Overview of the second largest cable-stayed bridge construction site in Vietnam seen from above

NHÓM PV |

Soc Trang - At the Dai Ngai 1 bridge construction site, contractors are urgently constructing, aiming to complete the second largest cable-stayed bridge in Vietnam.

Tren cong truong xay dung cau Dai Ngai 1 – mot trong nhung du an ha tang giao thong trong diem quoc gia, cac nha thau dang khan truong trien khai thi cong dong loat nhieu hang muc quan trong thuoc Goi thau 15-XL, bao gom cau chinh, cau dan, cau cong vu va duong dan hai dau cau.
At the Dai Ngai 1 bridge project site, contractors are urgently constructing many important items under package 15-XL, including the main bridge, approach bridge, service bridge and approach roads at both ends of the bridge.
Nha thau da hoan thanh cong tac do be tong coc khoan nhoi dau tien cua tru P24, coc khoan nhoi cua tru P23. Day la 2 tru day vang chinh cua cau Dai Ngai 1.
The contractor has completed the first concrete pouring of bored piles for P24 pillars and bored piles for P23 pillars. These are the two main cable-stayed pillars of Dai Ngai 1 Bridge.
Tong toan tru P23 co 32 coc. Cac ky su va cong nhan dang tien hanh thi cong san dao giai doan 1, dong thoi gia cong long thep coc khoan nhoi cho cac hang muc tiep theo. -Dai dien deo ca cho biet, sau khi hoan thanh do be tong coc dau tien, nha thau tiep tuc trien khai cac coc tiep theo, trung binh moi coc mat 6 ngay de thi cong. Du kien den het thang 11 se hoan thanh cac coc khoan nhoi tru 24.
A representative of the Deo Ca Group Contractor consortium said that at pillar P23, engineers and workers are constructing the first phase of the canopy, processing bored pile steel cages for the next items. After completing the first deposit concrete pouring, the next deposits will be deployed with an average progress of 6 days/deposit.
cong truong da huy dong gan 100 nhan su, chia thanh 17 mui thi cong, bao gom cong nhan xay dung, ky su hien truong, can bo quan ly chat luong,...
The construction unit has mobilized nearly 100 personnel, divided into 17 construction teams, including construction workers, site engineers, and quality management officers.
Cong tac an toan lao dong, quan ly chat che moi hoat dong cua cac to chuc, ca nhan tham gia thuc hien goi thau duoc Lien danh nha thau chu trong. Dac biet khong duoc lo la trong viec dam bao an toan cho nguoi lao dong, tai san, may moc thiet bi… tren cong truong.
Labor safety and site management work was strictly implemented by the Joint Venture of Contractors.
He thong thiet bi thi cong hien dai nhu may khoan coc nhoi XCMG460D, may cau 300T, 150T, sa lan 800T, 5000T, may dao, xe lu... cung duoc phan bo deu tai cac mui thi cong cau chinh, cau dan va duong cong vu.
Modern equipment such as XCMG460D pile drilling machines, 300T, 150T cranes, 800T, 5,000T barges... are distributed evenly at the construction sites.
Cac nhanh cau cong vu ket noi quan trong trong cong tac van chuyen va thi cong tren song, cung duoc trien khai thi cong tich cuc. Cac to doi da hoan thanh viec dong thep hinh, han khung gia co, thi cong mat cau cong vu va lap dung lan can bao ve. Viec gia cong thep hinh tai bai va thi cong mat cau duoc thuc hien tren cac nhip tu T30 den T82, voi chieu dai trung binh moi nhip la 12 met.
For the bridge leading to the territory of Tra Vinh province, the contractor has constructed 10 bored piles, expected by the end of August, 2025 will complete the construction of the P15-P20 piles, basically completing the bridge in October 2026. Public service bridges for transportation on the river are also promoted.
Ban Quan ly du an 85 - Chu dau tu du an cau Dai Ngai - cho biet, den nay tien do thi cong cau Dai Ngai 1 dat khoang 4%; ve phan duong da hoan thanh cong tac dao boc huu co, dang trien khai cong tac dap cat.
Project Management Board 85 - Investor of Dai Ngai bridge project said - to date the project has reached about 4% progress. The road has been organically peeled off and is being sand-filled.
Truoc do, vao thang 12.2024, goi thau 15-XL chinh thuc duoc khoi cong. Du kien cau se hoan thanh va thong xe ky thuat vao thang 6.2028.
Dai Ngai 1 Bridge is more than 3km long, of which the main bridge is 2.59km long, 21.5m wide, crossing the Hau River in Dinh An channel, connecting Tra Vinh and Soc Trang provinces. The bridge has a cable-stayed structure, 2 A-shaped towers 110m high, the second largest cable-stayed bridge in Vietnam after Can Tho Bridge. Expected to be completed and technically opened to traffic in June 2028.
NHÓM PV
TIN LIÊN QUAN

Complete the first bored pile of the Dai Ngai 1 bridge cable-stayed pillar

|

Soc Trang - The first bored pile of the Dai Ngai 1 bridge cable-stayed pillar has been completed, and all piles are expected to be completed in 2025.

The largest cable-stayed bridge in Ho Chi Minh City connecting Nha Be - Can Gio awaits planning

|

Ho Chi Minh City plans to submit an investment policy for Can Gio bridge, 7.3km long, connecting Nha Be district with Can Gio, in 2025, after the city's general planning is approved.

Construction of cable-stayed bridge across Hau River begins

|

Soc Trang - Dai Ngai 1 Bridge across Dinh An channel of Hau River is the second largest cable-stayed bridge in Vietnam and has just started construction.

Clarifying what to do in the province, what to do in the commune when leaving the district level

|

The Deputy Prime Minister said that when deciding on authority, it is necessary to focus on what should be upgraded to province and what should be upgraded to commune when the district level is no longer there.

Ba Ria - Vung Tau quickly controls the COVID-19 outbreak in schools

|

Ba Ria - Vung Tau - The COVID-19 epidemic with 3 infections at a high school in Ba Ria City has been quickly isolated, controlled, and closely monitored.

The Ministry of Education and Training eliminates 4 admission methods for universities and colleges in 2025

|

The Ministry of Education and Training (MOET) has finalized 19 admission methods for university and college admissions in 2025, of which 4 methods were eliminated and 3 more than in 2024.

CEO Nguyen Duc Thach Diem resigns, Sacombank shares suddenly increase the ceiling

|

STB shares increased the ceiling to 42,250 VND at the beginning of the session on May 21, after Ms. Nguyen Duc Thach Diem sent a letter of resignation from the position of General Director of Sacombank.

Illegal use of drugs is a crime, great pressure on detention facilities

|

Drafting a law to supplement the crime of illegal use of drugs, National Assembly deputies have given two views on whether drug addicts are patients or criminals.

Complete the first bored pile of the Dai Ngai 1 bridge cable-stayed pillar

PHƯƠNG ANH |

Soc Trang - The first bored pile of the Dai Ngai 1 bridge cable-stayed pillar has been completed, and all piles are expected to be completed in 2025.

The largest cable-stayed bridge in Ho Chi Minh City connecting Nha Be - Can Gio awaits planning

MINH QUÂN |

Ho Chi Minh City plans to submit an investment policy for Can Gio bridge, 7.3km long, connecting Nha Be district with Can Gio, in 2025, after the city's general planning is approved.

Construction of cable-stayed bridge across Hau River begins

PHƯƠNG ANH |

Soc Trang - Dai Ngai 1 Bridge across Dinh An channel of Hau River is the second largest cable-stayed bridge in Vietnam and has just started construction.