31 projects overdue for commencement, Gia Lai requests clarification of responsibility

Hoài Phương |

Gia Lai still has 52 projects that have not started construction, of which 31 projects have expired. The province requests clarification of responsibilities and acceleration of progress in the last months of the year.

Over the past time, Gia Lai province has promoted investment attraction and improved the investment and business environment. Many new projects have been attracted, some have completed procedures, started construction and gradually put registered capital into practice.

However, the implementation progress is not commensurate with the number, scale of projects and development requirements of the province. To date, there are still 52 projects in 34 communes and wards that have not started construction; of which 31 projects in 22 communes and wards have exceeded the deadline for starting construction.

The main obstacles are related to planning, compensation, site clearance, land allocation, land lease, land use purpose conversion... Some areas still have many projects that have not started such as Quy Nhon Bac, Quy Nhon, Phu Thien, Phu My...

In addition, some agencies and localities have not coordinated and handled dossiers decisively, and have not closely followed deadlines. Some investors have not proactively completed procedures, have not focused sufficient resources, and are slow to report progress and implementation capital. In some cases, construction has started but has not been implemented substantively on the ground.

At the meeting on September 14 on the situation and progress of preparation for commencement and removal of obstacles for projects, Standing Vice Chairman of Gia Lai Provincial People's Committee Nguyen Tuan Thanh requested units, localities and investors to focus on removing difficulties and accelerating the progress of non-budget projects.

Agencies and localities must review each project, each procedure; clearly identify problems, causes, handling agencies, completion deadlines and commencement milestones. In the immediate future, focus on 52 projects that have not started construction, especially 31 projects that have exceeded the time to start construction and projects committed to start construction in September, Q4/2026.

For communes and wards with projects that have not yet started construction, the Secretary and Chairman of the Commune-level People's Committee must directly inspect the site weekly, work with investors and relevant agencies to handle problems. Localities that delay projects due to subjective reasons must be responsible to the Provincial People's Committee.

Resolutely handle projects that are slow and prolonged, investors who lack capacity, are slow or do not properly implement commitments. In case they are no longer capable of implementation or violate, they must promptly propose to terminate operations and recover projects, not to let them be prolonged, occupying land, causing waste of resources," Mr. Nguyen Tuan Thanh directed.

Mr. Nguyen Tuan Thanh assigned the Department of Finance to urgently review 52 projects that have not started construction, especially 31 projects that have exceeded the time to start construction; clearly classify the causes belonging to state agencies, localities or investors.

Hoài Phương
RELATED NEWS

Colonel Tran The Phan becomes Commander of Gia Lai Military Command

|

Gia Lai - Colonel Tran The Phan holds the position of Commander of the Provincial Military Command, replacing Colonel Nguyen The Vinh - who has been transferred to a new task in Da Nang City.

Gia Lai plans to dissolve and merge many units in 2026

|

Gia Lai plans to merge, consolidate, and dissolve many public non-business units and transfer some functions and tasks in 2026.

Dak Lak tightens public investment discipline, resolutely transfers capital for slow-progress projects

|

Dak Lak - Provincial functional agencies are tightening public investment discipline, resolutely transferring capital for projects that are behind schedule for a long time.

Two father and son, the golden generation of Japanese sports, light the torch at ASIAD 20

|

Mr. Shigenobu and Mr. Koji Murofushi - two outstanding athletes of Japan - also participated in the ASIAD 20 torch lighting ceremony.

Phu Dinh sluice reaches the finish line, closing the days people slept with high tide water

|

Ho Chi Minh City - After many years of experiencing high tides, the Phu Dinh tide control culvert area has now changed significantly with wider and more spacious roads.

Nha Phuong speaks out after the scandals related to Truong Giang

|

Amidst the debates related to Truong Giang, Nha Phuong for the first time clarified her reaction to the information surrounding her husband and family.

From the 80-year-old teacher's class, Ho Chi Minh City reviews and opens up regular continuing education for children in the whole area's charity class

|

Ho Chi Minh City - From the story of the class of a nearly 80-year-old lottery ticket seller, a new direction is opened for children in Ho Chi Minh City's charity classes.

Floodwater rises, more than 600 households in Thanh Hoa are still flooded

|

Thanh Hoa - Floodwaters continue to rise, causing more than 600 households in Nong Cong commune to be flooded, and 70 households to be isolated.

Colonel Tran The Phan becomes Commander of Gia Lai Military Command

Hoài Phương |

Gia Lai - Colonel Tran The Phan holds the position of Commander of the Provincial Military Command, replacing Colonel Nguyen The Vinh - who has been transferred to a new task in Da Nang City.

Gia Lai plans to dissolve and merge many units in 2026

Hoài Phương |

Gia Lai plans to merge, consolidate, and dissolve many public non-business units and transfer some functions and tasks in 2026.

Dak Lak tightens public investment discipline, resolutely transfers capital for slow-progress projects

BẢO TRUNG |

Dak Lak - Provincial functional agencies are tightening public investment discipline, resolutely transferring capital for projects that are behind schedule for a long time.