7-year health project not completed, Quang Binh proposes solution

CÔNG SÁNG |

Quang Binh - The Provincial People's Committee has requested units to complete the old part in the first quarter of 2025 so that the new part can be deployed for the 7-year unfinished health project.

Uncooperative contractor

The Quang Binh Province Health Education and Communication Center project started in 2017 with a total investment of 49.3 billion VND, but has not yet been completed.

At the meeting of the People's Committee of Quang Binh province on the socio-economic situation in January 2025, Director of the Department of Health Duong Thanh Binh said that the Department had many working sessions with the Project Management Board and Contractors to promote progress.

However, the contractor has not cooperated throughout the year. To remedy this situation, the Department of Health requested the contractor to return to work and complete the violation handling procedures to recover the project and implement the next steps.

The biggest difficulty at present is that some projects have been completed but payment documents have not been completed. The acceptance of the project has not been agreed upon by all parties, causing the progress to continue to stagnate.

Co moc um tum trong du an. Anh: Cong Sang
Grass grows wildly in the project. Photo: Cong Sang

Vice Chairman of Quang Binh Provincial People's Committee Phan Phong Phu said that the Provincial People's Committee has submitted to the Provincial People's Council additional adjustments to the project, increasing the budget. However, according to the principle, procedures must be completed with the old contractor, then the project can be continued in the next phase with the new contractor, but so far it has not been completed.

Faced with this situation, the Provincial People's Committee has requested the investor and the project management consultant to complete the old part in the first quarter of 2025 so that the new part can be implemented. If this is not possible, the Provincial People's Committee will use legal measures to ensure that the project is completed as planned.

Du an toa lac ngay tai phuong Dong Phu, TP Dong Hoi, tinh Quang Binh. Anh: Cong Sang
The project is located in Dong Phu ward, Dong Hoi city, Quang Binh province. Photo: Cong Sang

Additional capital from provincial budget

This project was approved by the People's Committee of Quang Binh province on October 30, 2015, located in Dong Phu ward, Dong Hoi city. The project has a scale of a 5-storey main building, fully arranged with working space and professional operations for officials and civil servants in the industry. The investor is the Quang Binh Department of Health, the project consultant is Hung Dung Construction and Trading Company Limited, while the Quang Binh Province Civil and Industrial Construction Investment Project Management Board is responsible for management.

The project was originally scheduled to be completed in the 2016-2020 period but was delayed and extended to 2022. However, since then, the project has remained “covered”, overgrown with grass, with no signs of construction. The rough construction has been completed, but many items such as floor tiling and exterior tiling have not been completed.

According to information from the People's Council of Quang Binh province, the main reason for the project's delay is that the implementation process encountered many objective and subjective problems. The project did not meet the disbursement schedule and had its capital withdrawn by the central government. Therefore, it is necessary to supplement the provincial budget and adjust the project implementation time so that the investor has a basis to complete the project, ensuring the approved project objectives and effectiveness.

CÔNG SÁNG
TIN LIÊN QUAN

Adjusting investment policy for health projects after 7 years is not yet completed

|

Quang Binh - The Provincial People's Council has just passed a resolution on adjusting the investment policy of the Health Education - Communication Center project.

There is a mechanism to remove project obstacles in Ho Chi Minh City, Da Nang, Khanh Hoa

|

The National Assembly has issued a Resolution on specific mechanisms and policies to remove obstacles in projects and land according to the inspection conclusions in Ho Chi Minh City, Da Nang and Khanh Hoa.

HCMC spends nearly VND17,000 billion to support officials on leave

|

Ho Chi Minh City will spend nearly VND17,000 billion to support policies for 6,291 cadres, civil servants, public employees and workers who quit their jobs when restructuring the administrative apparatus.

Hanoi finalizes the time to announce the third exam subject for grade 10

|

Hanoi - The Department of Education and Training has just informed about the announcement time of the third exam subject in the 10th grade exam.

Reckless prices for additional teaching services

|

Many thieves take advantage of the opportunity to invite teachers to hire support services to register for extra business households after Circular 29/2024/TT-BGDDT takes effect.

Sa Pa Secretary talks about children wearing ethnic costumes dancing TikTok

|

The head of Sa Pa Town Party Committee expressed his opinion that the issue of girls wearing traditional costumes dancing to TikTok music is attracting tourists.

There are misunderstandings about the coffee collection for social insurance contributions

|

Gia Lai Enterprises and workers need to sit together to dialogue, negotiate, and resolve problems related to social insurance payments.

18 leaders of Thai Nguyen Police Department ask for early retirement

|

Many leaders at the department level, district and officers of Thai Nguyen Provincial Police voluntarily applied for early retirement during the process of arranging and organizing the apparatus.

Loạt dự án chậm tiến độ ở Bắc Ninh: Dự án Đại học bất động

Vân Trường |

Bắc Ninh - Dự án Trường Đại học Quốc tế Bắc Hà tại thị trấn Lim (huyện Tiên Du) vẫn bất động sau gần 20 năm được giao đất.

Adjusting investment policy for health projects after 7 years is not yet completed

CÔNG SÁNG |

Quang Binh - The Provincial People's Council has just passed a resolution on adjusting the investment policy of the Health Education - Communication Center project.

Dự án hơn 49 tỉ đồng về sức khỏe ở Quảng Bình 7 năm chưa xong

CÔNG SÁNG |

Dự án Trung tâm Truyền thông - Giáo dục sức khỏe Quảng Bình được đầu tư 49,3 tỉ đồng, xây dựng từ năm 2017 nhưng đến nay vẫn chưa hoàn thành.