Accelerate the progress of building a multi-level boarding school in Quang Tri

HƯNG THƠ |

Quang Tri - The progress of multi-level boarding schools in border areas is being accelerated, and many important items have been completed.

Completing many difficult items

At the Dakrong Primary and Secondary Boarding School project (Dakrong commune, Quang Tri province), the construction area is located close to a high hillside, so creating construction site faces many obstacles, requiring a lot of time and effort.

In the early days of April, the weather in Dakrong commune appeared hot, although affecting workers' health, it created favorable conditions for construction progress after a long period of interruption due to prolonged rain.

Mr. Phan Tuan Anh - Commander of Manh Linh - General Contractor Consortium No. 8 - Thuan An - Tuan Tien - Trang An - Hoa Hung - Phuoc Binh said that the construction site is far from the center, the transportation of materials is difficult, plus high technical requirements such as deep foundation excavation and sand buffers, causing initial progress to be affected.

Currently, the construction site has more than 200 officials and workers working continuously. Difficult items such as foundation and site clearance have been completed, and the remaining tasks are being quickly deployed" - Mr. Anh informed.

Công nhân thi công tại dự án Trường nội trú Tiểu học và THCS Đakrông. Ảnh: Hưng Thơ
Construction workers at the Dakrong Primary and Secondary Boarding School project. Photo: Hung Tho

According to records, the 3-story administrative building has completed the rough construction of the 1st and 2nd floors; the secondary school subject classroom building has also completed the rough construction of the floors; the teacher dormitory area has achieved similar progress...

Closely follow the progress of each project

According to the Quang Tri Provincial Construction Investment Project Management Board, in April 2026, the Dakrong Primary and Secondary Boarding School project will complete the entire reinforced concrete frame structure, and at the same time deploy wall construction, plastering and technical infrastructure construction.

In May, June and July, the unit will complete all items, install equipment for handover, and put the project into use according to plan.

Mr. Nguyen Thanh Binh - Director of the Provincial Construction Investment Project Management Board said that technical staff are assigned to closely monitor the construction site, monitor the progress of each item. The arising difficulties will be summarized, reported and proposed for timely handling plans.

Thi công dự án Trường nội trú Tiểu học và THCS Đakrông. Ảnh: Hưng Thơ
Construction of the Dakrong Primary and Secondary Boarding School project. Photo: Hung Tho

Along with Dakrong, from mid-November 2025, 3 other inter-level boarding school projects will also be implemented, including Huong Phung Primary and Secondary Boarding School, Thuong Trach and Dan Hoa.

According to the People's Committee of Quang Tri province, the progress of the projects basically meets the set requirements. In Huong Phung commune, the entire functional building block has constructed the body from the 1st floor to the roof; basic technical infrastructure has completed ground leveling, about 40% of items are continuing to be implemented. In Thuong Trach, about 70% of the building block is constructing the body from the 1st floor to the 2nd floor, auxiliary items are gradually being completed. Especially in Dan Hoa, the progress is slower than other projects.

According to statistics, 4 projects have been allocated enough 1,061 billion VND, reaching 100% of the total investment. Accumulated disbursement value to date reached 306.886 billion VND.

During the construction process, increasing fluctuations in fuel and construction material prices have affected costs and progress. Faced with this situation, the People's Committee of Quang Tri province has directed departments and branches to review and propose solutions to remove obstacles, ensure material supply, and stabilize construction.

HƯNG THƠ
RELATED NEWS

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

|

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Quang Tri starts construction and upgrading of 11 boarding schools

|

Quang Tri - 11 projects to build and upgrade boarding schools with a total capital of nearly 2,240 billion VND are being implemented simultaneously in 11 border communes.

Building a 360 billion VND inter-level boarding school in the border area of Quang Tri

|

Quang Tri - Huong Phung Primary and Secondary Boarding School was invested in construction with a total investment of 360 billion VND, with a scale of 40 classes.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Hanoi Industrial Meal Company won 148/148 bidding packages, with a total value of 505.8 billion VND

|

Hanoi Industrial Meal Service Joint Stock Company participated and won all 148 bidding packages to supply meals at schools in Hanoi and some northern provinces.

Teachers of Song Hong school nearly 20 months without salary, Phu Tho Department of Home Affairs speaks out

|

Phu Tho - Regarding the case of teachers of Song Hong Intermediate School who have not received salary for nearly 20 months, the Phu Tho Department of Home Affairs has spoken out.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

|

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

Mai Dung |

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Quang Tri starts construction and upgrading of 11 boarding schools

HƯNG THƠ |

Quang Tri - 11 projects to build and upgrade boarding schools with a total capital of nearly 2,240 billion VND are being implemented simultaneously in 11 border communes.

Building a 360 billion VND inter-level boarding school in the border area of Quang Tri

HƯNG THƠ |

Quang Tri - Huong Phung Primary and Secondary Boarding School was invested in construction with a total investment of 360 billion VND, with a scale of 40 classes.