The Ministry of Construction requests to check the quality of Song Lo bridge in Phu Tho

Xuyên Đông |

The Ministry of Construction has just issued a document requesting the inspection of the quality of Song Lo bridge, reporting before November 15.

According to the official dispatch of the Ministry of Construction, through press reports on the quality of some Song Lo bridge piers in Phu Tho province, they have seriously degraded. Some concrete pillars were exposed with load-bearing steel reinforcements, affecting the safety of the project.

The Ministry of Construction requests the People's Committee of Phu Tho province and assigns the State Appraisal Department of Construction Quality and the Vietnam Road Administration to carry out a number of contents as follows:

The People's Committee of Phu Tho province assigned the Department of Construction to organize an inspection of the current status of the project, direct and request the unit managing, exploiting and using the Song Lo bridge project and relevant agencies to comply with the provisions of Clause 1, Article 40 of Decree No. 06/2021/ND-CP, including:

Organize the quality inspection of the project.

Take necessary measures such as limiting the use of works, isolating dangerous areas or immediately repairing damages in cases where there is a risk of affecting the safety of use and safety of works.

Develop and adjust traffic plans in accordance with reality to ensure the safety of people and property when traveling through this area.

Report the implementation results to the Ministry of Construction before November 15, 2025.

Cau song Lo duoc dua vao su dung cach day 10 nam. Anh: To Cong.
The Lo River Bridge was put into use 10 years ago. Photo: To Cong

The Ministry of Construction assigns the State Appraisal Department of Construction Quality based on its functions and tasks to monitor, guide and coordinate with the Department of Construction in organizing the inspection and assessment of the quality and load-bearing capacity of the Song Lo bridge project.

Assign the Vietnam Road Administration, based on its functions and tasks, to guide and coordinate with relevant agencies under the People's Committee of Phu Tho province in organizing the control of vehicles traveling through the Song Lo bridge, dividing traffic, organizing traffic and guiding people and vehicles traveling in both directions of the bridgehead.

Previously, Lao Dong Newspaper reported that the Lo River bridge in Doan Hung commune, Phu Tho province, after 10 years of use, is now in a state of disrepair. After the water level of the Lo River receded, it was discovered that the T3 pillar was damaged and had exposed steel Beds, causing global insecurity.

Currently, the authorities have announced the limit on the carrying capacity of vehicles traveling through the Lo River Bridge, only allowing two-wheeled motorbikes, three-wheeled motorbikes, motorbikes (including electric motorbikes), rudimentary road vehicles and traffic participants to travel through the bridge.

Xuyên Đông
RELATED NEWS

Lo River Bridge damaged, people are more worried about riverbank erosion

|

Phu Tho - Along with the damage to the Lo River bridge affecting their lives, the riverbank landslide also makes people feel insecure.

Banning all cars across the Lo River bridge in Phu Tho

|

Phu Tho - The provincial Department of Construction has just announced the adjustment of traffic flow through the Lo River Bridge, Doan Hung Commune.

Phu Tho will invite experts to clarify the cause of the damage to the Song Lo bridge piers

|

Phu Tho - On October 30, Vice Chairman of the Provincial People's Committee Nguyen Huy Ngoc directly inspected the scene and directed the plan to fix the problem of damage to the Song Lo bridge piers.

Proposal to soon have a pricing mechanism, avoid price inflation or virtual valuation of intellectual property

|

The delegate emphasized the need to soon issue criteria, processes and mechanisms to monitor valuation, avoiding the situation of "inflating prices" or "defeasioning" the value of intellectual property.

Gold prices drop sharply, people no longer have to jostle to buy 5 taels

|

In Hanoi, the queue situation for gold trading continues but no longer causes congestion. The amount of gold sold is still limited.

Many famous gold shops in Thanh Hoa are still closed after the police inspected and searched

|

Thanh Hoa - Many days after the police force inspected and searched, many famous gold shops in Thanh Hoa province were still closed and had stopped trading.

German court sentenced Le Trung Khoa to slander and defame Vingroup

|

The German court declared Vingroup/VinFast a winner in a defamation case involving Le Trung Khoa, who had slandered the group for giving bribes and called it ghost.

Rice exports decreased compared to the same period, reaching 3.7 billion USD from the beginning of 2025

|

According to data from the Ministry of Agriculture and Environment, rice exports in the first 10 months of the year reached 7.2 million tons and 3.7 billion USD.

Lo River Bridge damaged, people are more worried about riverbank erosion

Tô Công |

Phu Tho - Along with the damage to the Lo River bridge affecting their lives, the riverbank landslide also makes people feel insecure.

Banning all cars across the Lo River bridge in Phu Tho

Tô Công |

Phu Tho - The provincial Department of Construction has just announced the adjustment of traffic flow through the Lo River Bridge, Doan Hung Commune.

Phu Tho will invite experts to clarify the cause of the damage to the Song Lo bridge piers

Minh Nguyễn - Tô Công |

Phu Tho - On October 30, Vice Chairman of the Provincial People's Committee Nguyen Huy Ngoc directly inspected the scene and directed the plan to fix the problem of damage to the Song Lo bridge piers.