Key transportation projects in Hanoi accelerate to welcome the Party Congress

SÓNG HỮU |

Hanoi - Many key transport projects are accelerating towards the finish line, hoping to create a breakthrough development momentum in the 14th Party Congress term.

On January 21, Hanoi weather turned cold, with occasional drizzle, but the construction atmosphere at the Ring Road 2.5 project site, Dam Hong - National Highway 1A section, was still extremely urgent.

a
Construction site of Ring Road 2.5 project, Dam Hong - National Highway 1A section, afternoon of January 21. Photo: Song Huu
a
Bridge L3 across the Lu River belonging to package No. 2 of the project is under construction. Photo: Song Huu

The Ring Road 2.5 construction project, Dam Hong - National Highway 1A section, is invested in the form of a BT contract (build - transfer) with a length of 1.6 km, with a total investment of more than 1,300 billion VND. The project started in 2014, expected to be completed in 2017 but was delayed.

By 2020, the project was temporarily suspended when it only reached about 40% of the workload. The reason is due to problems in site clearance and extension of BT contract appendices.

After 5 years of suspension, by the end of May 2025, with the permission of the Hanoi People's Committee, Hoang Mai - Hanoi Construction Investment Co., Ltd. (the project enterprise) organized the project restarting ceremony.

a
a
The project site is bustling with machinery and workers working. Photo: Song Huu
a
Workers paving sidewalks along the route. Photo: Song Huu
a
Green trees have been planted on the route. Photo: Song Huu

Representatives of Hoang Mai Construction Investment Co., Ltd. - Hanoi said that many workers and machinery have been mobilized to construct day and night, "3 shifts, 4 teams" simultaneously deploying items of the project.

With the workload reaching 95%, the investor and contractors are focusing all their efforts towards the important milestone of technical opening on February 10, 2026.

We encountered many obstacles in the construction process such as both construction and ensuring traffic safety, and scarcity of materials. However, the investor and contractor are trying to gradually overcome difficulties to complete the project according to the schedule assigned by the city" - said a representative of Hoang Mai Construction Investment Co., Ltd. - Hanoi.

This is not only an effort to reduce traffic congestion for the southern area of the city but also a meaningful project to celebrate the success of the 14th National Party Congress.

Another project is also accelerating to be completed, opening to traffic on February 10th is the Kim Dong - Giai Phong intersection underpass project.

a
Kim Dong - Giai Phong intersection underpass has revealed its shape, afternoon January 21. Photo: Song Huu
a
Machinery constructing some items of the underpass on Dam Hong side. Photo: Song Huu

The Kim Dong - Giai Phong intersection underpass construction project has a tunnel length and access road of 890 m in the direction of Ring Road 2.5.

The project was started in October 2022, with a total investment of about 778 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

This is the 5th underpass project in Hanoi since 2009 after the Kim Lien, Trung Hoa, Thanh Xuan and Le Van Luong tunnels.

To date, the project has basically completed the main items and is constructing the final items.

a
Kim Dong - Giai Phong intersection is about to reorganize traffic. Photo: Song Huu

At the Kim Dong - Giai Phong intersection, the contractor is deploying the installation of traffic light poles, painted lines, and installed traffic diversion islands.

Mr. Tran Binh Dinh - engineer of the Kim Dong - Giai Phong underpass project management board - said that the contractor has met with the investor, the inter-sectoral Department of Construction and the unit to develop traffic organization plans at the Kim Dong - Giai Phong intersection as soon as possible, to serve the travel needs of the people.

a
Construction site of Ring Road 1 project, Hoang Cau - Voi Phuc section. Photo: Song Huu

At the Ring Road 1 project site, Hoang Cau - Voi Phuc section in the city center, technical infrastructure items such as drainage and technical trenches are being deployed by contractors in the form of rolling and rolling, moving to where.

Two direct overpasses on the route at the Nguyen Chi Thanh and Giang Vo intersections are also being built.

a
Area for building the overpass at Ring Road 1 - Giang Vo intersection. Photo: Song Huu
a
Workers are making steel cages to serve the construction of drilled piles to make bridge foundations. Photo: Song Huu

Representatives of the Hanoi Civil Construction Investment Project Management Board said that right from the time of handing over the site on December 15, 2025, the investor has requested contractors to mobilize full personnel, equipment, and construction materials continuously during holidays and public holidays.

The entire road and two overpasses at Giang Vo and Nguyen Chi Thanh intersections are expected to be completed in 2026, contributing to reducing inner-city traffic congestion and changing the urban appearance.

SÓNG HỮU
RELATED NEWS

Exciting construction at many projects in Ha Tinh

|

Ha Tinh - Taking advantage of favorable weather, many projects in Ha Tinh are accelerating construction to create a vibrant atmosphere to celebrate the 14th Party Congress.

Hanoi Ring Road 2.5: Construction overnight, will be open to traffic at the end of January

|

Hanoi - Contractors are urgently constructing day and night to complete Ring Road 2.5, Dam Hong - National Highway 1A section by the end of January 2026.

Hanoi relocates nearly 200 graves to build road connecting Ring Road 2.5 to Ring Road 3

|

Hanoi - The city implements the relocation of nearly 200 graves to build the Minh Khai - Vinh Tuy - Yen Duyen road connecting Ring Road 2.5 to Ring Road 3.

Close-up of the fireworks rehearsal at My Dinh Stadium

|

On the evening of January 21, at My Dinh National Stadium, a general rehearsal of the fireworks program to celebrate the success of the 14th Party Congress took place.

Developing Vietnamese industry and trade for autonomy, connectivity, modernization, green transformation, digital transformation and effective integration into global production chains and supply chains

|

Speech by Comrade Le Manh Hung, Secretary of the Party Committee, Acting Minister of Industry and Trade at the 14th National Congress of the Party.

9th Hour No. 185: The abandoned child - Part 1

|

9th hour - Devoting herself to a married man, a country girl was forced by him to have an abortion. The girl determined to keep the drop of blood, will she overcome this tragedy?

International cultural integration, shifting from exchange to true cooperation

|

Vietnam proactively integrates internationally in culture, comprehensively transforms thinking from "interaction, meeting" to "genuine cooperation", promoting national soft power.

Near Tet, a 600-year-old craft village in Hung Yen is busy carving horse mascots

|

Hung Yen - Near the Lunar New Year, Dong Xam silver carving village is at its peak production, with horse mascot carving products favored by the market.

Exciting construction at many projects in Ha Tinh

TRẦN TUẤN |

Ha Tinh - Taking advantage of favorable weather, many projects in Ha Tinh are accelerating construction to create a vibrant atmosphere to celebrate the 14th Party Congress.

Thu hồi đất làm Vành đai 2,5: Bí thư phường trực tiếp xuống làm việc với các hộ dân

Anh Tuấn |

Hà Nội - Bí thư phường Cầu Giấy cùng đoàn công tác trực tiếp xuống làm việc với các hộ dân bị thu hồi đất để làm dự án đường Vành đai 2,5.

Hanoi Ring Road 2.5: Construction overnight, will be open to traffic at the end of January

SÓNG HỮU |

Hanoi - Contractors are urgently constructing day and night to complete Ring Road 2.5, Dam Hong - National Highway 1A section by the end of January 2026.

Hanoi relocates nearly 200 graves to build road connecting Ring Road 2.5 to Ring Road 3

KHÁNH AN |

Hanoi - The city implements the relocation of nearly 200 graves to build the Minh Khai - Vinh Tuy - Yen Duyen road connecting Ring Road 2.5 to Ring Road 3.