Vinh Te Canal and records from 200 years ago

Lục Tùng - Phong Linh |

An Giang – Many new studies show that Vinh Te canal set a record 200 years ago.

Record 4 postponements

As planned, at the 200th Anniversary of the completion of Vinh Te Canal (1824-2024) held in mid-November 2024 in Chau Doc City (An Giang), Vinh Te Canal will receive the record of "The longest manually dug canal in Vietnam".

Thoai Ngoc Hau Nguyen Van Thoai, nguoi co cong lon trong viec chi huy dao kenh Vinh Te.
Thoai Ngoc Hau Nguyen Van Thoai, who had great contributions in commanding the digging of Vinh Te canal. Photo: Luc Tung.

By applying technology and comparing many reliable historical sources, several recent research projects have proven that 200 years ago, Vinh Te Canal set a record for both the number of times and the duration of construction delays.

From comparing the perpetual calendar, many researchers have converted the time recorded in the old way in the Nguyen Dynasty's historical books (usually recording months, rarely recording days) and then applied the rule of rounding months to events that only recorded months, thereby determining that Vinh Te Canal was completed after 53 months of construction (December 15, 1819 - May 1824). However, during this time, there were 4 postponements and the construction postponement time was up to 43 months, accounting for 81.13% of the total time.

The first postponement was from March 1820 to January 1821, the main reason being that King Gia Long passed away and King Minh Mang had just ascended the throne.

Kenh Vinh Te doan di qua cho Tinh Bien (thi xa Tinh Bien, An Giang)
Vinh Te Canal section passing through Tinh Bien market (Tinh Bien town, An Giang). Photo: Luc Tung.

Immediately after ascending the throne to replace his father, King Minh Mang granted 16 graces. The postponement of mobilizing troops and people to dig Vinh Te canal was also part of the policy of the newly enthroned king.

The second postponement from January 1821 to March 1822 was due to the outbreak of an epidemic that today, according to world medical documents, coincided with the first global pandemic, which lasted for 4 years (1817-1823). The book "Dai Nam Thuc Luc" also recorded: "Now that the epidemic is circulating, it is appropriate to let the army and people rest and suspend all work."

The third postponement was from March 1822 to February 1823 due to an epidemic outbreak in Gia Dinh. And the fourth postponement was from April 1823 to February 1824 due to the impact of flooding on the Mekong River.

According to many researchers, up to now there has been no historical source showing that any contemporary project had the same number of times and days of suspension of operations as the Vinh Te canal project.

Real mining time 10 months

From the determination of the delay time, new studies also determined that the actual time to complete the digging of Vinh Te Canal only took 10 months. This point is different from the data that some sources have long said that the digging "lasted for 5 years". However, this new opinion is quite convincing both scientifically and practically.

Tuyen Trung Hau Nguyen Van Tuyen, nguoi co 2 lan tham gia chi huy dao kenh Vinh Te.
Marquis Tuyen Trung Nguyen Van Tuyen, who twice participated in commanding the digging of Vinh Te canal. Photo: Luc Tung.

Dr. Chau Huu Hau (An Giang) in his research work: "Thoai Ngoc Hau and the Vinh Te canal digging project" affirmed that there were 3 canal digging phases with a total digging time of 10 months.

According to calculations based on Nguyen Dynasty historical documents, Mr. Hau said that the total length of the canal was actually dug 37,190m because there was a section connecting to the existing Giang Thanh River... Of which, the first digging time was 3 months (December 15, 1819 to March 15, 1820); the second time was also 3 months (February 1823 to April 1823); the third time was 4 months (February 1824 to May 1824).

In the first excavation, it was led by Nguyen Van Thoai (1761-1829), Phan Van Tuyen (1763-1831), later given the national name Nguyen Van Tuyen and Nguyen Van Ton (1763-1820).

Kenh Vinh Te duoc danh gia la cong trinh co y nghia ve an ninh quoc phong, phat trien nong nghiep, thuong mai...
Vinh Te Canal is considered a project of significance in terms of national security, agricultural development, trade... Photo: Luc Tung.

In the second excavation, the commanding personnel were different between the two official historical sources of the Nguyen Dynasty. “Dai Nam Thuc Luc” recorded that the Governor and Deputy Governor of Gia Dinh citadel at that time were Le Van Duyet (1764-1832) and Truong Tan Buu (1752-1827). Meanwhile, “Dai Nam Chinh Bien Liet Truyen” recorded Nguyen Van Thoai and Tran Cong Lai (?-1824). In the third excavation, there were Nguyen Van Thoai, Nguyen Van Tuyen and Tran Cong Lai.

Although there are differences in some characters among historical documents, they all have one thing in common: they record that the command of digging Vinh Te canal was carried out by a group of generals, not the role of an individual.

Lục Tùng - Phong Linh
RELATED NEWS

Marquis Tuyen Trung - famous general who commanded the digging of Vinh Te canal twice

|

Dong Thap - It is very meaningful to review the contributions of General Tuyen Trung Hau, the general who twice participated in commanding the digging of Vinh Te canal - on the occasion of the 200th anniversary of the completion of this canal.

About the resting place of the famous general who commanded the digging of Vinh Te canal

|

Dong Thap - On the occasion of the 200th anniversary of the completion of Vinh Te Canal, it will be very meaningful to visit the resting place of the general who directly commanded the project.

Roadmap for illegal dumping from the Lao Cai Central Social Housing Project

|

Lao Cai - Reporters' records show that waste soil from the Yen Ninh social housing project is not transported to the licensing point but is constantly changing locations.

Many officials in Ca Mau have to retake civil servant and public employee exams

|

Tomorrow, March 19, many leading officials in Ca Mau will take recruitment exams for civil servants and public employees even though they have worked for a long time.

Israel hit by a series of missiles after assassination of Iranian security leader

|

Iran launched missiles at Tel Aviv in retaliation for Israel's assassination of senior security leader Ali Larijani.

Stocks maintain green color against strong net selling by foreign investors

|

The recovery of the stock market has not yet brought peace of mind as liquidity is still maintained at a low level, showing that participating cash flow is still cautious.

VGCL holds working meeting to prepare for the 14th Vietnam Trade Union Congress

|

Hanoi - March 18, the VGCL organized meetings of sub-committees to prepare for the 14th Vietnam Trade Union Congress, term 2026 - 2031.

Current status of Duc Giang chemical plant after a series of leaders were prosecuted

|

Lao Cai - Recording the current status of the factory after initiating a case at Duc Giang Chemical Group shows that the units are still operating, and workers are working normally.

Marquis Tuyen Trung - famous general who commanded the digging of Vinh Te canal twice

Lục Tùng - Phong Linh |

Dong Thap - It is very meaningful to review the contributions of General Tuyen Trung Hau, the general who twice participated in commanding the digging of Vinh Te canal - on the occasion of the 200th anniversary of the completion of this canal.

About the resting place of the famous general who commanded the digging of Vinh Te canal

Lục Tùng - Phong Linh |

Dong Thap - On the occasion of the 200th anniversary of the completion of Vinh Te Canal, it will be very meaningful to visit the resting place of the general who directly commanded the project.

An Giang: Một người tử vong trong vụ chìm ghe trên kênh Vĩnh Tế

Chiến Khu |

An Giang – Trong quá trình chở cây cất nhà từ thiện, ghe bị chìm trên kênh Vĩnh Tế  khiến người đàn ông tử vong.