National Highway 32C upgrade project to be completed after 13 years of construction

Duy Dũng |

Lao Cai - The National Highway 32C upgrade project is a key traffic project, of important significance in connecting the midland and mountainous areas of the North.

The project to upgrade National Highway 32C, Hien Luong - Yen Bai City (old) section was started phase 1 in 2012, section from Km79 - Km87; Phase 2 started in 2021, section from Km87+150 - Km96+500, passing through Au Lau ward (Lao Cai province).

The project is invested by the Investment and Construction Project Management Board No. 1 of Lao Cai province, and the construction unit is Yen Bai Transport Construction Joint Stock Company.

During the implementation process, the project was constructed halfway, interrupted, and lasted for more than 13 years, with many times having to extend the implementation progress.

In the last days of the year, on the construction site of the National Highway 32C upgrade project, the construction atmosphere is urgent and bustling. On the construction site, machinery is operating bustlingly, vehicles carrying materials in and out in droves, the sound of excavators and levelers is loud.

Workers are divided into many groups and teams to complete each assigned item.

Cong nhan va may moc hoat dong nhon nhip tren cong truong.
Workers and machinery operate bustlingly on the construction site. Photo: Duy Dung

According to observations, the remaining section near Lao Cai General Hospital No. 1 has a total length of about 2 km, which has been expanded synchronously for both the road surface and sidewalks. Currently, construction teams are closely following each item, taking advantage of each period of time and favorable weather to accelerate progress.

Mr. Nguyen Quoc Thinh - Director of Yen Bai Transport Construction Joint Stock Company - shared: Up to this point, the project has basically completed the main part. The unit is focusing on completion work, such as: curbs, sidewalks and auxiliary items, ensuring requirements for aesthetics, quality and traffic safety.

The brothers determined that this is the key stage of the project. Taking advantage of favorable weather, teams organize overtime, shift division, and construction of 3-4 consecutive teams to compensate for progress, striving to complete the entire project before the 2026 Lunar New Year according to instructions," Mr. Thinh said.

 cac don vi dang tap trung cong tac hoan thien, nhu: bo via, le duong va cac hang muc phu tro
Units are focusing on completing auxiliary items. Photo: Duy Dung

Mr. Nong Van Hien - Deputy Head of Construction Investment Project Management Board No. 1 of Lao Cai province - said: From July 1, 2025, the local government at 2 levels will go into operation, the merger of agencies related to site clearance along with changes in guidelines and policies has caused this work to be interrupted, not meeting the progress requirements.

Up to now, the project has been removed from arising difficulties. This is the final stage of the project, so the units are focusing maximum resources to complete the remaining items, clean up the construction site, and prepare the necessary conditions for acceptance, handover and putting the project into operation".

Tuyen duong dang dan hoan thien, tao ket noi giao thong thuan tien cho khu vuc phuong Au Lau, tinh Lao Cai.
The project is gradually being completed, creating convenient traffic connections for the Au Lau ward area, Lao Cai province. Photo: Duy Dung

According to Mr. Hien, when the project to upgrade National Highway 32C section Hien Luong - old Yen Bai City is completed and put into operation, the road will become an important traffic axis, strengthening connectivity with the urban center and neighboring localities.

Wide road surface and synchronous infrastructure help traffic and transport goods more conveniently and safely, reducing pressure on existing networks, while creating a foundation to promote socio-economic development and urban space renovation in the area.

Duy Dũng
RELATED NEWS

Accelerating the progress of the 500 billion VND road project that has not been completed after 13 years of construction in Lao Cai

|

Lao Cai - The National Highway 32C upgrade project, the section from Hien Luong - Yen Bai City (old) is being accelerated to open the route before December 31, 2025.

Dien Bien exempts land rent for 13 years for rubber latex processing factory project

|

Dien Bien - The Provincial People's Committee has just decided to exempt land rent for the Dien Bien Rubber latex processing factory project in Thanh Nua commune.

Vieng Phu Market in 2026 ready for the New Year's session

|

Ninh Binh - Localities have developed plans, ready for the meeting on the first day of the new year of Vieng Phu market in 2026.

Land dossiers are much delayed, Lam Dong focuses on handling

|

Lam Dong - Many shortcomings in land dossier processing have been clearly pointed out, functional agencies are proposing solutions to overcome them, without causing trouble for people.

Em thua co ta" and how musical dramas dominate TikTok, YouTube

|

A series of videos making "content" from the songs Em thua co ta, Thiep hong sai ten, Hon bat cu ai... are dominating social media platforms.

Ukrainian Brigade loses 70% of personnel in clashes in Krasnoarmeysk

|

Nearly 70% of the troops of the Ukrainian Landing Brigade in Krasnoarmeysk have been eliminated from the battlefield in the fighting in the region.

Warm winter weather forecast lasts until mid-February

|

Increased cold air waves continue to pour down, forecasting harsh winter weather will last until mid-February.

Accelerating the progress of the 500 billion VND road project that has not been completed after 13 years of construction in Lao Cai

Văn Đức |

Lao Cai - The National Highway 32C upgrade project, the section from Hien Luong - Yen Bai City (old) is being accelerated to open the route before December 31, 2025.

Dien Bien exempts land rent for 13 years for rubber latex processing factory project

QUANG ĐẠT |

Dien Bien - The Provincial People's Committee has just decided to exempt land rent for the Dien Bien Rubber latex processing factory project in Thanh Nua commune.

Land clearance problems, National Highway 32C Upgrade Project has been under construction for 13 years and has not been completed

Bảo Nguyên - Văn Đức |

Lao Cai - The National Highway 32C upgrade project started in 2012 but has not yet completed site clearance.