4 trillion-dong projects connecting Ho Chi Minh City with Long Thanh airport

MINH QUÂN |

Ho Chi Minh City will complete Ring Road 3, An Phu intersection, start construction of Ring Road 2 and expand Ho Chi Minh City - Long Thanh expressway in 2025 to increase connectivity to Long Thanh airport.

Complete Ring Road 3 section and An Phu intersection by the end of 2025

Long Thanh Airport (Dong Nai province) is expected to complete phase 1 by the end of 2025, with a capacity to serve 25 million passengers and 1.2 million tons of cargo per year.

According to the Ho Chi Minh City Department of Transport, to increase connectivity with Long Thanh airport, the city is speeding up the completion and commencement of a series of key projects.

By the end of this year, Ho Chi Minh City will complete the An Phu intersection project and the Ring Road 3 section through Thu Duc City.

Nut giao Vanh dai 3 voi cao toc TPHCM - Long Thanh, phia xa la cau Nhon Trach.  Anh: Minh Quan
The intersection of Ring Road 3 with Ho Chi Minh City - Long Thanh Expressway, in the distance is Nhon Trach Bridge. Photo: Minh Quan

Beltway 3 through Ho Chi Minh City is more than 47 km long, of which the section through Thu Duc City is more than 14 km long, designed with an elevated road with 4 lanes in phase 1.

This route connects from Ho Chi Minh City - Long Thanh - Dau Giay Expressway, passes through Thu Duc City and ends at Tan Van Intersection (Binh Duong). The project is currently being accelerated and is expected to open to traffic by the end of 2025.

Du an nut giao An Phu (TP Thu Duc).  Anh: Anh Tu
An Phu Intersection Project (Thu Duc City). Photo: Anh Tu

The An Phu intersection project (Thu Duc City) has a total investment of more than 3,400 billion VND, and has now reached more than 65% of the total construction volume.

Of which, Ba Dat bridge on the Ho Chi Minh City - Long Thanh - Dau Giay expressway and Giong Ong To 2 bridge (connecting Mai Chi Tho street with Dong Van Cong) have been completed.

Currently, 5 overpasses and 2 underpasses in this area are being urgently deployed to ensure the completion of the entire project by the end of 2025.

Construction of two sections of Ring Road 2 and expansion of expressway access roads commenced

Along with that, Ho Chi Minh City will start construction of two sections of Belt Road 2 through Thu Duc City and expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway.

The two sections of Ring Road 2 include: the section from Phu Huu Bridge to Vo Nguyen Giap Street (3.5 km long) and the section from Vo Nguyen Giap Street to Pham Van Dong Street (2.8 km long).

Vanh dai 2 TPHCM gan cau Phu Huu (TP Thu Duc).  Anh: Anh Tu
Ho Chi Minh City Ring Road 2 near Phu Huu Bridge (Thu Duc City). Photo: Anh Tu

The total investment for these two sections is over VND13,800 billion, of which site clearance costs account for about VND7,500 billion. The project is expected to start in the second quarter of 2025 and be completed before June 30, 2026.

Beltway 2 will have a clearance width of 67 m, with parallel roads 17 m wide on each side, including 3 lanes. The middle part will be reserved for future expansion. This project affects about 1,166 cases and the total land acquisition area is more than 61 hectares.

Duong dan cao toc TPHCM - Long Thanh se duoc mo rong len 8 lan.  Anh: Anh Tu
The Ho Chi Minh City - Long Thanh Expressway will be expanded to 8 lanes. Photo: Anh Tu

The 4km Ho Chi Minh City - Long Thanh - Dau Giay Expressway (section from An Phu intersection to Ring Road 2) will be expanded from 4 to 8 lanes, including upgrading Muong Kenh Bridge and Do Xuan Hop overpass.

Because there is no need for site clearance (because it has been done before), the project has a total investment capital of nearly 1,000 billion VND from the Ho Chi Minh City budget.

The project is expected to start construction in the third quarter of 2025 and be completed in the third quarter of 2026.

MINH QUÂN
TIN LIÊN QUAN

No change in target to complete Long Thanh airport by 2025

|

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Ho Chi Minh City's Ring Road 3 sprints to the finish line

|

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

Ho Chi Minh City - Long Thanh Expressway is about to escape traffic jams

|

Ho Chi Minh City spends nearly VND1,000 billion to expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway from 4 to 8 lanes, with plans to start construction in 2025 and complete in 2026.

Kinh Bac cultural characteristics in Hoa Minzy's MV "Bac Bling"

|

"Bac Bling" (Bac Ninh) by Hoa Minzy has a close, emotional lyrics and is full of pride in her homeland. The MV recreates many unique cultural features of Kinh Bac region.

Unexpected forecast for gold prices in the short term

|

In the short term, economic researchers believe that gold prices may gradually stabilize, not many more shocks like before.

structure of the Ministry of Education and Training after streamlining the apparatus

|

The Ministry of Education and Training has 18 units, reducing 5 units after the arrangement and streamlining.

270 social housing units for rent to be sold in Gia Lam district

|

The social housing project in Dang Xa 2 new urban area, Gia Lam district (Hanoi) has 270 apartments converted from rent to sell, with an area of 44.75-69.38 m2.

Strictly prohibiting free commercial banks from increasing interest rates

|

The Prime Minister requested a strict ban on free commercial banks increasing interest rates without direction, unfair competition, and inequality.

No change in target to complete Long Thanh airport by 2025

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Ho Chi Minh City's Ring Road 3 sprints to the finish line

MINH QUÂN |

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

Ho Chi Minh City - Long Thanh Expressway is about to escape traffic jams

MINH QUÂN |

Ho Chi Minh City spends nearly VND1,000 billion to expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway from 4 to 8 lanes, with plans to start construction in 2025 and complete in 2026.