On January 27, Mr. Vo Dang Dung - Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh ward and Mr. Nguyen Sy Doan - Chairman of the Ward People's Committee together went to the scene by motorbike to inspect and urge the progress of site clearance for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.
Talking to Lao Dong reporters at the scene, Party Secretary of Khuong Dinh Ward Vo Dang Dung said that the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, is 1.52km long, involving 736 households, individuals and 13 organizations having to implement site clearance.
As of January 27, Khuong Dinh ward has completed site clearance for 12/13 agencies and units; 31 households have handed over land and are demolishing works to implement the project according to regulations.
For the remaining about 700 households and individuals, the ward has completed the measurement and inventory of the current situation and publicly announced the draft of more than 250 compensation, support, and resettlement plans.
In the process of publicizing, local authorities continue to organize direct dialogues to listen to people's thoughts and aspirations, summarize and reflect to superiors, ensuring compliance with the provisions of law.


Over the past time, the government of Khuong Dinh ward has focused on leading and drastically directing the site clearance of the Ring Road 2.5 project, closely following the directions of the City Party Committee, People's Council, and Hanoi People's Committee.
The ward has established a steering committee for site clearance, assigning specific tasks to members of the Standing Committee of the Party Committee and leaders of the Ward People's Committee to organize implementation.
Party Secretary and Chairman of the Ward People's Committee directly go to the scene an average of 2 times a day to inspect and urge progress, and at the same time propagate and mobilize people to comply with the land clearance policy.
When unexpected opinions and recommendations arise, ward leaders also proactively arrange time to go to the scene as soon as possible to handle them.



Secretary of the Khuong Dinh Ward Party Committee Vo Dang Dung said that in the process of implementing site clearance for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, local authorities still face some difficulties due to the project being prolonged for many years.
The implementation from the 2000s to now has been more than 25 years, during that process people have bought, sold, transferred, and built works within the project scope, causing many obstacles when implementing land recovery.
In addition, people currently complain the most related to compensation, support and resettlement policies.
We always promptly grasp the thoughts and aspirations of the people to report to the City Party Committee, People's Council, and Hanoi People's Committee for consideration and promulgation of appropriate policies, ensuring legitimate rights for the people in the land clearance process," Mr. Dung emphasized.


Khuong Dinh ward identified this as a key political task in 2026 and is determined to complete the site clearance of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, in accordance with the direction of Hanoi City.
In the immediate future, in the first quarter, Khuong Dinh ward will hand over about 500m out of a total of 1,520m of route length to the construction unit to implement the project.