Road 70 unfinished for nearly 10 years, Hanoi sets milestone for traffic opening in Q4/2026

Minh Hạnh |

Hanoi sets a goal to complete site clearance, accelerate the progress of the 70 extended road project, and strive to open the entire route to traffic in the fourth quarter of 2026.

The project to build the road from To Huu street to extended road 70 (section from Van Phuc, Ha Dong ward to residential group 13, Dai Mo ward) started in 2016, with a total investment of more than 581 billion VND. However, after nearly 10 years of implementation, the project is still unfinished due to problems in site clearance.

The road was once expected to contribute to reducing traffic congestion in the area. However, currently, this area is often congested during peak hours, posing a potential risk of traffic unsafety.

Currently, Dai Mo Ward People's Committee - the new investor of the project - sets a goal to completely resolve existing problems, striving to open the entire route to traffic in the fourth quarter of 2026.

Đường 70 Hà Nội chậm tiến độ nhiều năm tiềm ẩn nguy cơ mất an toàn giao thông. Ảnh: Minh Hạnh
Hanoi Road 70 has been delayed for many years, posing a risk of traffic unsafety. Photo: Minh Hanh

Records of Lao Dong Newspaper reporters show that the beginning of the route connecting to road 70 (belonging to Ha Dong ward) to Louis City Dai Mo urban area, about 300m long, has a large number of vehicles passing through every day, especially during peak hours. However, this section has only been constructed half of the roadbed on the right side, the rest has not been deployed, and many "potholes" and dust have appeared, causing difficulties for traffic.

According to Mr. Nguyen Van Binh (resident of Dai Mo street), prolonged construction has seriously degraded the road. "On rainy days, the left side of the road is often flooded; on sunny days, dust flies everywhere whenever vehicles pass by. We have repeatedly proposed to speed up the progress but so far it has not been improved," Mr. Binh said.

Sau gần 10 năm dang dở, đường 70 Hà Nội đặt mục tiêu thông xe cuối năm 2026. Ảnh: Minh Hạnh
After nearly 10 years of being unfinished, Hanoi Road 70 aims to open to traffic by the end of 2026. Photo: Minh Hanh

Notably, the end section of the project passing through residential group 13, Dai Mo ward (adjacent to Dai Mo Urban Functional Area and B32 Thang Long residential area), near the Aeon Mall Ha Dong area, exists a "bottleneck" of about 200m long. During peak hours, this area often experiences prolonged congestion. Some sections have completed site clearance but have not been constructed, being occupied as car parking and garbage collection places, making the road even more narrow.

The unfinished construction situation makes the road dusty in sunny weather and muddy and slippery in rainy weather. Meanwhile, the area is densely populated but the infrastructure is not synchronized, posing many risks of traffic unsafety. In particular, the section passing through HH3. 1, HH3. 2 apartment buildings, Dai Mo urban functional area and B32 Thang Long residential area has a narrow and degraded road surface, with many "potholes", and many traffic accidents have occurred recently.

According to Mr. Hoang Minh Hai - Vice Chairman of Dai Mo Ward People's Committee, the main reason for the slow progress of the project is due to problems in site clearance.

The project has a total recovered area of 62,358.4m2, involving 178 households using agricultural land, 90 households using residential land and 4 organizations. To date, the locality has completed the recovery of the entire area of agricultural land (28,026.4m2). For 90 households with residential land, plans have been approved for 83 households with an area of 3,873.6m2; the remaining 7 households have not been approved for compensation, support and resettlement plans. In addition, there are about 5 graves at the end of the project that have not been relocated.

Hà Nội gỡ vướng mặt bằng, đặt mục tiêu thông xe đường 70 trong năm 2026. Ảnh: Minh Hạnh
Hanoi removes site obstacles, sets target to open road 70 to traffic in 2026. Photo: Minh Hanh

The main reasons are difficulties and obstacles related to land plot consolidation and block consolidation for eligible households; overlapping boundaries between adjacent projects; along with that, some households have not agreed with the compensation and support plan.

Representatives of Dai Mo Ward People's Committee said that this is a key project. After implementing the 2-level local government model, the ward was assigned to be the investor and is focusing on removing "bottlenecks", especially in site clearance and resettlement arrangement.

To ensure the rights of the people, the People's Committee of Dai Mo ward has proposed to the People's Committee of Hanoi City to allocate resettlement land fund in land plot DD1 and TT5-TT6 area, belonging to the Land Use Right Auction Area of Xuan Phuong ward for eligible households. Currently, the locality is coordinating with the People's Committee of Xuan Phuong ward to implement this work, and at the same time continue to mobilize households to hand over land.

To date, the project implementation volume has reached about 80%. However, the remaining 20% is the most difficult part, directly related to land clearance for residential land and tomb relocation.

The People's Committee of Dai Mo ward requests construction units to be ready with manpower and equipment to deploy immediately when there is clean ground. It is expected that resettlement and site clearance will be completed in the second quarter of 2026; striving to complete the project and put it into operation in the fourth quarter of 2026," Mr. Hoang Minh Hai said.

Minh Hạnh
RELATED NEWS

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

|

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.

Trillion-VND road in Hanoi has been technically opened to traffic but still has site clearance problems

|

Hanoi - Ring Road 2.5, Dam Hong section - National Highway 1A, technically opened to traffic 2 months ago, but so far site clearance has not been completed.

Hanoi technically opens Linh Dam lakeside road on April 15, 2026

|

Hanoi - Linh Dam lakeside road, will be technically opened to traffic on April 15, 2026, 45 days earlier than planned, contributing to reducing traffic pressure in the area.

Starting demolition of a 35-year-old apartment building in Hanoi

|

Hanoi - Functional forces begin clearing ground and demolishing a 35-year-old apartment building at 51 Huynh Thuc Khang.

US - Iran negotiations fail, many significant disagreements exist

|

Negotiations between the US and Iran in Pakistan have ended without any specific agreement.

7th Conference of the Presidium of the Central Committee of the Vietnam Fatherland Front, X term

|

On the morning of April 12, the Central Committee of the Vietnam Fatherland Front organized the 7th Conference of the Presidium of the Central Committee of the Vietnam Fatherland Front, term X to discuss and give opinions on some work contents.

Ambulance and pickup truck collide in a crossroads in Phu Tho

|

Phu Tho - On the evening of April 11, at the intersection of Nguyen Tat Thanh street and Truong Chinh street (Van Phu ward), a traffic accident occurred between an ambulance and a pickup truck.

Hormuz opens its door, 3 super ships carrying 6 million barrels of oil head to Asia

|

Oil flows through the Strait of Hormuz are stirring again as 3 supercarriers capable of carrying up to 6 million barrels leave the Persian Gulf on April 11.

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

Hữu Vũ |

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.

Trillion-VND road in Hanoi has been technically opened to traffic but still has site clearance problems

SÓNG HỮU |

Hanoi - Ring Road 2.5, Dam Hong section - National Highway 1A, technically opened to traffic 2 months ago, but so far site clearance has not been completed.

Hanoi technically opens Linh Dam lakeside road on April 15, 2026

Minh Hạnh |

Hanoi - Linh Dam lakeside road, will be technically opened to traffic on April 15, 2026, 45 days earlier than planned, contributing to reducing traffic pressure in the area.