Tan Son Nhat T3 Station is expected to be completed 2 months early Thousands of workers and engineers are rushing to complete the final items of Tan Son Nhat Airport T3 Station, the project has a total capital of nearly 11,000 billion VND.

This is the largest domestic station in the country, capacity of 20 million passengers/year, including three main items: Passenger Station, High -rise Garage combined with non -aviation services and viaduct system.
The station is built on an area of 112,500m² with a basement and four floating floors.The top floor is the flight procedure, VIP lounge, check-in counter is completed; The lower floor is the arrival station, the luggage area has basically been completed.
According to Mr. Le Khac Hong - Head of the Project Management Board, T3 Terminal is expected to inaugurate on April 19 (2 months earlier than the plan) under the direction of the Prime Minister, on the occasion of the 50th anniversary of the liberation of the South and reunification of the country.
Station T3 will test exploitation from 24.4 and officially operate from 5.5.2025, serving the entire domestic flight of Vietnam Airlines and Vietjet Air.The remaining firms continue to operate at T1 station.When put into operation, T3 increased the total capacity of Tan Son Nhat airport to 50 million passengers/year.
Road connecting Tran Quoc Hoan - Cong Hoa, a total capital of more than VND 4,800 billion, will clear the whole route on April 30.The route is longer than 4km, including 25-48m wide main roads with 6 lanes, two 3-4 lanes, one in front of T3 station and two underground tunnels.This route not only connects directly to T3 station but also contributes to reducing traffic pressure on Truong Son Street and the gateway area of Tan Son Nhat airport.
Long Thanh International Airport welcomes good news in Dong Nai, Long Thanh International Airport Project is being accelerated with nearly 10,000 engineers, workers and nearly 3,000 machinery and equipment operating day and night.
Package 4.6 - Construction of landing lines - expected to be completed before April 30, exceeding the progress of 3 months compared to the contract.
Package 6.12 - Including two routes connecting the airport will clear the technical vehicle No. 1 before April 30, completed and handed over to use the project before September 2, 2025.
Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board - said: "In 2025, we are determined to complete the basic construction of Long Thanh Airport Project phase 1".
The 1A component project of Ho Chi Minh City Ring Road 3, including Nhon Trach Bridge across the Dong Nai River, connecting Thu Duc City with Nhon Trach District (Dong Nai), is being accelerated to keep up with technical traffic on April 30.The bridge is 2.6km long, phase 1 has 4 motor lanes and 2 mixed lanes.This is an important project to help connect, shorten the travel time between Ho Chi Minh City, Dong Nai and neighboring provinces.
After clearing 3.4km from the first section from My Yen intersection (Long An) to Le Kha Phieu Street (Binh Chanh District, Ho Chi Minh City), Ben Luc - Long Thanh Expressway will continue to exploit an additional 18.8km from Le Kha Phieu Street to Nguyen Van Tao intersection (Nha Be district) on April 30.
Ben Luc - Long Thanh Expressway section through Dong Nai is 14km long, from Phuoc An intersection to Ring 3 Ho Chi Minh City, being completed to keep up to use on April 30.Previously, the 7km section from Highway 51 to Phuoc An was completed.It is expected that on April 30, more than 43km on the total length of 57km of the highway will be exploited, close to the goal of completing the entire route by 2026.
In Ba Ria - Vung Tau, component project 3 Bien Hoa - Vung Tau Expressway is 19.5km long, total investment capital of VND 5.190 billion, has been constructed nearly 90% of the volume.The route has 11 bridges, of which 7 bridges are constructing abutments, beams and concreting the bridge surface, the remaining 4 bridges enter the completion stage.Contractors mobilize maximum manpower, deploy 15 constructions to complete technical traffic on April 30.
The entire Bien Hoa - Vung Tau highway is nearly 54km long is expected to be completed and put into operation in 2026.

Dai Ngai 2 Bridge exceeded 6 months in the Mekong Delta and Dai Ngai 2 Bridge connecting Cu Lao Dung district (Soc Trang) with the Southern River Highway Hau, which is completing the final stage, expected to communicate with technical vehicles on April 30.
The project has a total length of more than 15km, an investment capital of nearly VND 8,000 billion, including two main bridges Dai Ngai 1 and 2, connecting Tra Vinh - Soc Trang, replacing traditional ferries, helping to shorten movement time, increase the capacity of freight.
Currently, the construction site has 25 constructions (14 bridges, 10 tips, 1 embankment), the atmosphere is urgent and bustling.The groups of workers focused on installing the sphere, completing the railing ...
ensuring the commitment progress.
Mr. Nguyen Duc Long - Project Commander - said that all resources were mobilized to the maximum, making 3 shifts continuously, exceeding the schedule of 6 months compared to the plan.According to Mr. Tran Van Nguyen - Chairman of Cu Lao Dung District People's Committee, Dai Ngai 2 Bridge not only resolves traffic but also creates a push for economic - agricultural development, attracting investment in high -tech agriculture and tourism.
On the occasion of April 30 this year, besides inauguration of many transport works, a series of large projects were also started. The project of renovating Xuyen Tam canal - The polluted canal route is nearly 9km long through Binh Thanh and Go Vap districts - will start the first package before April 30. The remaining two packages are expected to be deployed before 29.2025. With a total capital of more than 17,200 billion VND, this is the largest urban embellishment project in Ho Chi Minh City, the expectation of improving the environment, reducing flooding and improving the quality of life, completed by 2028. The project is more than 2,870ha, an investment capital of nearly 217,000 billion dong, is expected to serve 230,000 residents and welcome 8-9 million visitors/year, contributing to the development of the marine economy and tourism in Ho Chi Minh City. Ba Ria - Vung Tau plans to start the connection route to Bien Hoa - Vung Tau highway, divided into 3 sections. The first 6.7km long, connecting Highway 56 (Hoa Long commune) to the Vung Zhuhuo roundabout, expected to start construction on April 24, design 4 high -speed lanes and 2 emergency stop lanes. The remaining two sections include a striped part - coastal road (capital of VND 5,200 billion) and a section from coastal roads to the roundabout roundabout (capital of about VND 2,000 billion).