Prime Minister directs immediate replacement of weak cadres and civil servants

PHẠM ĐÔNG |

The Prime Minister directed the strict handling of collectives and individuals who deliberately slow down the disbursement of public investment capital; immediately replace weak cadres and civil servants.

Prime Minister Pham Minh Chinh has just signed Official Dispatch No. 162/CD-TTg dated September 11, 2025, requesting ministries, branches and localities to focus on promoting the disbursement of public investment capital in 2025.

According to the telegram, from the beginning of 2025 to now, the Government and the Prime Minister have issued many documents to strongly direct ministries, central and local agencies in allocating and disbursing public investment capital in 2025.

The disbursement results by the end of August 2025 are estimated at 46.3% of the plan assigned by the Prime Minister, higher than the same period in 2024 (40.4%); of which 9 ministries, central agencies and 22 localities have a disbursement rate above the national average; 29 ministries, central agencies and 12 localities have a disbursement rate below the national average.

The Prime Minister requested ministries, central and local agencies to develop a detailed disbursement plan for each project and control the progress weekly and monthly. Focus on speeding up site clearance, construction progress, timely removal of difficulties and obstacles related to land, resources, etc.

Specifically assign leaders responsible for monitoring progress, promptly removing difficulties and obstacles according to their authority or proposing to competent authorities to resolve them. Proactively transfer capital from slow-disbursement projects to well-disbursed projects and need to supplement capital according to regulations.

Propose to adjust the 2025 public investment capital plan of the Ministry, its agencies and localities (if any), and send it to the Ministry of Finance before September 20, 2025.

At the same time, strengthen discipline and order in disbursing public investment capital, strictly handle according to regulations that collectives and individuals intentionally slow down the progress of allocating and disbursing public investment capital; immediately replace cadres, civil servants and public employees who are weak and have limited capacity and responsibility; resolutely handle negative and corrupt behaviors in managing and using public investment capital.

The Provincial Party Secretaries, City Party Committees and Chairmen of Provincial and Municipal People's Committees direct Party Committee Secretaries, Chairmen of Commune, Ward and Special Zone People's Committees to clearly identify and further promote their roles and responsibilities in implementing site clearance for projects.

Resolutely do not let the implementation of local government at both levels affect the progress of site clearance and disbursement of public investment capital for projects in the area.

Strictly handle according to regulations for cadres who do not perform properly or lack responsibility in performing assigned duties and responsibilities; be fully responsible to the Government and the Prime Minister for this matter.

Ministries, central and local agencies synthesize and report on the disbursement of public investment capital of their ministries, agencies and localities to the Ministry of Finance before the 20th of each month for synthesis and reporting to the Government and the Prime Minister according to regulations.

In particular, it is necessary to clearly report the achieved results, difficulties, problems, causes and propose drastic and effective solutions to promote the disbursement of public investment capital in 2025 of ministries, agencies and localities.

The Ministry of Finance directs the State Treasury to promptly pay the completed volume, promote payment through the State Treasury's online public service; direct functional units to ensure payment sources for projects; promptly handle problems in payment, settlement, negotiation, signing of agreements, and withdrawal of capital from sponsors.

PHẠM ĐÔNG
RELATED NEWS

The Deputy Prime Minister spoke about people's concerns when handling pollution only stops on paper

|

The Deputy Prime Minister said that people question the effectiveness of many pollution treatment measures that are just on paper and not yet put into practice.

Prime Minister directs Quang Tri province to continue to reorganize and streamline the apparatus

|

The Prime Minister directed Quang Tri province to continue to reorganize and streamline the apparatus; review and publicize administrative procedures.

Allocating more than 33 billion VND in public investment plan with state budget capital to 4 localities

|

The Deputy Prime Minister assigned to supplement the central budget public investment plan for 4 localities including Tuyen Quang, Son La, Gia Lai, Kien Giang.

The huge Mid-Autumn Festival lantern worth hundreds of millions of VND lights up the streets of Tuyen Quang ward

|

Tuyen Quang - The Mid-Autumn Festival in Tuyen Quang is famous for its giant lanterns.

Do not let power projects get stuck due to delayed administrative procedures

|

The Deputy Prime Minister requested 3 corporations and 1 military enterprise to resolutely implement the power project and not to let the power project stall due to delayed administrative procedures.

Husband goes to work far away, wife stays at home, has an affair and has a child with another person - Part 1

|

The 9th hour - Husband leaves home to work far away, sending money to support the family. But in loneliness, his wife had an affair and became pregnant with someone else. What will happen to this family?

Vietnam continues to contribute to bringing peace at the Thailand - Cambodia border

|

Vietnam welcomes the positive developments between Cambodia and Thailand, and will continue to strive to contribute to bringing peace at the border between the two countries.

Vietnam General Confederation of Labor guides on collecting union funds

|

Grassroots trade unions are allowed to use 75% of total trade union budget revenue, according to the guidance document of the Vietnam General Confederation of Labor.

The Deputy Prime Minister spoke about people's concerns when handling pollution only stops on paper

PHẠM ĐÔNG |

The Deputy Prime Minister said that people question the effectiveness of many pollution treatment measures that are just on paper and not yet put into practice.

Prime Minister directs Quang Tri province to continue to reorganize and streamline the apparatus

PHẠM ĐÔNG |

The Prime Minister directed Quang Tri province to continue to reorganize and streamline the apparatus; review and publicize administrative procedures.

Allocating more than 33 billion VND in public investment plan with state budget capital to 4 localities

PHẠM ĐÔNG |

The Deputy Prime Minister assigned to supplement the central budget public investment plan for 4 localities including Tuyen Quang, Son La, Gia Lai, Kien Giang.