Dong Nai criticizes the Director of the Project Management Board for slow relocation of power infrastructure for the expressway project

HÀ ANH CHIẾN |

Dong Nai - Vice Chairman of the Provincial People's Committee Ho Van Ha criticized 1 individual and 2 groups for being slow to relocate the power infrastructure of the Bien Hoa - Vung Tau expressway project.

On May 23, Vice Chairman of Dong Nai People's Committee Ho Van Ha presided over working with relevant units on the relocation of electricity infrastructure for construction of Bien Hoa - Vung Tau Expressway Project and criticized the Director of Long Thanh District Project Management Board, reminding two units, the provincial Land Fund Development Center, the Management Board of the Provincial Transport Construction Project.

Vice Chairman of the People's Committee of Ho Van Ha also assigned the Department of Industry and Trade to monitor and report the whole progress of the relocation of the electricity infrastructure of Bien Hoa - Vung Tau Expressway Project. The investor units rebuilt the newly implemented line to send to the Department of Industry and Trade to evaluate the provincial People's Committee for the provincial People's Committee to approve the report plan and commit to the implementation progress to the Ministry of Construction.

According to the Department of Industry and Trade, for the project route passing through Bien Hoa City, there are 10 locations of the lower voltage medium power grid that needs to be relocated, dismantled and renovated underground to serve the construction of the project. Up to now, the construction unit has completed 9 positions. With the remaining position at the location of the intersection of Vo Nguyen Giap street, it was also registered for the power cutting schedule on May 29 to carry out the relocation.

With high voltage grids, there are 2 positions of the 220kV power grid to be relocated, raising the pillar that has been gathered by the contractor but has not yet been constructed because it has not been handed over the ground. With the route through Bien Hoa City, the relocation of electricity infrastructure has completed about 90% of the volume under the contract and is expected to be completed in the end of May 5.2025.

For the project section through Long Thanh district, the medium and low voltage power grid and transformer station have 32 locations that need to be relocated, dismantled, and undergrounded. To date, 21 locations have been completed, the remaining 11 locations are expected to be completed before June 10. With the high-voltage grid, there are 13 locations that need to be relocated, 20 electric poles need to be raised. Currently, Long Thanh district has mobilized people to hand over the site, is implementing the construction of 7 pillar locations and is expected to complete the entire workload in June 2025.

HÀ ANH CHIẾN
RELATED NEWS

Enforcing households that have not yet handed over the land for the Bien Hoa - Vung Tau expressway project

|

Dong Nai - The authorities are enforcing households in Long Duc commune, Long Thanh district that have not yet handed over the construction site of the Bien Hoa - Vung Tau expressway.

Enforcing the first household in the Bien Hoa - Vung Tau expressway project

|

Dong Nai - The Land Acquisition Enforcement Board of the Bien Hoa - Vung Tau Expressway Project (Long Thanh District) deploys a plan for 15 households in Long Duc Commune.

People come to live, resettlement areas in the Bien Hoa - Vung Tau expressway project have not been connected to electricity

|

Dong Nai - Dozens of households have given up land for the Bien Hoa - Vung Tau expressway project to live in the resettlement area but have not been connected to the power grid.

Close-up of the fireworks rehearsal at My Dinh Stadium

|

On the evening of January 21, at My Dinh National Stadium, a general rehearsal of the fireworks program to celebrate the success of the 14th Party Congress took place.

Developing Vietnamese industry and trade for autonomy, connectivity, modernization, green transformation, digital transformation and effective integration into global production chains and supply chains

|

Speech by Comrade Le Manh Hung, Secretary of the Party Committee, Acting Minister of Industry and Trade at the 14th National Congress of the Party.

9th Hour No. 185: The abandoned child - Part 1

|

9th hour - Devoting herself to a married man, a country girl was forced by him to have an abortion. The girl determined to keep the drop of blood, will she overcome this tragedy?

International cultural integration, shifting from exchange to true cooperation

|

Vietnam proactively integrates internationally in culture, comprehensively transforms thinking from "interaction, meeting" to "genuine cooperation", promoting national soft power.

Near Tet, a 600-year-old craft village in Hung Yen is busy carving horse mascots

|

Hung Yen - Near the Lunar New Year, Dong Xam silver carving village is at its peak production, with horse mascot carving products favored by the market.

Enforcing households that have not yet handed over the land for the Bien Hoa - Vung Tau expressway project

HÀ ANH CHIẾN |

Dong Nai - The authorities are enforcing households in Long Duc commune, Long Thanh district that have not yet handed over the construction site of the Bien Hoa - Vung Tau expressway.

Enforcing the first household in the Bien Hoa - Vung Tau expressway project

HÀ ANH CHIẾN |

Dong Nai - The Land Acquisition Enforcement Board of the Bien Hoa - Vung Tau Expressway Project (Long Thanh District) deploys a plan for 15 households in Long Duc Commune.

People come to live, resettlement areas in the Bien Hoa - Vung Tau expressway project have not been connected to electricity

HÀ ANH CHIẾN |

Dong Nai - Dozens of households have given up land for the Bien Hoa - Vung Tau expressway project to live in the resettlement area but have not been connected to the power grid.