Road connecting National Highway 32 with Noi Bai - Lao Cai expressway is untangled

Bảo Nguyên - Duy Dũng |

After many prolonged obstacles, the project of connecting National Highway 32 with the Noi Bai - Lao Cai expressway (IC14) has been untangled to accelerate construction.

In mid-April, at the construction site of the road project connecting National Highway 32 with the Noi Bai - Lao Cai expressway, the construction atmosphere was urgent. Excavators, rollers, and transport trucks operated continuously; hundreds of workers divided shifts to construct excavation, leveling, drainage culverts, and asphalt pavement at many sections.

At the bidding package from Km3+644 to Km5, An Viet Construction Investment Joint Stock Company has mobilized 15 locomotives and nearly 20 engineers and workers to continuously construct to compensate for progress.

Dự án đường nối Quốc lộ 32 với cao tốc Nội Bài - Lào Cai có tổng chiều dài 11,8 km, một số điểm còn vướng mặt bằng.
The road project connecting National Highway 32 with the Noi Bai - Lao Cai expressway has a total length of 11.8 km, with some points still facing site clearance issues. Photo: Huong Tra

According to Mr. Nguyen Van Thong, a technical officer of the unit, the current construction volume is about 70%, striving to complete the roadbed before May 30 and pave the road surface before June 30.

The project has a total length of 11.8km, of which the section passing through Trung Tam ward, Lao Cai province is 9.8km long, affecting 408 households, 69 cases have to relocate houses. Up to now, most of the site has been handed over, only a few cases are still problematic.

Mr. Nguyen The Nghia - Vice Chairman of the People's Committee of Trung Tam ward said that the locality is focusing on definitively handling 4 remaining households, including particularly difficult cases that need flexible support solutions instead of just applying administrative measures.

Vướng mắc giải phóng mặt bằng từng khiến dự án đường nối Quốc lộ 32 với cao tốc Nội Bài - Lào Cai chậm tiến độ nay đang được khơi thông.
Land clearance problems that once caused the project of connecting National Highway 32 with the Noi Bai - Lao Cai expressway to be delayed have been resolved. Photo: Huong Tra

One of the typical cases is the family of Ms. Luong Thi Nguyet - a disabled household in particularly difficult circumstances. The level 4 house is in the clearance area, but the family does not have sufficient financial conditions to build a new house, causing the handover of land to be prolonged.

Instead of letting obstacles continue, the local government has chosen a sharing approach: building houses of gratitude, mobilizing socialized resources, and calling on people and organizations to join hands to support labor days, materials, and help families relocate.

Các lực lượng đào móng, vận chuyển vật liệu và dựng nhà cho gia đình chị Lường Thị Nguyệt.
Forces dig foundations, transport materials and build houses for Ms. Luong Thi Nguyet's family. Photo: Huong Tra

On April 18, more than 100 people including local officials, unions and people of Nong residential group jointly supported leveling the ground, transporting materials, and starting the construction of a new house for the family. On the same day, the foundation was basically completed, and the ground was handed over to the contractor to continue construction.

Mr. Nguyen Phu Tham, a resident of group 15, Trung Tam ward, shared that people all hope the project will be completed soon to facilitate travel, shorten connection time with the lowland provinces, and expand trade opportunities and economic development.

Toàn tuyến bứt tốc thi công sau thời gian dài đình trệ
The entire route is accelerating construction after a long period of stagnation. Photo: Huong Tra

On April 22, in an exchange with Lao Dong Newspaper, Mr. Tran Viet Dung - Director of Investment and Construction Management Board No. 1 of Lao Cai province said that to date, the main route has handed over 11.5/11.8km of site; the roadbed has basically completed 8.8km; road surface paving has reached 2.5km; the total value of construction and installation has reached about 69.43%.

Faced with the pressure of progress, the investor is requesting contractors to increase manpower, machinery, and take advantage of favorable weather to accelerate construction.

Theo chủ đầu tư, một số hạng mục bổ sung các tuyến nhánh cũng sẽ hoàn thiện trong năm 2026.
According to the investor, some additional items for the branch lines will also be completed in 2026. Photo: Huong Tra

At the same time, closely coordinate with localities to thoroughly handle the remaining bottlenecks, especially at newly added branch roads. Units strive to complete the entire project in 2026.

Not only is it a traffic project, this route is expected to open an important connecting axis between National Highway 32 and the Noi Bai - Lao Cai expressway, contributing to reducing existing infrastructure load, promoting regional linkages and creating motivation for socio-economic development for the region.

Bảo Nguyên - Duy Dũng
RELATED NEWS

Removing site bottlenecks for a hundred-billion VND infrastructure project in Lao Cai to reach its target

|

Lao Cai - Removing site bottlenecks will help the Tan Lap urban area infrastructure project reach the finish line in 2026.

National Highway 32C upgrade project to be completed after 13 years of construction

|

Lao Cai - The National Highway 32C upgrade project is a key traffic project, of important significance in connecting the midland and mountainous areas of the North.

Joint venture of 3 contractors to construct 2 Noi Bai - Lao Cai expressway intersections

|

Phu Tho - The consortium of 3 contractors will construct the IC2 and IC5 intersections of the Noi Bai - Lao Cai expressway section through the old Vinh Phuc province.

The Inspection Committee of the Journalists Association highly appreciates the operating results of the Journalists Association of Lao Dong Newspaper

|

According to the annual inspection and supervision plan for 2026, on April 22, the Inspection Board of the Vietnam Journalists Association had a working session with the Journalists Association of Lao Dong Newspaper.

Many Meritorious Artists and People's Artists have quit their profession and become freelancers due to injuries

|

National Assembly Deputy Trinh Thuy Mui shared that many artists who are proficient in their profession, meritorious artists, and people's artists have quit their profession and gone to other freelance jobs.

Long Thanh Airport recruits 400 personnel for commercial operation at the end of 2026

|

Dong Nai - Airports Corporation of Vietnam (ACV) is recruiting 400 personnel to work at Long Thanh airport when this project goes into commercial operation at the end of 2026.

Russia proposes receiving Iranian uranium: The most difficult relocation problem in history

|

Russia proposes receiving Iran's high-enriched uranium to reduce the risk of nuclear escalation in the context of undiminished US-Iran tensions.

National Assembly deputies talk about films "Red Rain", "Little Wolfoo", MV "Northern Bling"

|

National Assembly deputies cited the films "Red Rain", "Little Wolfoo", MV "Northern Bling" and said that traditional culture can become an attractive creative material.

Removing site bottlenecks for a hundred-billion VND infrastructure project in Lao Cai to reach its target

Đinh Đại |

Lao Cai - Removing site bottlenecks will help the Tan Lap urban area infrastructure project reach the finish line in 2026.

National Highway 32C upgrade project to be completed after 13 years of construction

Duy Dũng |

Lao Cai - The National Highway 32C upgrade project is a key traffic project, of important significance in connecting the midland and mountainous areas of the North.

Joint venture of 3 contractors to construct 2 Noi Bai - Lao Cai expressway intersections

Tô Công |

Phu Tho - The consortium of 3 contractors will construct the IC2 and IC5 intersections of the Noi Bai - Lao Cai expressway section through the old Vinh Phuc province.