Expressway worth more than 31,000 billion VND through Can Tho needs 7 million m3 of sand

Tạ Quang |

Can Tho - The expressway project worth more than 31,000 billion VND through Can Tho is lacking about 7 million m3 of filling sand, creating great pressure on construction progress.

The Chau Doc - Can Tho - Soc Trang expressway project phase 1 is a key traffic project of the Mekong Delta region, in which component projects 2, 3 and 4 passing through Can Tho City are being implemented simultaneously.

Dự án đường bộ cao tốc Châu Đốc – Cần Thơ – Sóc Trăng giai đoạn 1 là công trình giao thông trọng điểm. Ảnh: Tạ Quang
The Chau Doc - Can Tho - Soc Trang expressway project phase 1 is a key traffic project. Photo: Ta Quang

The project has a total investment of 31,288.077 billion VND, implementation time from 2022 to 2027, with a route scale starting at Km57+200 in Thanh Quoi commune (Can Tho City), ending point at Km189+666.65 intersecting with Nam Song Hau National Highway and the access road to Tran De port according to the plan, total length of about 132.47 km.

Currently, component projects 2, 3 and 4 have a total of 11 construction packages, including 10 construction packages and 1 construction package for traffic safety systems, with a total construction volume of about 54%.

The Can Tho City Traffic and Agricultural Construction Investment Project Management Board (PMB) said that in the process of implementation, one of the biggest difficulties of component projects 2, 3 and 4 is the supply of materials, especially filling sand and construction stone.

Khối lượng cát đã được đưa về công trường đạt khoảng 10,234 triệu m3. Ảnh: Tạ Quang
The volume of sand brought to the construction site reached about 10.234 million m3. Photo: Ta Quang

The total demand for filling sand of the three component projects is about 17.4 million m3, while the volume brought to the construction site reached about 10.234 million m3. However, the supply still faces many obstacles due to unstable mine sources, many mines are in the process of extending licenses, expiring exploitation periods or having to temporarily suspend operations.

For component project 2, Binh Phuoc Xuan mine (An Giang province) is carrying out procedures to extend the mining license and is expected to be completed in April 2026; Vam Nao and Tan Hoa mines have expired their mining licenses and are currently continuing to carry out procedures to extend them to serve the project.

In Dong Thap province, mines such as An Nhon and Hoa Hung 4 have total reserves according to the license of about 2.896 million m3, but in reality, exploitation is low due to some mines temporarily suspended due to landslides or not meeting technical requirements, causing the total feasible exploitation volume to be only about 1.538 million m3.

For component project 4, the city has licensed the exploitation of 3 sea sand mines including B1. 1, B1. 2 and B1. 4 with a total reserve of about 4.3 million m3, but the actual exploitation capacity is expected to only reach about 1 million m3.

Tổng khối lượng thi công của các dự án thành phần 2, 3 và 4 đã đạt khoảng 54%. Ảnh: Tạ Quang
The total construction volume of component projects 2, 3 and 4 has reached about 54%. Photo: Ta Quang

In addition, the total demand for stone material for 3 component projects is about 4.123 million m3, of which about 0.805 million m3 has been gathered for the project and has been used. The volume of stone identified sources is 1.832 million m3, and the volume of unidentified sources is about 2.291 million m3.

Although the construction volume of component projects 2, 3 and 4 has reached about 54%, progress is still under great pressure due to a shortage of materials, especially filling sand and construction stone. If difficulties in the mining mechanism are not soon removed and stable supply is ensured, the project completion target by 2027 may be affected.

Tạ Quang
RELATED NEWS

The appearance of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April

|

Dong Nai - 34km of Bien Hoa - Vung Tau expressway through Dong Nai is completing the final stages to open to traffic along with 19.5km of Ho Chi Minh City by the end of April 2026.

La Son - Hoa Lien expressway expansion project overcomes difficulties, accelerates progress

|

Rising fuel prices have led to increased costs of materials and machinery operation, putting great pressure on the construction of the La Son - Hoa Lien expressway.

Hau Giang - Ca Mau expressway section is expected to be opened on April 30

|

After a period of temporary suspension to complete the items, the Hau Giang - Ca Mau expressway section is being accelerated, expected to be put back into operation on April 30, 2026.

Social housing project illegally advertised for sale

|

Ho Chi Minh City - The investor of the Ly Thuong Kiet social housing project warns about the situation of brokers arbitrarily advertising for sale and receiving illegal deposits.

Recall of grade 3 textbooks containing unsafe links in Hue

|

HUE - Hue University Publishing House recalls "Informatics Worksheet 3" containing unsafe links, stops issuing, refunds and coordinates with functional agencies for handling.

There is no "safe zone" for the leader if leadership is relaxed

|

Head of the Central Propaganda and Mass Mobilization Commission Trinh Van Quyet clearly stated that there is no "safe zone" for the head if leadership is relaxed.

Clarify the authority to organize villages and residential groups in the draft revised Capital Law

|

National Assembly Deputy Tran Thi Nhi Ha said that it is necessary to clarify the authority to organize villages and residential groups in Article 7 of the draft Capital Law (amended).

Red River in a 100-year vision: Awakening the urban face of Hanoi in the future

|

In the Hanoi Capital Master Plan with a 100-year vision, the Red River is identified as the central landscape axis and a new symbol of the city's development.

The appearance of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April

HÀ ANH CHIẾN |

Dong Nai - 34km of Bien Hoa - Vung Tau expressway through Dong Nai is completing the final stages to open to traffic along with 19.5km of Ho Chi Minh City by the end of April 2026.

La Son - Hoa Lien expressway expansion project overcomes difficulties, accelerates progress

An Thượng |

Rising fuel prices have led to increased costs of materials and machinery operation, putting great pressure on the construction of the La Son - Hoa Lien expressway.

Hau Giang - Ca Mau expressway section is expected to be opened on April 30

NHẬT HỒ |

After a period of temporary suspension to complete the items, the Hau Giang - Ca Mau expressway section is being accelerated, expected to be put back into operation on April 30, 2026.