Successful energization, put into operation 2 110kV transformer stations at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport 110kV transformer station with a total capacity of 80MVA contributes significantly to ensuring power supply for the airport super project.

On the evening of November 24, information from Dong Nai Power Company said that the project to install machinery for the two 110kV transformer stations at Long Thanh airport has been officially successfully energized.

Toan canh cong trinh tram bien ap 110kV san bay Long Thanh. Anh: HAC
Overview of the 110kV transformer station project at Long Thanh airport. Photo: HAC

The project to install the engine of 2 Long Thanh airport 110kV transformer stations, started on September 29, 2025, is part of the project "Long Thanh airport 110kV transformer station and connecting lines".

This is phase 2 of the project, with a total investment of 38.8 billion VND. The scale of the project includes 1 transformer with a capacity of 40MVA. The project belongs to group C, type of energy project level II.

Nguoi lao dong thi cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
Workers constructing the installation of machinery for 2 110kV transformer stations at Long Thanh airport. Photo: HAC

Previously, on November 27, 2024, Dong Nai Power Company successfully energized phase 1 of the project. The scale of phase 1 is 1 transformer with a capacity of 40MVA, a 3.8 km long connection line to the station, with a total investment of 119 billion VND, ensuring power supply as soon as the airport comes into operation.

With the operation of the Long Thanh Airport 110kV transformer station 2, the total capacity of the Long Thanh airport 110kV was increased to 80MVA, contributing significantly to ensuring power supply for Long Thanh International Airport, while contributing to reducing the 22kV power supply radius, reducing losses, ensuring voltage quality, and improving the reliability of power supply in neighboring areas.

Cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
The project to install the 2 110kV transformer stations of Long Thanh airport. Photo: HAC

In the past time, Dong Nai Power Company has always ensured electricity supply for the activities of the Long Thanh airport construction site, with an average electricity output of 730,000 kWh/month.

Currently, the main power source for the construction of Long Thanh airport is being supplied through 2 110kV transformer stations outside the airport. In the coming time, when relevant units complete the infrastructure and procedures synchronously, the 110kV transformer station of Long Thanh airport will be connected to directly provide electricity for the project, both during the construction process and when the airport is put into operation.

Some images of the construction of the project to install the 2 110kV transformer stations of Long Thanh airport that Lao Dong newspaper reporters recorded at the project:

Cong trinh tram bien ap 110kV san bay Long Thanh co vi tri nam o giap ranh hang rao Cang hang khong Quoc te Long Thanh. Anh: HAC
The 110kV Long Thanh airport transformer station project is located at the fence of Long Thanh International Airport. Photo: HAC
Nguoi lao dong thi cong giua troi trua nang day nhanh tien do du an. Anh: HAC
Workers are working in the sunny afternoon to speed up the project's progress. Photo: HAC

Nguoi lao dong thi cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
Workers constructing the installation of machinery for 2 110kV transformer stations at Long Thanh airport. Photo: HAC
Nguoi lao dong thi cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
Workers constructing the installation of machinery for 2 110kV transformer stations at Long Thanh airport. Photo: HAC
Nguoi lao dong thi cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
Workers constructing the installation of machinery for 2 110kV transformer stations at Long Thanh airport. Photo: HAC
Cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
The project to install the 2 110kV transformer stations of Long Thanh airport. Photo: HAC
Cong cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
The project to install the 2 110kV transformer stations of Long Thanh airport. Photo: HAC
Duong day dau noi cong trinh lap may 2 tram bien ap 110kV san bay Long Thanh. Anh: HAC
The line connecting the project to install machinery for 2 110kV transformer stations at Long Thanh airport. Photo: HAC

HÀ ANH CHIẾN
RELATED NEWS

Opening 2 routes passing through 4 communes in Dong Nai connecting Ho Chi Minh City with Long Thanh airport

|

Dong Nai - The 25B and 25C road projects will be technically open to traffic at the end of 2025 and the beginning of 2026 to connect Long Thanh airport.

Solving the problem of one route carrying an entire airport in the Long Thanh airport project

|

Dong Nai - ACV recommends synchronizing transportation projects connecting to Long Thanh airport soon to solve the problem of "one route carries the entire airport".

Demand for nearly 900 people, Long Thanh airport extends time to receive labor recruitment documents

|

Dong Nai - The Recruitment Council extended the time to receive documents of workers applying to work at Long Thanh airport.

Adding more than 53,000 billion VND to localities to ensure implementation of the basic salary

|

The National Assembly Resolution estimates more than VND53,000 billion to supplement localities to ensure the implementation of the basic salary of VND2.34 million/month.

People are busy moving their homes to prepare for the start of construction of Ring Road 2 in Ho Chi Minh City

|

Ho Chi Minh City is speeding up the site clearance process, many households are rushing to relocate in time to hand over land, preparing to start the Ring Road 2 project by the end of 2025.

Excitedly winning the online lottery to buy social housing at 29.4 million VND/m2 in Hanoi

|

Hanoi - On November 24, the Rice City Long Chau social housing project organized an online lottery for apartment purchase and rental rights.

Hanoi plans to spend 1,985 billion VND in additional income for cadres, civil servants and public employees in 2025

|

The Hanoi People's Committee submitted to the People's Council a draft Resolution on paying additional income to cadres, civil servants and public employees from the basic salary fund and reforming outstanding salaries.

After Ring Road 1, Hanoi calculates the time to ban motorbikes running on gasoline in Ring Road 3

|

Hanoi plans to ban gasoline motorbikes in Ring Road 1 according to time frames/time frames and areas to limit the impact on production and business and people's lives.

Opening 2 routes passing through 4 communes in Dong Nai connecting Ho Chi Minh City with Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The 25B and 25C road projects will be technically open to traffic at the end of 2025 and the beginning of 2026 to connect Long Thanh airport.

Solving the problem of one route carrying an entire airport in the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - ACV recommends synchronizing transportation projects connecting to Long Thanh airport soon to solve the problem of "one route carries the entire airport".

Demand for nearly 900 people, Long Thanh airport extends time to receive labor recruitment documents

HÀ ANH CHIẾN |

Dong Nai - The Recruitment Council extended the time to receive documents of workers applying to work at Long Thanh airport.