Hoa Binh - Moc Chau Expressway is behind schedule due to land clearance problems

NGUYỄN TRƯỜNG |

Son La - The Hoa Binh - Moc Chau Expressway project is being delayed due to problems in site clearance.

The investment project to build the Hoa Binh - Moc Chau expressway, the section passing through Son La province, belongs to the CT3 expressway from Hanoi to the old Hoa Binh, Son La and Dien Bien provinces.

The route is 33.32km long, with a total investment of VND4,400 billion from the central budget and the Son La provincial budget. The project implementation period is from 2025 to 2028.

The project directly affects nearly 760 households and individuals and the total number of households expected to be resettled and newly allocated residential land is 72 households. The total area recovered for the project is about 318.3 hectares.

According to the report of the Son La Province Traffic Construction Investment Project Management Board (investor), the Hoa Binh - Moc Chau Expressway Construction Project, the section passing through Son La province, started construction in May 2025, however, the project implementation is currently facing many difficulties, especially problems in site clearance, causing the project's progress to not reach the plan.

The investor's representative said that the Hoa Binh - Moc Chau Expressway Construction Project, the section passing through Son La province, is divided into 3 component projects.

As of July 15, for component project 1 on compensation, support, resettlement, and site clearance, in To Mua commune and Van Ho commune, up to now, the locality has only started construction at 4 resettlement points. The relocation of power lines cannot be implemented due to incomplete procedures, many locations have not completed determining the origin of land and extracting cadastral maps.

Component project 2 in Van Son ward, although 10.57ha of site clearance has been basically completed, still has 7,667.2m2 of which has not approved the compensation payment dossier for arising households. The handover and adjustment of the boundary markers has not been completed, causing further progress to be interrupted.

For component project 3, although the technical design of the entire 32.3km route has been approved, the selection of contractors for construction and supervision has not been completed due to slow preparation and appraisal of estimate documents. The inspection of the current status of the new project is only in the coordination phase between the contractor and the supervision consultant.

On July 16, speaking with reporters, Mr. Dang Ngoc Hau - Vice Chairman of Son La Provincial People's Committee said that the Project Steering Committee had directly worked with Van Ho and To Mua communes on the progress of site clearance for the above project.

The People's Committee of Son La province has also assigned departments and branches to coordinate in guiding communes with projects to complete the approval of land prices for support and compensation for land acquisition. At the same time, the People's Committee of To Mua commune is required to coordinate with the People's Committee of Van Ho commune to determine the origin of the land, sign the confirmation of the cadastral measure, issue a notice of land recovery, appraise and approve specific land prices, so that the project can be completed on schedule.

NGUYỄN TRƯỜNG
TIN LIÊN QUAN

Proposing solutions for the Dien Bien - Son La expressway to be implemented soon

|

In order for the Dien Bien - Son La expressway to be implemented soon, Minister of Finance Nguyen Van Thang said that the Dien Bien - Son La section should be invested in PPP form.

Son La allocates more than VND6,100 billion for public investment but the disbursement rate is only 20%

|

Son La - Son La province has allocated over VND6,100 billion in public investment capital, but so far, the disbursement rate has only reached over VND1,200 billion.

Son La invests 245 billion VND to build a road connecting Lai Chau

|

Son La - Quynh Nhai District invested 245 billion VND for the 107C Provincial Road project (from Chieng Khay Commune, Quynh Nhai District to Nam So Commune, Tan Uyen District, Lai Chau Province).

Son La spends 312 billion VND to build a provincial road connecting Yen Chau - Ta Khoa

|

Son La - Provincial road 120C connecting Yen Chau district with Bac Yen district, the section belonging to Yen Chau district will be built with a total investment of more than 312.7 billion VND.

Amending bottlenecks in planning and land laws to avoid confusion in management

|

The Deputy Prime Minister noted that bottlenecks in planning and land laws need to be amended promptly to avoid confusion in local management.

HCMC fines Chagee milk tea company 60 million VND

|

HCMC The Inspectorate of the Department of Culture and Sports of HCMC has administratively fined Chagee Vietnam Co., Ltd. VND60 million.

The Ministry of Foreign Affairs speaks out about the case of a Korean tourist beating a Vietnamese woman

|

Vietnamese authorities are verifying and clarifying information related to the case of two Korean women assaulting a Vietnamese woman.

Discussion: Green transportation transformation - an irreversible trend

|

In order to protect the environment and improve people's health, Lao Dong Newspaper organized a seminar: Green transportation transformation - an irreversible trend.

Proposing solutions for the Dien Bien - Son La expressway to be implemented soon

VĂN THÀNH CHƯƠNG |

In order for the Dien Bien - Son La expressway to be implemented soon, Minister of Finance Nguyen Van Thang said that the Dien Bien - Son La section should be invested in PPP form.

Son La allocates more than VND6,100 billion for public investment but the disbursement rate is only 20%

NGUYỄN TRƯỜNG |

Son La - Son La province has allocated over VND6,100 billion in public investment capital, but so far, the disbursement rate has only reached over VND1,200 billion.

Son La invests 245 billion VND to build a road connecting Lai Chau

Tô Công |

Son La - Quynh Nhai District invested 245 billion VND for the 107C Provincial Road project (from Chieng Khay Commune, Quynh Nhai District to Nam So Commune, Tan Uyen District, Lai Chau Province).

Son La spends 312 billion VND to build a provincial road connecting Yen Chau - Ta Khoa

Tô Công |

Son La - Provincial road 120C connecting Yen Chau district with Bac Yen district, the section belonging to Yen Chau district will be built with a total investment of more than 312.7 billion VND.