Urgent 600 billion project construction is slow due to lack of land

Đặng Tình |

Hoa Binh - The urgent project of Pheo - Che flood prevention dyke in the lower Da River with a total investment of nearly 600 billion is being slowly constructed due to lack of land.

The urgent project of Pheo - Che flood prevention dyke in the downstream of Da River, Ky Son District (now Ky Son Ward) has a total investment of more than 597 billion VND, invested by the Project Management Board of Agricultural Works of Hoa Binh Province. The Center for Land Fund Development of Hoa Binh City is responsible for site clearance.

The project is 6.2 km long (from Km0-Km6+200, Provincial Road 445); starting point at Pheo area, Ky Son ward; ending point at Che area, Hop Thinh commune, Hoa Binh city, adjacent to Hanoi city.

In March 2024, the above project was started, according to plan, the project will be completed by the end of 2025. However, up to now, the construction is still going slowly due to many problems in site clearance.

Du an phai thi cong kieu “xoi do” do thieu mat bang. Anh: Dang Tinh
The project had to be constructed in a "hands-off" manner due to lack of land. Photo: Dang Tinh

On November 27, according to the reporter's records, in some areas at the construction site, construction activities were still taking place with dozens of machines and workers mobilized.

However, many locations are under construction at a slow pace, and machinery has even stopped operating due to lack of space.

Talking to reporters, Mr. Dinh Van Hoan - project engineer (My Phong Company - construction unit) said: "The project is being constructed at a slow pace due to lack of land. Currently, machinery has been mobilized to the construction site, but there is not enough work to do. For the areas where the land has been handed over, the contractor has started construction."

Regarding the progress of the project, the representative of the Project Management Board of Agricultural Works of Hoa Binh province said that up to now, the Ngoi Mai bridge item has demolished the old bridge and reinforced it with steel sheet piles, reinforced concrete piles to reinforce the foundation, drilled bored piles, abutments and installed girder cranes. The contractor is constructing the two ends of the abutments, the breast wall and reinforcing the stream bed. This package has completed 45% of the volume.

Mot so hang muc dang duoc thi cong. Anh: Dang Tinh
Some items are under construction. Photo: Dang Tinh

For the dike line package and works on section 1 (from Km0-Km6+200), only 15% of the volume value has been completed.

Currently, the construction unit has filled the ground at the beginning of the route, constructed culvert No. 1 and additional culvert. Particularly, Ngoi Mong bridge, which is part of this project, has completed bored pile drilling, installed bridge girders and slabs, and is currently pouring concrete for the bridge deck beams, bridge abutments, and approach roads at both ends of the bridge.

Talking about the difficulties, the representative of this unit said that, up to now, the construction unit has officially received the handover of the site from the Land Fund Development Center of Hoa Binh City, mainly the part under construction is the advance payment from the local government and households.

On the local side, Ms. Nguyen Thi Oanh - a resident of Gieng hamlet, Hop Thanh commune - shared: "We really hope this project will be completed and put into use soon. Currently, the old road is degraded and dirty, making life very difficult for the people here."

Some images reporters recorded at the project:

a
The urgent project of Pheo - Che flood prevention dike in the lower Da River, Ky Son district (now Hoa Binh city) has the starting point at Pheo area, Ky Son ward; the ending point at Che area, Hop Thinh commune, Hoa Binh city, adjacent to Hanoi city. Photo: Google Maps
Du an thi cong i ach do thieu mat bang. Anh: Dang Tinh
Construction project is sluggish due to lack of land. Photo: Dang Tinh
Vat lieu xay dung ngon ngang... Anh: Dang Tinh
Construction materials are scattered. Photo: Dang Tinh
Nhung khu dat thuoc du an van chua the giai phong mat bang. Anh: Dang Tinh
The land plots of the project have not yet been cleared. Photo: Dang Tinh
a
Unfinished projects. Photo: Dang Tinh
a
In some areas where the land has been handed over, contractors are urgently constructing. Photo: Dang Tinh
Đặng Tình
TIN LIÊN QUAN

The 2,600 billion VND belt project connecting Ho Chi Minh City - Dong Nai is behind schedule

|

Dong Nai - 3 main packages in the component project 3 of Ho Chi Minh City's Ring Road 3 passing through Nhon Trach district are behind schedule, with only 55% of the construction site completed.

Businesses are about to be allowed to buy agricultural land for housing projects?

|

The Government proposes that investors agree to receive the right to use agricultural land, non-agricultural land that is not residential land, and other land in the same plot to do commercial housing projects.

Lang Nu residential area project is gradually being completed

|

The Lang Nu residential area project, Phuc Khanh commune, Bao Yen district, Lao Cai province is ensuring the right progress.

Quang Nam overcomes landslides, brings students back to class

|

Prolonged heavy rain has caused landslides and cracks in many traffic routes in the mountainous area of ​​Nam Tra My, Quang Nam, and a newly built school has also collapsed.

Ha Dinh social housing does not have a construction permit

|

The Hanoi Department of Construction has just informed that the NO1 Ha Dinh social housing project must be completed in the fourth quarter of 2024, but so far there has been no construction permit.

Union News: Who will be able to retire 10 years early in 2025

|

The main content of the union newsletter is: Maintain the union fee contribution rate at 2%; In which cases can one retire 10 years early from July 1, 2025?

Trump team considers direct negotiations with North Korea

|

The initial goal was said to be to re-establish basic interaction between the US and North Korea.

Close-up of a landslide next to an apartment project in Hanoi

|

Hanoi - Authorities have barricaded and banned vehicles from entering Mai Phuc Street (Long Bien District) for the past 2 days to fix the problem and clarify the cause.

The 2,600 billion VND belt project connecting Ho Chi Minh City - Dong Nai is behind schedule

HÀ ANH CHIẾN |

Dong Nai - 3 main packages in the component project 3 of Ho Chi Minh City's Ring Road 3 passing through Nhon Trach district are behind schedule, with only 55% of the construction site completed.

Businesses are about to be allowed to buy agricultural land for housing projects?

Thạch Lam |

The Government proposes that investors agree to receive the right to use agricultural land, non-agricultural land that is not residential land, and other land in the same plot to do commercial housing projects.

Lang Nu residential area project is gradually being completed

NHÓM PV |

The Lang Nu residential area project, Phuc Khanh commune, Bao Yen district, Lao Cai province is ensuring the right progress.