Project of 1,940 billion VND entangled in site clearance, risk of delayed disbursement

HƯNG THƠ |

The National Highway 15D phase 1 traffic road project in Quang Tri province is more than 21km long, with a total investment of 1,940 billion VND, and disbursement must be completed by the end of 2026, but so far site clearance (GPMB) is still unfinished and the completion date is unknown.

Difficulties with illegal construction and tombs

The National Highway 15D phase 1 traffic road project in Quang Tri province is more than 21km long, with a total investment of 1,940 billion VND, passing through My Thuy, Dien Sanh, Vinh Dinh communes. According to statistics, the section passing through Dien Sanh commune is 13.21km long, with a total planned recovered area of about 61.3ha, related to 534 land plots and affecting about 297 organizations, households, and individuals. For the section from National Highway 1A to Cam Lo - La Son expressway, most of which is forest land, the locality has signed land acquisition regulations for 90/95 plots. The section from National Highway 1A to the border of Vinh Dinh commune has completed 428 plots, reaching about 95%. However, the biggest difficulty currently is the existence of more than 30 illegal construction works and more than 100 graves located within the site clearance area, mainly in the East of National Highway 1A. In Hau Truong village, Dien Sanh commune, many temporary works are erected with corrugated iron and iron frames located within the project area. Ms The project is paved with concrete foundation, surrounded by corrugated iron, living conditions are still lacking. Not only Ms. Tinh's family, this area also has many rows of other temporary houses, some of which are uninhabited, causing difficulties for the work of counting, handling and mobilizing people to dismantle.

Mr. Le Xuan Nam - Vice Chairman of Dien Sanh Commune People's Committee - informed that the locality has made records for illegal constructions, and at the same time promoted propaganda and mobilized people to voluntarily dismantle.

In My Thuy commune - a locality located at the beginning of the route, the area requiring site clearance is less, but problems arise. According to Mr. Le Dac Trieu - Vice Chairman of My Thuy Commune People's Committee, so far the locality has handed over about 1km of the beginning of the route to the construction unit. The remaining part has completed land origin verification, asset valuation and public disclosure of compensation plans.

Large disbursement schedule pressure

According to the Quang Tri Provincial Department of Construction, by the end of January 2026, the project investment preparation work has been completed, shortened by about 5 months compared to regulations. However, the site clearance progress is still slow compared to the requirements. At the time of commencement at the end of January 2026, localities had only handed over about 2km on a total length of more than 21km, along with 5 bridge construction locations.

Mr. Hoang Nam - Standing Vice Chairman of Quang Tri Provincial People's Committee - said that the province has regularly inspected and urged the progress of site clearance and assigned direct responsibility to the Chairmen of the People's Committees of communes: Vinh Dinh, Dien Sanh, My Thuy. The deadline for completing site clearance is determined before April 30, 2026 and is considered a criterion for evaluating the level of task completion. My Thuy commune strives to complete it before April 15, 2026.

HƯNG THƠ
RELATED NEWS

Entangled" with 2 households, nearly 1,500 billion VND project to expand the southern gateway cannot reach the finish line

|

Ho Chi Minh City - With a total capital of nearly 1,500 billion VND, the National Highway 50 expansion project is currently 95% on schedule. The investor is focusing efforts on removing site obstacles to open traffic.

600 billion VND road project connecting National Highway 6 is still under construction but not completed

|

Phu Tho - The road connecting Tran Hung Dao street with National Highway 6 is under construction due to site clearance problems and lack of materials.

Enforced land recovery for 27 households to implement the regulating lake project in Hanoi

|

Hanoi - Tu Liem Ward People's Committee has just organized the enforcement of land recovery for 27 households to implement the Phu Do regulating lake construction project.

Explosives discovered near Russian gas pipeline, Hungary holds emergency meeting before elections

|

Hungary held an emergency meeting after Serbia discovered explosives with great destructive power only a few hundred meters from the Russian gas pipeline.

Party and State leaders, National Assembly deputies visit President Ho Chi Minh's Mausoleum

|

Party and State leaders, National Assembly deputies enter the Mausoleum to pay respects to President Ho Chi Minh before the opening session of the First Session of the 16th National Assembly.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Trump warns of destroying Iranian infrastructure

|

Mr. Trump on April 5 (local time) issued a warning that he would destroy Iran's important civilian infrastructure.

Hanoi Industrial Meal Company won 148/148 bidding packages, with a total value of 505.8 billion VND

|

Hanoi Industrial Meal Service Joint Stock Company participated and won all 148 bidding packages to supply meals at schools in Hanoi and some northern provinces.

Entangled" with 2 households, nearly 1,500 billion VND project to expand the southern gateway cannot reach the finish line

BẢO TÚ |

Ho Chi Minh City - With a total capital of nearly 1,500 billion VND, the National Highway 50 expansion project is currently 95% on schedule. The investor is focusing efforts on removing site obstacles to open traffic.

600 billion VND road project connecting National Highway 6 is still under construction but not completed

Minh Nguyễn |

Phu Tho - The road connecting Tran Hung Dao street with National Highway 6 is under construction due to site clearance problems and lack of materials.

Enforced land recovery for 27 households to implement the regulating lake project in Hanoi

Anh Tuấn |

Hanoi - Tu Liem Ward People's Committee has just organized the enforcement of land recovery for 27 households to implement the Phu Do regulating lake construction project.