Da Nang removes obstacles, accelerates disbursement of public investment capital in 2025

Trần Thi |

Da Nang held a meeting to remove difficulties, promote disbursement of public investment capital in 2025, and prepare for the 2026 plan.

On September 22, the People's Committee of Da Nang City held a meeting to remove difficulties and obstacles to promote the disbursement of public investment capital in 2025.

The meeting was sent online to Chairmen of People's Committees of communes and wards; Directors of the Management Boards of Investment and Construction Projects of the area; Directors of the Regional Branch of the Da Nang City Land Fund Development Center at the headquarters of the People's Committees of communes and wards.

At the meeting, Chairman of the City People's Committee Pham Duc An said that the disbursement of public investment was delayed due to many reasons, especially the slow compensation and site clearance work and the supply of raw materials such as soil and sand was difficult, prices increased.

Therefore, it is required that in the coming time, it is necessary to promote decentralization and delegation of authority so that units and localities have enough authority to handle practical issues. Develop a handbook to guide localities to reduce procedures and support effective project implementation.

For the problem of construction materials such as sand that have been auctioned but prices have increased sharply affecting fixed contracts, timely solutions are needed. Site clearance and resettlement arrangements need to ensure essential infrastructure, handle cemeteries with clear planning, respect the deceased, be in accordance with tradition and legal regulations.

Cuoc hop thao go kho khan, vuong mac de day manh cong tac giai ngan von dau tu cong nam 2025 do Chu tich UBND TP Da Nang Pham Duc An chu tri. Anh: UBND TP Da Nang
The meeting to remove difficulties and obstacles to promote the disbursement of public investment capital in 2025 was chaired by Chairman of the People's Committee of Da Nang City Pham Duc An. Photo: Da Nang City People's Committee

According to the report of the Department of Finance, from the beginning of the year, the work of planning and allocating detailed public investment capital plans has been proactively implemented. Before and after merging and organizing local governments at both levels, the city has proactively directed departments, branches, localities, investors, project operators and related units to review, handle problems and difficulties and advise the City People's Committee to deploy solutions to speed up the progress of public investment projects and works to ensure progress.

At the same time, units are required to commit to disbursement milestones from the beginning of the year in conjunction with the emulation assessment during the year and to effectively implement the internal transfer of capital plans to speed up the disbursement progress of works and projects.

The City People's Committee has requested investors and project management units to have a detailed monthly and quarterly plan on the disbursement progress of each specific project. Urge contractors and relevant agencies and units in implementation, especially ensuring progress, quality of implementation, site clearance, assigning affiliated specialized agencies and related units to regularly update and report on the implementation of works and projects in the city, especially key projects,

The City People's Committee established 9 working groups headed by the City People's Committee leaders to remove difficulties and obstacles for investment projects in the area, especially projects that are backlogged and prolonged; urge key and dynamic projects in the city.

As of August 31, 2025, the total disbursement value of the 2025 capital plan of the entire city of Da Nang (new) reached nearly VND 6,806 billion, equal to 41.5% of the capital plan assigned by the Prime Minister; reaching 38% compared to the plan assigned by the City People's Council and People's Committee (including the 2024 budget capital plan allowed to be extended to 2025).

For 5 Management Boards under the City People's Committee, nearly VND 3,566 billion has been disbursed, equal to 54.8% of the assigned capital plan and 50% of the total disbursement of the city (as of September 15, 2025).

Trần Thi
RELATED NEWS

Da Nang Department of Industry and Trade talks about the acceptance of national grid towing projects

|

Da Nang - The Department of Industry and Trade of Da Nang City has just responded to the acceptance of national grid electricity projects.

Da Nang disburses total resources, accelerates the implementation of a series of key projects

|

Da Nang - The city is vigorously implementing solutions to speed up the disbursement of public investment capital, especially important and key projects and works.

Da Nang is slow to disburse public investment capital partly due to lack of sand and filling materials

|

Da Nang's progress in public investment disbursement in 2025 is facing a big challenge when it only reached nearly 21% of the plan after the first 5 months of the year.

A picture of central hospitals after the Ministry of Health reorganizes affiliated hospitals

|

The Government requires continuing to arrange and transfer a number of hospitals under the Ministry of Health to the provincial level for management.

Adding a set of lights makes road users angry, pickup truck driver receives a fine

|

Hanoi - The driver with additional headlights causing frustration for road users has been fined.

Ho Chi Minh City Police invite Ngu Ho Tuong band with Ung Hoang Phuc to work

|

The Cyber Security and High-Tech Crime Prevention Department (PA05) of Ho Chi Minh City Police invited the group of singer Ngu Ho Tuong with Ung Hoang Phuc to work.

Elderly people need care in the morning to pick them up and take them home in the afternoon

|

Mr. Truong Xuan Cu - Vice President of the Vietnam Association of the Elderly - hopes that many elderly people will be cared for during the day "in the morning pick them up and take them home in the afternoon".

Da Nang Department of Industry and Trade talks about the acceptance of national grid towing projects

Thu Giang |

Da Nang - The Department of Industry and Trade of Da Nang City has just responded to the acceptance of national grid electricity projects.

Da Nang disburses total resources, accelerates the implementation of a series of key projects

Thu Giang |

Da Nang - The city is vigorously implementing solutions to speed up the disbursement of public investment capital, especially important and key projects and works.

Da Nang is slow to disburse public investment capital partly due to lack of sand and filling materials

An Thượng |

Da Nang's progress in public investment disbursement in 2025 is facing a big challenge when it only reached nearly 21% of the plan after the first 5 months of the year.