400ha project is behind schedule for 18 years, Binh Dinh province proposes to reclaim

Hoài Luân |

After 18 years of implementation, the project of Investment in construction and business of technical infrastructure of Nhon Hoi Industrial Park (Area B) - abbreviated as Nhon Hoi Industrial Park project (Area B) - is still unclear in the completion date.

The project has been sluggishly implemented for 18 years

Nhon Hoi Industrial Park Project (Area B) in Nhon Hoi Economic Zone (Binh Dinh) invested by Hong Yeung Vietnam One Member Co., Ltd. The legal representative is Mr. Tu Phong Boi (Xu Xie Feng Pei) - General Director.

In 2007, this company was granted the first Investment Certificate by the Nhon Hoi Economic Zone Management Board (now the Binh Dinh Economic Zone Management Board). By 2012, the certificate was adjusted to invest in the project of Investment in construction and business of infrastructure of Nhon Hoi Industrial Park (Area B), with an area of 447 hectares, with a total investment capital of more than 546 billion VND. According to the committed schedule, the project must complete the infrastructure according to the approved plan by the end of 2011.

However, up to now, this company has not completed the planning adjustment procedures and investment procedures according to regulations. Currently, the company has stopped construction and has not proven the actual construction volume arising since the recording of the minutes of the Economic Zone Management Board on April 23, 2021.

The company has not yet completed the procedures for reviewing and approving the construction drawing design documents, but has organized the leveling and implementation of some infrastructure items. At the same time, it has not provided relevant documents such as detailed design drawings, quality management documents, acceptance minutes, completion volume confirmation, completed drawings, payment invoices, etc., making it difficult to assess the quality and quantity of items.

Although the synchronous infrastructure has not been completed and the project has not been accepted, the company has leased the premises to a secondary unit in Nhon Hoi Industrial Park (Area B) which is not in accordance with regulations.

In May 2021, Hong Yeung Vietnam One Member Co., Ltd. proposed to extend the land use period in Nhon Hoi Industrial Park (Area B). After that, the Economic Zone Management Board issued a decision to extend the land use progress for 2 years, with the land rental amount of more than 60 billion VND.

After being extended and receiving the payment notice, this company submitted a petition to the Economic Zone Management Board, the Provincial People's Committee and was considered and responded to. However, the company did not agree, so it continued to file a lawsuit with the People's Court of Binh Dinh province. After acceptance and public trial, the Court rejected all the contents of the lawsuit of this company.

Du an cua Cong ty TNHH MTV Hong Yeung Viet Nam tai khu kinh te Nhon Hoi (Binh Dinh). Anh: Hoai Luan
Project of Hong Yeung Vietnam One Member Co., Ltd. in Nhon Hoi Economic Zone (Binh Dinh). Photo: Hoai Luan

Ask for the opinion of the Ministry of Public Security to reclaim land

According to Vice Chairman of Binh Dinh Provincial People's Committee Nguyen Tu Cong Hoang, in 2022 and 2023, the Provincial People's Committee, the Economic Zone Management Board and related units have worked and urged many times, but the company still refuses to pay land rent and late payment fees to the State budget...

After reviewing and consolidating the dossier, the Department of Natural Resources and Environment submitted to the People's Committee of Binh Dinh province for consideration and issuance of a notice of land reclamation to Hong Yeung Vietnam One Member Co., Ltd. and related parties. The notice period is not more than 45 days from the date of issuance.

When the notice period expired, the Provincial People's Committee issued a decision to reclaim more than 400 hectares of land that the Economic Zone Management Board had leased to this company in 2009, to implement the Nhon Hoi Industrial Park project (Area B).

The reason for land reclamation is that the investor violated the 2024 Land Law. Of which, more than 84 hectares of land were leased by the State to implement the project but not used for 12 consecutive months from the date of handover; more than 320 hectares of land were leased by the State to implement the project but the land use progress was 24 months behind the commitment in the investment project.

"Because Hong Yeung Vietnam One Member Co., Ltd. has foreign factors and a long investment time, the People's Committee of Binh Dinh province proposed that the Ministry of Public Security consider and give opinions on the land recovery of Nhon Hoi Industrial Park project (Area B) due to violations of land laws, so that the province can organize and implement it" - Mr. Nguyen Tu Cong Hoang suggested.

Hoài Luân
TIN LIÊN QUAN

Quang Binh takes strong measures to reclaim land with slow-progressing projects

|

Quang Binh - The province resolutely reclaims land for projects that are behind schedule, violate financial obligations, and avoid wasting resources.

Difficulty accessing capital, social housing projects behind schedule

|

Tien Giang - After more than 8 years of construction, the HQC Tan Huong social housing project (Tien Giang) has not yet been completed due to difficulties in accessing loans.

The VND2,160 billion project in Pleiku is behind schedule due to land clearance problems

|

Currently, there are 327 households with land and assets in the planning and clearance area that have not agreed to relocate because they think the compensation price is still low.

Gold price today 13.3: Breaking the peak, approaching the 95 million VND mark

|

Gold price today 13.3: All increased in both domestic and international markets. Plain gold rings approached the 95 million VND/tael mark.

President Trump gives reasons for not sanctioning Russia

|

President Donald Trump said on March 12 that he would not impose sanctions to put pressure on Russia because he wanted to achieve peace in Ukraine.

Union newsletter: Lowest salary of commune civil servants in 2025

|

Today's union newsletter includes: Lowest salary of commune civil servants in 2025; Self-managed boarding house team helps workers feel secure living and working...

Canada pays US aluminum and steel taxes

|

Canada responds to US President Donald Trump's global steel and aluminum tax rate of 25% with the corresponding tax rate targeting US goods worth 29.8 billion Canadian dollars.

Research on turning To Lich River into a place to store water during floods

|

Hanoi - The city assigned the Department of Planning and Architecture and related units to study turning To Lich River into a place to store water during flooding.

Quang Binh takes strong measures to reclaim land with slow-progressing projects

CÔNG SÁNG |

Quang Binh - The province resolutely reclaims land for projects that are behind schedule, violate financial obligations, and avoid wasting resources.

Difficulty accessing capital, social housing projects behind schedule

Thành Nhân |

Tien Giang - After more than 8 years of construction, the HQC Tan Huong social housing project (Tien Giang) has not yet been completed due to difficulties in accessing loans.

The VND2,160 billion project in Pleiku is behind schedule due to land clearance problems

Phan Tuấn |

Currently, there are 327 households with land and assets in the planning and clearance area that have not agreed to relocate because they think the compensation price is still low.