 basements, for rent in Viet Hung ward.

Request to definitively handle the case of 15 ancient villas and the Doi Cu Golf Club building in Da Lat

|

Lam Dong - Lam Dong Department of Agriculture and Environment requests to definitively handle existing issues related to 15 ancient villas and the Doi Cu Golf Club building.

Jennie (Blackpink) buys a 20 billion won building

|

Korean singer Jennie (Blackpink) attracts attention with a real estate deal worth 20 billion won.

Hanoi traffic police stick to the road to control alcohol concentration violations on a hot sunny day

|

Hanoi - Traffic police strengthen control of alcohol concentration violations on hot sunny days.

Hanoi workers struggle in a 10m2 rented room in hot weather

|

Hanoi - The intense heat covering makes it even more difficult for many workers far from home living in rented rooms of only about 10m2.

Agree on the plan to assign Hanoi as the investor of 2 40,000 billion VND railway projects

|

2 projects are expected to be assigned to Hanoi for implementation with a total investment of about 40,000 billion VND, aiming to relocate the existing railway line out of the inner city area.

List of collectives and individuals expected to be honored in the 2026 Glory of Vietnam Program

|

On the afternoon of June 25, 2026, the Selection Council for the 2026 Glory of Vietnam Program met to consider nominees from Central Committees, Ministries, sectors and Provincial and City Labor Federations, Central Industry Trade Unions and equivalents. Below are the expected selection of collectives and individuals to be considered and honored in the 2026 Glory of Vietnam Program.

Hanoi plans to build 7 rental buildings in Viet Hung, with a total investment of more than 3,500 billion VND

HOÀI ANH |

Hanoi - The city plans to build 7 new housing projects with 12 - 13 floors and 2 basements, for rent in Viet Hung ward.

Request to definitively handle the case of 15 ancient villas and the Doi Cu Golf Club building in Da Lat

Phúc Khánh |

Lam Dong - Lam Dong Department of Agriculture and Environment requests to definitively handle existing issues related to 15 ancient villas and the Doi Cu Golf Club building.

Jennie (Blackpink) buys a 20 billion won building

DƯƠNG HƯƠNG |

Korean singer Jennie (Blackpink) attracts attention with a real estate deal worth 20 billion won.